HomeMy WebLinkAbout04.a. Receive Quarterly Update on the Fiscal Year2024-25 Capital Improvement ProgramPage 1 of 18
Item 4.a.
prid'al-IFEC-S0
February 5, 2025
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE QUARTERLY UPDATE ON THE FISCAL YEAR 2024-25 CAPITAL
IMPROVEMENT PROGRAM
Attached is the new Capital Improvement Program quarterly report for Fiscal Year 2024-25 Quarter 2.
Staff will present and discuss the report.
Strategic Plan re -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 1 - Promote and uphold ethical behavior, openness, and accessibility, Strategy 3 - Maintain financial stability
and sustainability
GOAL SIX: Infrastructure Reliability
Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Quarterly Report, October to December 2024
February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 24 of 43
Page of i
&mL — —
maimivc-6DCENTRALSAN
CENTRAL CONTRA COSTA SANITARY DISTRICT
m} J
CAPITAL IMPROVEMENT PROGRAM - CIP
Capital Projects Quarterly Status Report — Q2
OCTOBER - DECEMBER 2024
.�. MW-t 1tIMli
L
Capital Projects
Division Manager
7 {
U96-
t.. -.- - Ts
:11111111111m,ft
Since 1946, Central Contra Costa Sanitary District (Central San) has provided safe
and reliable wastewater collection and treatment for residents in central Contra Costa
County. Today we serve over 481,600 residents and 3,000 businesses in 147 square
miles. Our services include supplying recycled water for parks and golf courses,
providing both commercial and residential recycled water pickup programs, operating
a household hazardous waste collection facility and running a sophisticated water
quality laboratory. Our core mission is to protect public health and the environment,
and our customers can count on us for vital services 24 hours a day, every day.
Central San's infrastructure includes a 1,540-mile collection system (including 18
pumping stations) and a wastewater treatment plant that have been well maintained,
but due to their advanced ages, now require renovation and upgrades. Already, the
equipment at the plant and in the system have been extended well beyond their
typical useful life due to responsible and robust maintenance practices. Some of the
collection system facilities are over 100 years old, and many are over 50 years. The
treatment plant facilities were primarily constructed in the 1970s and some are now at
the point where maintenance alone cannot maintain reliable performance. These
recommended extensive renovation and improvement projects will provide for
continued reliable operation. Central San funds an extensive Capital Improvement
Program (CIP) designed to prepare, maintain, optimize, and enhance Central San's
assets-, meet regulatory requirements, accommodate the community needs-, and
protect public health and the environment. Capital improvements are construction or
renovation activities that add value to Central San's fixed assets (pipelines, buildings,
facilities, and equipment) or significantly extend their useful life.
This report summarizes the CIP's progress and major highlights or accomplishments
in Fiscal Year (FY) 2024-25, Quarter 2 (October to December 2024).
B
C (A-B) fir
TOTAL
TOTAL
TOTAL
%
ESTIMATED
SPENT
REMAINING
�TOTALSPENT
PROGRAM PROJECT BUDGETS
TO DATE
TO DATE
TO DATE
Time Elanaed fn RMA
E
CURRENT
F
FISCAL YEAR
G (F%E)
H (F-E)
J(I-H)
APPROVED
TOTAL
TOTAL
%
KPI
EXPENDITURES
SPENT IIN
REMAINING
SPENT IN
�FY2024-25�
FY 2024.25
FY 2024-25
FY 2024-25
FY 2024-25
Collection System
�$
184,601,256
$ 56,971,844
$ 117,629,412
36%
$ 55,371,314
$ 11,516,903
$ 43,854,411
21%
29%
Treatment Plant
�$
517,754,331
$ 137,576,239
$ 380,178,094
27%
$ 60,891,113
$ 30,407,021
$ 30,484,092
50%
0%
General Improvements
�$
37,609,000
$ 16,786,191
$ 20,822,809
45%
$ 9,578,624
$ 3,530,815
$ 6,047,809
37% ::
13%
Recycled Water
�$
58,058,001
$ 41,886,108
$ 16,171,892
72%
$ 2,841,177
$ 790,283
$ 2,030,894
28%
22%
TOTAL
$
798,022,588
$ 263,220,332
$ 534,802,207
33%
$128,632,228
$ 46,245,022
$ 82,437,206
36% (_]
14%
CIB Contingency
$
2,350,000
$ 2,350,000
$ 2,350,000
$ 2,350,000
TOTAL with Contingency
$
800,372,588
$ 263,220,382
$ 537,152,207
$131,032,228
$ 46,245,022
$ 84,787,206
$140
$120
$100
$ 80
$ 60
540
$ 20
Budget to Actual Spending Trend FY 24-2S
Sewer Canstrucdon Fund
(in millions)
Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar25 Apr-25 May-25 Jun-25
--*--Budget —y— Target (90% of Budget less contingency) --s—Actuals —Projected
Capital Projects Quarterly Report I OCT-DEC 2024 Page 3 of 17
CE14SATRALCO
NITARYY DISTRICT
February 5, 2025 ECIPS Regular Committee Meeting Agenda Packet - Page 27 of 43
Active Major Projects by Phase
The CIP traditionally uses a Design -Bid -Build project delivery method in which an owner, Central San, first develops a
high-level scope for the needed improvements and then either plans and designs the project in-house or procures a
professional engineering firm to perform the services. For major infrastructure projects, engineering firms with specialty or
multi -discipline professionals including sub -consultants are commonly hired. Central San then solicits public bids for the
project and procures a general contractor to construct the project based on the contract documents.
Alternatively, Central San is working on a second method for project delivery that consists of a Design -Build approach.
This delivery method contracted with a single design -build firm in which the design, cost estimating, construction is
package under a final guaranteed maximum price (GMP) contract. This approach has two phases (final design and
construction) for consideration and approval.
Regardless of project delivery method, every project follows a consistent process of consecutive delivery stages as
presented in the model below:
Project Highlights - Collection System/Pumping Station
Pump Station Upgrade - Phase 2A
Protect Description
The project involves replacing corroded steel dry pits with
new wet wells at Fairview and Maltby Pumping Stations,
backup generators, instrumentation, pumps, valves, gates,
all piping, and concrete. It also includes rehabilitating or
replacing flow meters, updating major electrical controls per
Arc Flash Study recommendations, replacing and seismically
bracing worn control panels and electrical cabinets, and
improving safety devices such as gas detection systems and
eye wash stations.
Benefit
Safety of employees, meeting regulatory air standards,
energy efficiency, and reliability of critical infrastructure.
Project Budget: $ 38 million
Expected Completion Date: OCT 2025
Pump Station Upgrade - Phase 2B
Protect Description
This project aims to address aging infrastructure and
enhance reliability at the
Martinez Pumping Station.
Key components include
the replacement of critical
instrumentation, flow
lr
meters, and major
_
electrical components in
compliance with Arc Flash
Study recommendations.
Pumps, valves, gates, and
i
piping will be repaired or
F
- i
replaced, while concrete
A
surfaces will be repaired
�l ,+
or recoated. Additional
--
upgrades involve the
replacement and seismic
bracing of control panels
Figure 2 Crane support clips installation at
and electrical cabinets,
Martinez
along with the installation
of improved safety devices, including gas detection systems
and eye wash stations.
Protect Progress
• Poured generator pad, valve vault floor and walls at Maltby
and Fairview.
• Installed interior piping and new pumps at Maltby.
• Installed ductbanks and the majority of underground
electrical at Maltby.
• Installed structural steel for monorail at Fairview.
• Ongoing review and work on electrical equipment submittals
and procurement.
261% Marina
Figure 1 — Steel install for crane at Fairview
I
Lookahead
• Continue site
improvements including
electrical buildings, new
PG&E service
entrances, and flood
wall (Maltby).
• Install new
generators. Anticipated
completion by Fall 2025.
Benefit
Safety of employees, meeting regulatory air standards,
energy efficiency, and reliability of critical infrastructure
Protect Progress
• Electrical investigation
• Electrical equipment submittals
Lookahead
• Equipment procurement and installation
• Construct new service entrance
• Seal water piping work
Project Budget: $10.5 million
Expected Completion Date: DEC 2025
Collection System - Sewer Renovation Projects
Pleasant Hill Sewer Renovation - Phase 3
Protect Description
This project will replace or
rehabilitate 9,400 feet of small
_
diameter sewers located in
both public right-of-way and
+w
easements within the City of
Pleasant Hill. This project will
be focused on the Gregory
Gardens area and coordinated
Figure 3 Ph2 Open cut installation
with other utilities and paving
plans as a joint effort to rehabilitate the impacted community.
Protect Progress
• The project design was completed.
• The project was bid and awarded.
• Contract execution is in progress.
I nnkahcarl
• Contract should be executed in the next few weeks.
• Mobilization and Construction expected to begin in
February 2025.
Project Budget*: $ 0.65 million
Expected Completion Date: NOV 2025
*Construction budget to be included in Jan 2025
Buchanan Lift Stations Abandonment & Sewer
Proiect Description
This project will replace and
remove aging equipment in
poor condition at the South & -�
North Buchanan Lift Stations. Va! -
14 .
Major elements are:
k
• Abandon the South
Buchanan and North
Buchanan air ejector lift, 1. .
stations and the sewer
main under the
runway of Buchanan Figure 5 Buchanan Field South Lift Station
Field Airport.
• Reroute approximately 4,800 feet of sewer mains near
the Buchanan Field Airport.
Project Budget: $ 6.4 million
Expected Completion Date: DEC 2025
Lafayette Sewer Renovation - Phase 15
Project Description
This project will VW.
VW
replace or rehabilitate
T
_. �
up to approximately
13,000 feet of small
diameter sewers
y
located in both public
right-of-way and
easements within the
Figure 4 Open cut installation
City of Lafayette and unincorporated areas of Lafayette
Protect Progress
• The project design was completed.
• The project was bid and awarded.
• Contract execution is in progress.
Lookahead
• Contract should be executed in next few weeks.
• Mobilization and Construction expected to begin in
February 2025.
Project Budget*: $ 0.75 million
Expected Completion Date: NOV 2025
*Construction budget to be included in Jan 2025
Protect Progress
• Completed 100% Design.
• Ongoing coordination with Contra Costa County
for airport requirements and property rights.
• Public outreach in progress.
• NEPA CATEX determination in progress.
Lookahead:
• Obtain easement exchange and encroachment
permit conditions from County (expected
resolution in March 2025).
• Continue outreach to impacted businesses.
• Obtain approval of NEPA CATEX status from FAA.
• Bid Project.
Sewer Renovation - Pipe Installation Progress
This program conducts in-house design and construction management for projects for public sewer mains (6-
12" diameter pipelines) that are near the end of their useful life and in poor condition. The program budgets for
and has a goal to replace or renovate approximately 6-miles per year. Given that projects can range in scope,
complexity, and timeline, this goal is a total per year running average. During this quarter, the program has
completed approximately 0.1 miles as shown below. There was no significant progress in November and
December as the program focused on completing the final design.
Sewer Replacement Metric
(Goal of 6.0 miles)
Fiscal
Miles
Year
(3-year avg)
2020-21
7.1
2021-22
6.5
2022-23
5.9
2023-24
4.5
2024-25
TBD
Sewer replacement work is conducted in public or private streets and routinely in backyard sewer easements as shown
in the following pictures.
O
Project Highlight - Treatment Plant
Solids Handling Facility Improvements — Phase 1A
Protect Description
Major renovation of the furnace wet scrubber system,
dewatering equipment, cake pumps, seismic retrofitting,
furnace burner replacement, and electrical systems within
the Solids Conditioning Building at the treatment plant.
Benefit
Safety of employees, meeting regulatory air standards,
energy efficiency, and reliability of critical infrastructure.
Project Milestones
• Notice to Proceed with Construction was issued in
October of 2023 with an anticipated completion
date of October of 2027.
• Construction on each of the two furnaces are
limited to a 18-months duration.
Project Budget: $ 200 million
Expected Completion Date: OCT 2027
Protect Progress
• Infill Floor Slab was
poured on 1st Floor.
• Wet scrubber is being
assembled.
• Sludge blending tank
has been cleaned,
coated and a new lid
has been placed.
• Seismic buttress work
on South and East side
continued to make
progress.
Lookahead
Aeration Basins Diffuser Replacement - Phase 1
Project Description
Major renovation fft—
ate"
and upgrades to the
aeration basins
structures
and
aeration mechanical
systems. Work
includes seismic C
retrofitting, concrete��
repairs, QQ)C
improvements to the a--
process equipment, Figure 7— New Aeration Diffusers
upgraded diffusers,
piping, and electrical controls.
Benefit
Improve aeration system performance and optimize the
activated sludge process, which will improve nutrient
removal within the existing facilities.
Figure 6 New Cover for the sludge
blending tank
• Complete sludge blending tank cover including additional
work by April 2025.
• Continue concrete work for structural buttresses.
• Continue structural for interior seismic.
• Preparing for demolition of furnace #2 train.
• Continue working on Electrical submittals.
Project Milestones
• Notice to Proceed was issued in August 2023 and the
completion date is scheduled for December of 2025.
• Basin 1 renovation to be completed by November of
2024. Basin 2 by November of 2025.
Protect Progress
• Basins 1A and 1 B were completed on schedule. Controls
are being tweaked to optimize new diffusers.
• Electrical ductbanks were installed.
Lookahead
• Prepare for the next basin to start in April 2025.
• Continue making progress on electrical work.
Project Budget: $20.9 million
Expected Completion Date: DEC 2025
TOTAL
B
TOTAL
C (A -
TOTAL
%
ESTIMATED
SPENT
REMAINING
TOTALSPENT
PROJ NO
PROJECT TITLE
PROJECT BUDGETS
TO DATE
TO DATE
TO DATE
8443
LG Diameter Pipe line Inspection
$
7,492,000
$ 777,052
$ 6,714,948
10%
8457
Pump Station Upgrades - Ph. 2
$
39,000,000
$ 23,655,239
$ 14,344,761
62%
100007
39-Inch Main Trunk No. 1 Renovation
$
4,500,000
$ 529,561
$ 3,970,439
12%
100025
Lafayette Sewer Renovations, Ph. 15
$
750,000
$ 846,331
$ (96,331)
113%
100039
Collection System Sewer Renovation
$
59,403,000
$ 228,346
$ 59,174,654
0%
100041
Buchanan Lift Stations Abandonment
$
6,400,000
$ 669,214
$ 5,730,786
10%
100042
Pump Sation Upgrades, Phase 2B
$
10,531,000
$ 2,452,509
$ 8,078,491
23%
100050
CCTAA-Line Relocation
$
1,100,000
$ 1,009,192
$ 90,808
92%
100066
Martinez Urgent Force Main
s
3,962,000
$ 3,628,017
$ 333,983
92%
100068
Pleasant Hill Sewer Renovations Ph. 3
$
650,000
$ 632,870
$ 17,130
97%
I CS Major ProlecMs�
132,788,000
$ 34,428,331
$ 98,359,669
26%
&al FY 2024-23 CS AmJREEEE='!�
184,601,256
$ 66,971,S44
$ 117,629,412
36%
Project Phase
Bid & Award
Construction
Close-out
Not Applicable*
Total
0
0
E
F
G (F/E)
H (F-E)
J(I-H)
APPROVED
TOTAL
TOTAL
%
KPI
EXPENDITURES
SPENT IN
REMAINING
SPENT IN
FY
2024-25
FY 2024-25
FY 2024-25
FY
2624-25
FY 2024-25
$ 2,764,531 $
49,583 $
2,714,948
2% 0
48%
$ 10,212,799 $
4,718,038 $
5,494,761
46%
4%
$ 2,241,591 $
271,152 $
1,970,439
12%#
38%
110,120 $
206,451
-96,331
187%0
-137%
$ 18,219,937 $
45,283 $
18,174,654
0%0
50%
$ 2,586,049 $
205,263 $
2,380,786
8% 0
42%
$ 6,237,974 $
490,483 $
5,747,491
8% 0
42%
$ 596,497 $
495,689 $
90,808
85%
-35%
$ 3,195,267 $
2,961,294 $
333,983
90%0
-40%
$ 394,247 $
377,117 $
17,130
96%0
-46%
$ 46,549,012 $ 9,720,343 $ 36,828,669
26%1!llp' 24%
$ 55,371,314 $ 11,516,903 $ 43,654,411
21%_ff
29%
No. of Projects
Percent by No.
of Projects
6
16%
10
27%
4
11%
11
30%
6
16%
0
0%
0
0%
37
100%
Total Project
Value
$ 15,305,01
$ 124,455,256
$ 27,491,000
$ 194,601,256
Percent by Project
Value
8%
5%
5%
67%
15%
Capital Projects Quarterly Report I OCT-DEC 2024 Page 9 of 17
CE14SATRALCO
NITARYY DISTRICT
February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 33 of 43
Program Summary - Treatment Plant
s AL
The FY 2024-25 Treatment Plant (TP) Program prioritizes replacing aging equipment to prevent structural and mechanical
failures, reduce downtime, and control maintenance costs. It includes rehabilitating infrastructure to ensure reliable process
systems, meeting or exceeding employee safety standards, and responding to regulatory requirements for pending air
emissions regulations. Additionally, the program emphasizes increasing sustainability efforts and implementing energy -related
projects to support long-term environmental and operational goals.
There are 33 active projects in the Treatment Plant Program. All are multi -year efforts that range from the project planning
stage to nearing construction completion or yearly budgets for equipment or other needed functions at Central San. In all
cases, performance can be tracked at the yearly spending level.
In FY 2024-25, the emphasis is on 6 large projects which together account for $47.5 million or 78% of the total Treatment
Plant Budget for the year. Each major project budget is shown below.
Figure 9 displays the total budgets of active projects in each
phase of the Treatment Plant Program as of December 31,
2024. The number of currently active projects in each phase is
indicated in parentheses.
(11), Construction,
$248,527,058 (6), Close-out,
$28,410,000
loop, A� I Completed,
'r-.00�0
[2(, Bid & Jg7A (0(,Not
Award, a�4pplicable", $-
$6,500,000
(9), Panning,
(5), Design, $97,567,275
$136,75 ,
Figure 9 Total TP Program Budget for Active Projects in Each Phase
Project Phase No. of Projects Percent by No. Total Project Percent by Project
of Projects Value Value
Planning 9 27% $ 97,567,275 191%
Design 5 15% $ 136,750,000 26%
Bid & Award 2 6% $ 6,500,000 1%
Construction 11 33% $ 248,527,058 48%
Close-out 6 18% $ 28,410,000 5%
Completed 0 0% $ - 0%
Not Applicable* 0 0% $ - 01/6
Total 33 100% $ 517,754,333 1000/0
"Not Applicable" category is for the project that does not include construction
As of the end of the reporting period, nine (9) projects with a
total value of $97.6 million are in the planning phase, five
(5) project with a total value of $136.8 million is in the
design phase, two (2) projects with a total value of $6.5
million are in the bid & award phase, eleven (11) projects
with a total value of $248.5 million are in the construction
phase, and six (6) projects with a total value of $28.4 million
are in the close-out phase.
Program Summary - General Improvements
Ak
The General Improvements Program focuses on property, administrative buildings, information technologies, asset management,
and equipment and vehicle needs:
• Vehicle Replacement Program: Annual replacement of vehicles, with a 30% budget increase this year for electric
vehicles to meet new State Fleet Electrical regulations.
• Equipment Acquisition: Purchases of new equipment approved annually.
• Management Information Systems: Enhances IT operations with updates to the IT strategic plan and funding for future
technology needs, integrated into the Ten -Year CIP.
• General Projects: Includes property improvements, legal expenses, security system upgrades, and an Asset
Management Program designed to optimize asset lifecycles and ensure sustainable, reliable services.
There are 18 active projects in the General Improvements (GI) Program. All are multi -year efforts that range from the project
planning stage to nearing construction completion or yearly budgets for equipment or other needed functions at Central San. In all
cases, performance can be tracked at the yearly spending level.
In FY 2024-25, the emphasis is on 5 large projects which together account for $6.3 million or 66.2% of the total General
Improvements Budget for the year. Each major project budget is shown below.
Figure 10 displays the total budgets of active projects in each
phase of the General Improvements Program as of December
31, 2024. The number of currently active projects in each
phase is indicated in parentheses.
(a), aid &
Award, -1
(11), Construction,
$27,494,000
/ (1), Close-out,
$ 350,000
(0), Completed,
S-
(1), Not Applicable*,
$775,000
Figure 10 Total GI Program Budget for Active Projects in Each Phase
Project Phase No. of Projects Percent by No. Total Project Percent by Project
of Projects Value Value
Planning 4 22% $ 3,700,000 10%
Design 1 6% $ 5,290,000 14%
Bid & Award 4 0% $ - 01/.
Construction 11 61% $ 27,494,000 731Y
Close-out 1 6% $ 350,000 1%
Completed 0 0% $ - 0%
Nat Applicable* 1 6% $ 775,000 2%
Total 18 100% $ 37,609,000 100%
"Not Applicable" category is for the project that does not include construction
As of the end of the reporting period, four (4) projects with a
total value of $3.7 million are in the planning phase, one (1)
project with a total value of $5.3 million is in the design phase,
eleven (11) projects with a total value of $27.5 million are in
the construction phase, and one (1) project with a total value
of $0.4 million is in the close-out phase.
Program Summary - Recycled Water
The Recycled Water (RW) Program this fiscal year focuses on finalizing the construction and permitting of the Filter & Clearwell
Improvements — Phase 1A project to upgrade recycled water treatment and storage facilities. Additionally, Phase 1 B will
complete the design for electrical replacements and filter upgrades at the Filter Plant. Efforts will continue to attract new
customers in Zone 1, pursue federal and state funding for recycled water projects, and collaborate with regional water supply
agencies on alternatives like the Water Exchange Project with Contra Costa Water District and discussions with other districts
including EBMUD and SFPUC.
There are 5 active projects in the Recycled Water Program. All are multi -year efforts that range from the project planning stage
to nearing construction completion or yearly budgets for equipment or other needed functions at Central San. In all cases,
performance can be tracked at the yearly spending level.
In FY 2024-25, the emphasis is on 2 large projects which together account for $2.1 million or 72.4% of the total Recycled Water
Program Budget for the year. Each major project budget is shown below.
Figure 11 displays the total budgets of active projects in each
phase of the Recycled Water Program as of December 31,
2024. The number of currently active projects in each phase
is indicated in parentheses.
(2), Construction,
$41,533,000
(0),
Completed,
(0), Close-out,
(0), Bid & Award, (0), Not
Applicable*, $-
S- (1), Design, (2), Planning,
$14,950,000 $1,575,000
Figure 11 Total RW Program Budget for Active Projects in Each Phase
—Not Applicable" category is for the project that does not include construction
As of the end of the reporting period, two (2) projects with a
total value of $1.6 million are in the planning phase, one (1)
project with a total value of $14.9 million is in the design
phase, and two (2) projects with a total value of $41.5 million
are in the construction phase.
Page 14 of 18
Collection System Program
Status as of Dec-24
Pump Station Upgrade - Phase 2A
Scope
Project Information
The project involves replacing corroded steel dry pits with new wet wells at
Program Mgr.
Mark W
Project number 8457
Fairview and Maltby Pumping Stations, backup generators, instrumentation,
District Project Mgr.
Mark W
Priority Rank 3
pumps, valves, gates, all piping, and concrete. It also includes rehabilitating or
Construction Mgr.
Mark W
Phase Construction
replacing flow meters, updating major electrical controls per Arc Flash Study
recommendations, replacing and seismically bracing worn control panels and
Contractor
C. Overaa & Co
Concord Billing? No
electrical cabinets, and improving safety devices such as gas detection systems
Designer
HDR
%Cost Completion 59.2%
and eye wash stations.
• Poured generator pad, valve vault floor and walls at Maltby and Fairview
• Installed interior piping and new pumps at Maltby.
• Installed ductbanks and the majority of underground electrical at Maltby
• Installed structural steel for monorail at Fairview
• Ongoing review and work on electrical equipment submittals and procurement
Inception to Date Cost Details
Lookahead
• Continue site improvements including electrical buildings, new PG&E
service entrances, and flood wall (Maltby).
• Install new generators. Anticipated completion by Fall 2025.
Total
Budget to Date
Expenditure
% Spent
Phase
(Thru Current FY)
Future FY
Total Budget
TO DATE
Total Remaining
(Total Budget)
Time Elapsed
KPI
Planning
$ 150,000
$ 150,000
$ 38,826
$
111,174
25.9%
Design
$ 3,900,000
$ 3,900,000
$ 3,517,041
$
382,959
90.2%
Construction
$ 25,100,000
$ 8,850,000
$ 33,950,000
$ 20,099,372
$
13,850,628
59.2%
71.5%
40 12.3%
Total
$ 29,150,000
$ 8,850,000
$ 38,000,000
$ 23,655,239
$
14,344,761
62.3%
71.5%
40 9.3%
Contract Financials
Major
Original
Change Order
Current Contract
Total Invoiced
% Spent
Total# of Change
Contracts
Contract Amount
Amount
Amount
TO DATE
Remaining
(Total Contract)
Orders
TBD
Designer(s)
$ 3,154,561
$ 160,000
$ 3,314,561
$ 2,746,265
$
568,296
82.9%
6
Equipment
$ 207,718
$ -
$ 207,718
$ 207,718
$
-
100.0%
General Contractor
$ 27,608,204
$ -
$ 27,608,204
$ 15,294,628
$
12,313,576
55.4%
CM
$ 1,595,702
$ (10,072)
$ 1,585,630
$ 1,183,933
$
401,697
74.7%
2
Other
$
-
Total
$ 32,566,184
$ 149,928
$ 32,716,112
$ 19,432,543
$
13,283,568
59.4%
8
Major CO (over $200k) approved this period:
Safety Record
This Period
Total to Date
COxx - none
Near Miss
0
0
First Aid
0
0
Project Budget FY 2024-25 Performance
Property Damage
0
0
Total
0
0
Project
Budget -Planned
vs Actual
100%
80%
40% '..
20%
0% _
Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25
• • • • • Plan % Cum Spent % Cum
Project Schedule Status
Current
Milestones Plan Actual Approved Date Forecast Date Variance
Planning Start 11/1/2019 11/1/2019
Planning End
Design NTP
Design Completion
Construction NTP
Construction End
11/29/2022 11/29/2022 11/29/2022
10/31/2025 10/31/2025 10/31/2025
Site/Progress Photo
Areas of Concern/Risks Risk Type
-Electrical supply chain Schedule/Cost
-Generator load bank changes to Schedule/Cost
meet regulatory requirements
CENTRAL SAN
Capital Projects Quarterly Report I OCT - DEC 2024
February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 37 of 43
Page 13 of 17
Page 15 of 18
Collection System Program
Status as of Dec-24
Pump Station Upgrade - Phase 213
Scope
Project Information
To address aging infrastructure and enhance reliability at the Martinez Pumping
Program Mgr. Mark W
Project number 100042
Station. The key elements include replacing critical instrumentation and
District Project Mgr. Mark W
Priority Rank 3
rehabilitating/replacing flow meters. Pumps, valves, and gates will either be
reconditioned or replaced, and both piping and concrete will be repaired or
Construction Mgr. Mark W
Phase Construction
recoated. The project also entails replacing major electrical components and
Contractor C. Overaa & Co
Concord Billing? No
controls in accordance with Arc Flash Study recommendations, as well as replacing
Designer HDR
% Cost Completion 22.9%
worn control panels and seismically bracing control panels and electrical cabinets.
Safety devices will be improved through the replacement of gas detection systems
and eye wash stations.
Progress Summary
Lookahead
• Electrical Investigation
• Equipment procurement and installation.
• Electrical equipment submittals
• Construct new service entrance.
• Seal water piping work
Inception to Date Cost Details
Tota I
Budget to Date
Expenditure
% Spent
Phase (Thru Current FY)
Future FY
Total Budget TO DATE
Total Remaining (Total Budget)
Planning $ -
$
$
$
Design
$
$ - $ 42,465
$ (42,465)
Construction $ 8,200,000
$ 2,331,000
$ 10,531,000 $ 2,410,044
$ 8,120,956 22.9%
Time Elapsed KPI
62.0% 39.2%
Total
$
8,200,000
$ 2,331,000
$ 10,531,000
$ 2,452,509
$
8,078,491
23.3% 62.0% 38.8%
Contract Financials
Major
Original
Change Order
Current Contract
Total Invoiced
%Spent Total N of Change
Contracts
Contract Amount
Amount
Amount
TO DATE
Remaining
(Total Contract) Orders TBD
Designer(s)
$
326,000
$ 326,000
$ 151,794
$
174,206
46.6%
Equipment
$
-
$ -
$
-
General Contractor
$
7,912,000
$ -
$ 7,912,000
$ 1,715,000
$
6,197,000
21.7%
CM
$
500,000
$ 500,000
$ 88,391
$
411,609
17.7%
Other
$
-
$ -
$
-
Total $ 8,738,000 $
Major CO (over $200k) approved this period:
COxx- none
Project Budget FY 2024-25 Performance
$ 8,738,000 $ 1,955,185 $ 6,782,815
Project Budget -Planned vs Actual
100%
80 %
60 %
40%
20% ... .. .....
0%�
Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25
• • • • • Plan %Cum Spent %Cum
Project Schedule Status
22.4
Safety Record This Period Totalto Date
Near Miss 0 0
First Aid 0 0
Property Damage 0 0
Total 0 0
Site/Progress Photo
Milestones Plan Actual Appr Variance
Planning Start 11/1/2019 11/1/2019 Areas of Concern/Risks
Planning End -Electrical supply chain
Design NTP -PG&E coordination
Design Completion
Construction NTP 5/16/2023
Construction End 12/30/2025 12/30/2025
Risk Type
Schedule/Cost
Schedule
Capital Projects Quarterly Report I OCT - DEC 2024 Page 14 of 17
,tam ruary 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 38 of 43
Page 16 of 18
Treatment Plant Program
status as of
Dec-24
Solids Handling Facility Improvements — Phase 1A
Scope
Project Information
To rehabilitate and replace the sludge dewatering centrifuges, cake pumps, and furnace
Program Mgr.
Craig M
Project number
7348
air pollution control equipment. The project involves replacing the existing wet scrubber
District Project Mgr.
Will G
Priority Rank
1
with a new Venturi scrubber capable of bypassing the waste heat boiler, along with the
replacement of centrifuges and cake pumps. It also includes upgrading furnace burners
Construction Mgr.
MWH
Phase
Construction
and electrical and control systems to accommodate the new equipment. Additionally,
Contractor
Overaa
Concord Billing?
Yes
seismic upgrades will be implemented as part of Solids Phase 1B.
Designer
CDM Smith
% Cost Completion
28.2%
Progress Summary
• Infill Floor Slab was poured on 1st floor.
• Wet Scrubber is being assembled.
• Sludge Blend tank has been cleaned, coated and a new lid has been placed
• Seismic buttress work on South and East side continue to make progress.
Lookahead
• Complete sludge blending tank cover including additional work by April
2025.
• Continue concrete work for structural buttresses.
• Continue structural for interior seismic
• Preparing for demolition of furnace #2 train.
Continue workong on Electrical Submittals
Inception to Date Cost Details
Total
Budget to Date Expenditure %Spent
Phase (Thru Current FY) Future FY Total Budget TO DATE Total Remaining (Total Budget) Time Elapsed KPI
Planning $1,000,000 $ 1,000,000 $74,779 $927,886 7.5%
Design $15,000,000 $ 15,000,000 $20,271,312 ($5,241,917) * 135.1%
Construction $64,518,687 $119,445,000 $ 183,963,687 $51,860,103 $153,186,034 28.2% 29.2% 0 1.0%
Total $ 80,518,687 $ 119,445,000 $ 199,963,687 $ 72,206,194 $148,872,003 36.1% 29.2% -6.9%
*Overrun due to rebidding and redesign/repackaging Phase 1A and other solid related projects
Contract Financials
Total
Major Original Contract Change Order Current Contract Expenditure % Spent Total # of Change
Contracts Amount Amount Amount TO DATE Remaining (Total Contract) Orders TBD
Designer(s) $ 8,784,320 $ 5,214,162 $ 13,998,482 $ 9,655,348 $ 4,343,134 69.0%
Equipment $ 9,130,726 $ 3,223,814 $ 12,354,540 $ 4,384,895 $ 7,969,645 35.5%
General Contractor $ 126,288,000 $ 402,328 $ 126,690,328 $ 22,964,150 $ 103,726,178 18.1%
CM $ 457,206 $ 11,355,084 $ 11,812,290 $ 2,362,551 $ 9,449,739 20.0%
Others $ 26,435 $ 26,435 $ - $ 26,435 0.0%
Total $ 144,686,687 $ 20,195,389 $ 164,882,076 $ 39,366,944 $ 125,515,132 23.9%
Major Change Orders (over $200k) approved this period: Safety Record This Period Total to Date
None Near Miss 0 0
First Aid 0 0
Project Budget FY 2024-25 Performance Property Damage 0 0
Project Budget -Planned vs Actual Total 0 0
100% Site/Progress Photo
50%
0%
i
Jul-24 •Aug-24 Sep-24* Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 "�•—
• • • • • Plan %Cum —Spent %Cum
*Sep2024 Spent to Cum % includes an accrual for $2,816,949 which was reversed in October.
Project Schedule Status
ctual Approved Date Forecast Date Varim
Planning Start Areas of Concern/Risks Risk Type
Planning Completion • None
Design NTP
Design Completion
Construction NTP 7/1/2023 10/1/2023
Construction End 8/1/2025 10/30/2027 10/30/2027
Capital Pro'ects Quarter) Report I OCT - DEC 2024 Page 15 of 17
`moo• ruary 5, 2025 EOPS Regular pommitfee Meeting Agenda Packet -Page 39 of 43
Page 17 of 18
Treatment Plant Program Status as of Dec-24
Aeration Basins Diffuser Replacement - Phase 1
Scope Project Information
This project includes mechanical rehab, concrete repairs, and seismic upgrades to
Program Mgr.
Will G
Project number
100019
extend the life of aeration basins and diffuser systems. It involves replacing diffusers,
District Project Mgr.
Will G
Priority Rank
8
some air piping, and large underground valves, optimizing sludge processing by
reconfiguring unused channels, and upgrading controls for better air flow. Phase 1
Construction Mgr.
Will G
Phase
Construction
covers two aeration basins, with the remaining two in Phase 2. Seismic upgrades were
Contractor
Overaa
Concord Billing?
Yes
added in Phase 1.
Designer
HDR
% Cost Completion
58.4%
Progress Summary Lookahead
• Basin 1A and 1B were completed on schedule. Controls are being tweaked to • Prepare for the next basin to start in April 2025.
opitmize new diffusers. • Continue making progress on electrical.
-Electrical Ductbanks were installed.
Inception to Date Cost Details
Total
Budget to Date
Expenditure
% Spent
Phase
(Thru Current FY)
Future FY Total Budget
TO DATE
Total Remaining
(Total Budget)
Planning
$200,000
$ 200,000
$562,381
$ (362,381)
281.2%
Design
$3,300,000
$ 3,300,000
$2,014,461
$ 1,285,539
61.0%
Construction
$11,480,000
$5,899,000 $ 17,379,000
$10,145,357
$ 7,233,643
58.4%
Time Elapsed KPI
59.3% Q 0.9%
Total $ 14,980,000 $ 5,899,000 $ 20,879,000 $ 12,722,199 $ 8,156,801 60.9% 70.7% Q
Contract Financials
Total
Major
Original
Change Order
Current Contract
Expenditure
%Spent Total # of Change
Contracts
Contract Amount
Amount
Amount
TO DATE
Remaining
(Total Contract) Orders
Designer(s)
$ 1,111,000
$ 1,787,153
$
2,898,153
$ 2,094,018
$
804,135
72.3%
Equipment
$ 1,537,853
$
1,537,853
$ 75,000
$
1,462,853
4.9%
General Contractor
$ 12,723,245
$ 492,900
$
13,216,145
$ 6,716,704
$
6,499,441
50.8%
CM
$ 594,857
$ (2,547)
$
592,310
$ 309,170
$
283,139
52.2%
Others
$
-
$
-
Total $ 15,966,955 $ 2,277,505 $ 18,244,460 $ 9,194,892 $ 9,049,568
Major Change Orders (over $200k) approved this period:
COxx -
Project Budget FY 2024-25 Performance
Project Budget -Planned vs Actual
100 %
80%
60%
40%
20% ........ .....
0
-20%
Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25
• • • • • Plan % Cum Spent % Cum
Project Schedule Status
Milestones Approved Dat Variance
Planning Start 7/1/2022
Planning Completion
Design NTP
Design Completion
Construction NTP 8/28/2023
Construction End 12/24/2025 12/24/2025
21130
ruary 5, 2025 EOPS Regular ommi eetWaIngr�gegat�acket - ' ge �0 of 43
9.8 %
TBD
50.4%
Safety Record This Period Totalto Date
Near Miss 0 0
First Aid 0 0
Property Damage 0 0
Total 0 0
Site/Progress Photo
Areas of Concern/Risks Risk Type
• Unknown condition of existing Schedule/Cost
concrete and air leaks.
• Completing renovation prior to Schedule
wet weather (Oct 31st).
Page 16 of 17
Page 18 of 18
This page intentionally left blank.