Loading...
HomeMy WebLinkAbout04.a. Receive Quarterly Update on the Fiscal Year2024-25 Capital Improvement ProgramPage 1 of 18 Item 4.a. prid'al-IFEC-S0 February 5, 2025 TO: ENGINEERING AND OPERATIONS COMMITTEE FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER REVIEWED BY: GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS ROGER S. BAILEY, GENERAL MANAGER SUBJECT: RECEIVE QUARTERLY UPDATE ON THE FISCAL YEAR 2024-25 CAPITAL IMPROVEMENT PROGRAM Attached is the new Capital Improvement Program quarterly report for Fiscal Year 2024-25 Quarter 2. Staff will present and discuss the report. Strategic Plan re -In GOAL ONE: Customer and Community Strategy 1— Deliver high -quality customer service GOAL FOUR: Governance and Fiscal Responsibility Strategy 1 - Promote and uphold ethical behavior, openness, and accessibility, Strategy 3 - Maintain financial stability and sustainability GOAL SIX: Infrastructure Reliability Strategy 2 - Execute long-term capital renewal and replacement program ATTACHMENTS: 1. Quarterly Report, October to December 2024 February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 24 of 43 Page of i &mL — — maimivc-6DCENTRALSAN CENTRAL CONTRA COSTA SANITARY DISTRICT m} J CAPITAL IMPROVEMENT PROGRAM - CIP Capital Projects Quarterly Status Report — Q2 OCTOBER - DECEMBER 2024 .�. MW-t 1tIMli L Capital Projects Division Manager 7 { U96- t.. -.- - Ts :11111111111m,ft Since 1946, Central Contra Costa Sanitary District (Central San) has provided safe and reliable wastewater collection and treatment for residents in central Contra Costa County. Today we serve over 481,600 residents and 3,000 businesses in 147 square miles. Our services include supplying recycled water for parks and golf courses, providing both commercial and residential recycled water pickup programs, operating a household hazardous waste collection facility and running a sophisticated water quality laboratory. Our core mission is to protect public health and the environment, and our customers can count on us for vital services 24 hours a day, every day. Central San's infrastructure includes a 1,540-mile collection system (including 18 pumping stations) and a wastewater treatment plant that have been well maintained, but due to their advanced ages, now require renovation and upgrades. Already, the equipment at the plant and in the system have been extended well beyond their typical useful life due to responsible and robust maintenance practices. Some of the collection system facilities are over 100 years old, and many are over 50 years. The treatment plant facilities were primarily constructed in the 1970s and some are now at the point where maintenance alone cannot maintain reliable performance. These recommended extensive renovation and improvement projects will provide for continued reliable operation. Central San funds an extensive Capital Improvement Program (CIP) designed to prepare, maintain, optimize, and enhance Central San's assets-, meet regulatory requirements, accommodate the community needs-, and protect public health and the environment. Capital improvements are construction or renovation activities that add value to Central San's fixed assets (pipelines, buildings, facilities, and equipment) or significantly extend their useful life. This report summarizes the CIP's progress and major highlights or accomplishments in Fiscal Year (FY) 2024-25, Quarter 2 (October to December 2024). B C (A-B) fir TOTAL TOTAL TOTAL % ESTIMATED SPENT REMAINING �TOTALSPENT PROGRAM PROJECT BUDGETS TO DATE TO DATE TO DATE Time Elanaed fn RMA E CURRENT F FISCAL YEAR G (F%E) H (F-E) J(I-H) APPROVED TOTAL TOTAL % KPI EXPENDITURES SPENT IIN REMAINING SPENT IN �FY2024-25� FY 2024.25 FY 2024-25 FY 2024-25 FY 2024-25 Collection System �$ 184,601,256 $ 56,971,844 $ 117,629,412 36% $ 55,371,314 $ 11,516,903 $ 43,854,411 21% 29% Treatment Plant �$ 517,754,331 $ 137,576,239 $ 380,178,094 27% $ 60,891,113 $ 30,407,021 $ 30,484,092 50% 0% General Improvements �$ 37,609,000 $ 16,786,191 $ 20,822,809 45% $ 9,578,624 $ 3,530,815 $ 6,047,809 37% :: 13% Recycled Water �$ 58,058,001 $ 41,886,108 $ 16,171,892 72% $ 2,841,177 $ 790,283 $ 2,030,894 28% 22% TOTAL $ 798,022,588 $ 263,220,332 $ 534,802,207 33% $128,632,228 $ 46,245,022 $ 82,437,206 36% (_] 14% CIB Contingency $ 2,350,000 $ 2,350,000 $ 2,350,000 $ 2,350,000 TOTAL with Contingency $ 800,372,588 $ 263,220,382 $ 537,152,207 $131,032,228 $ 46,245,022 $ 84,787,206 $140 $120 $100 $ 80 $ 60 540 $ 20 Budget to Actual Spending Trend FY 24-2S Sewer Canstrucdon Fund (in millions) Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar25 Apr-25 May-25 Jun-25 --*--Budget —y— Target (90% of Budget less contingency) --s—Actuals —Projected Capital Projects Quarterly Report I OCT-DEC 2024 Page 3 of 17 CE14SATRALCO NITARYY DISTRICT February 5, 2025 ECIPS Regular Committee Meeting Agenda Packet - Page 27 of 43 Active Major Projects by Phase The CIP traditionally uses a Design -Bid -Build project delivery method in which an owner, Central San, first develops a high-level scope for the needed improvements and then either plans and designs the project in-house or procures a professional engineering firm to perform the services. For major infrastructure projects, engineering firms with specialty or multi -discipline professionals including sub -consultants are commonly hired. Central San then solicits public bids for the project and procures a general contractor to construct the project based on the contract documents. Alternatively, Central San is working on a second method for project delivery that consists of a Design -Build approach. This delivery method contracted with a single design -build firm in which the design, cost estimating, construction is package under a final guaranteed maximum price (GMP) contract. This approach has two phases (final design and construction) for consideration and approval. Regardless of project delivery method, every project follows a consistent process of consecutive delivery stages as presented in the model below: Project Highlights - Collection System/Pumping Station Pump Station Upgrade - Phase 2A Protect Description The project involves replacing corroded steel dry pits with new wet wells at Fairview and Maltby Pumping Stations, backup generators, instrumentation, pumps, valves, gates, all piping, and concrete. It also includes rehabilitating or replacing flow meters, updating major electrical controls per Arc Flash Study recommendations, replacing and seismically bracing worn control panels and electrical cabinets, and improving safety devices such as gas detection systems and eye wash stations. Benefit Safety of employees, meeting regulatory air standards, energy efficiency, and reliability of critical infrastructure. Project Budget: $ 38 million Expected Completion Date: OCT 2025 Pump Station Upgrade - Phase 2B Protect Description This project aims to address aging infrastructure and enhance reliability at the Martinez Pumping Station. Key components include the replacement of critical instrumentation, flow lr meters, and major _ electrical components in compliance with Arc Flash Study recommendations. Pumps, valves, gates, and i piping will be repaired or F - i replaced, while concrete A surfaces will be repaired �l ,+ or recoated. Additional -- upgrades involve the replacement and seismic bracing of control panels Figure 2 Crane support clips installation at and electrical cabinets, Martinez along with the installation of improved safety devices, including gas detection systems and eye wash stations. Protect Progress • Poured generator pad, valve vault floor and walls at Maltby and Fairview. • Installed interior piping and new pumps at Maltby. • Installed ductbanks and the majority of underground electrical at Maltby. • Installed structural steel for monorail at Fairview. • Ongoing review and work on electrical equipment submittals and procurement. 261% Marina Figure 1 — Steel install for crane at Fairview I Lookahead • Continue site improvements including electrical buildings, new PG&E service entrances, and flood wall (Maltby). • Install new generators. Anticipated completion by Fall 2025. Benefit Safety of employees, meeting regulatory air standards, energy efficiency, and reliability of critical infrastructure Protect Progress • Electrical investigation • Electrical equipment submittals Lookahead • Equipment procurement and installation • Construct new service entrance • Seal water piping work Project Budget: $10.5 million Expected Completion Date: DEC 2025 Collection System - Sewer Renovation Projects Pleasant Hill Sewer Renovation - Phase 3 Protect Description This project will replace or rehabilitate 9,400 feet of small _ diameter sewers located in both public right-of-way and +w easements within the City of Pleasant Hill. This project will be focused on the Gregory Gardens area and coordinated Figure 3 Ph2 Open cut installation with other utilities and paving plans as a joint effort to rehabilitate the impacted community. Protect Progress • The project design was completed. • The project was bid and awarded. • Contract execution is in progress. I nnkahcarl • Contract should be executed in the next few weeks. • Mobilization and Construction expected to begin in February 2025. Project Budget*: $ 0.65 million Expected Completion Date: NOV 2025 *Construction budget to be included in Jan 2025 Buchanan Lift Stations Abandonment & Sewer Proiect Description This project will replace and remove aging equipment in poor condition at the South & -� North Buchanan Lift Stations. Va! - 14 . Major elements are: k • Abandon the South Buchanan and North Buchanan air ejector lift, 1. . stations and the sewer main under the runway of Buchanan Figure 5 Buchanan Field South Lift Station Field Airport. • Reroute approximately 4,800 feet of sewer mains near the Buchanan Field Airport. Project Budget: $ 6.4 million Expected Completion Date: DEC 2025 Lafayette Sewer Renovation - Phase 15 Project Description This project will VW. VW replace or rehabilitate T _. � up to approximately 13,000 feet of small diameter sewers y located in both public right-of-way and easements within the Figure 4 Open cut installation City of Lafayette and unincorporated areas of Lafayette Protect Progress • The project design was completed. • The project was bid and awarded. • Contract execution is in progress. Lookahead • Contract should be executed in next few weeks. • Mobilization and Construction expected to begin in February 2025. Project Budget*: $ 0.75 million Expected Completion Date: NOV 2025 *Construction budget to be included in Jan 2025 Protect Progress • Completed 100% Design. • Ongoing coordination with Contra Costa County for airport requirements and property rights. • Public outreach in progress. • NEPA CATEX determination in progress. Lookahead: • Obtain easement exchange and encroachment permit conditions from County (expected resolution in March 2025). • Continue outreach to impacted businesses. • Obtain approval of NEPA CATEX status from FAA. • Bid Project. Sewer Renovation - Pipe Installation Progress This program conducts in-house design and construction management for projects for public sewer mains (6- 12" diameter pipelines) that are near the end of their useful life and in poor condition. The program budgets for and has a goal to replace or renovate approximately 6-miles per year. Given that projects can range in scope, complexity, and timeline, this goal is a total per year running average. During this quarter, the program has completed approximately 0.1 miles as shown below. There was no significant progress in November and December as the program focused on completing the final design. Sewer Replacement Metric (Goal of 6.0 miles) Fiscal Miles Year (3-year avg) 2020-21 7.1 2021-22 6.5 2022-23 5.9 2023-24 4.5 2024-25 TBD Sewer replacement work is conducted in public or private streets and routinely in backyard sewer easements as shown in the following pictures. O Project Highlight - Treatment Plant Solids Handling Facility Improvements — Phase 1A Protect Description Major renovation of the furnace wet scrubber system, dewatering equipment, cake pumps, seismic retrofitting, furnace burner replacement, and electrical systems within the Solids Conditioning Building at the treatment plant. Benefit Safety of employees, meeting regulatory air standards, energy efficiency, and reliability of critical infrastructure. Project Milestones • Notice to Proceed with Construction was issued in October of 2023 with an anticipated completion date of October of 2027. • Construction on each of the two furnaces are limited to a 18-months duration. Project Budget: $ 200 million Expected Completion Date: OCT 2027 Protect Progress • Infill Floor Slab was poured on 1st Floor. • Wet scrubber is being assembled. • Sludge blending tank has been cleaned, coated and a new lid has been placed. • Seismic buttress work on South and East side continued to make progress. Lookahead Aeration Basins Diffuser Replacement - Phase 1 Project Description Major renovation fft— ate" and upgrades to the aeration basins structures and aeration mechanical systems. Work includes seismic C retrofitting, concrete�� repairs, QQ)C improvements to the a-- process equipment, Figure 7— New Aeration Diffusers upgraded diffusers, piping, and electrical controls. Benefit Improve aeration system performance and optimize the activated sludge process, which will improve nutrient removal within the existing facilities. Figure 6 New Cover for the sludge blending tank • Complete sludge blending tank cover including additional work by April 2025. • Continue concrete work for structural buttresses. • Continue structural for interior seismic. • Preparing for demolition of furnace #2 train. • Continue working on Electrical submittals. Project Milestones • Notice to Proceed was issued in August 2023 and the completion date is scheduled for December of 2025. • Basin 1 renovation to be completed by November of 2024. Basin 2 by November of 2025. Protect Progress • Basins 1A and 1 B were completed on schedule. Controls are being tweaked to optimize new diffusers. • Electrical ductbanks were installed. Lookahead • Prepare for the next basin to start in April 2025. • Continue making progress on electrical work. Project Budget: $20.9 million Expected Completion Date: DEC 2025 TOTAL B TOTAL C (A - TOTAL % ESTIMATED SPENT REMAINING TOTALSPENT PROJ NO PROJECT TITLE PROJECT BUDGETS TO DATE TO DATE TO DATE 8443 LG Diameter Pipe line Inspection $ 7,492,000 $ 777,052 $ 6,714,948 10% 8457 Pump Station Upgrades - Ph. 2 $ 39,000,000 $ 23,655,239 $ 14,344,761 62% 100007 39-Inch Main Trunk No. 1 Renovation $ 4,500,000 $ 529,561 $ 3,970,439 12% 100025 Lafayette Sewer Renovations, Ph. 15 $ 750,000 $ 846,331 $ (96,331) 113% 100039 Collection System Sewer Renovation $ 59,403,000 $ 228,346 $ 59,174,654 0% 100041 Buchanan Lift Stations Abandonment $ 6,400,000 $ 669,214 $ 5,730,786 10% 100042 Pump Sation Upgrades, Phase 2B $ 10,531,000 $ 2,452,509 $ 8,078,491 23% 100050 CCTAA-Line Relocation $ 1,100,000 $ 1,009,192 $ 90,808 92% 100066 Martinez Urgent Force Main s 3,962,000 $ 3,628,017 $ 333,983 92% 100068 Pleasant Hill Sewer Renovations Ph. 3 $ 650,000 $ 632,870 $ 17,130 97% I CS Major ProlecMs� 132,788,000 $ 34,428,331 $ 98,359,669 26% &al FY 2024-23 CS AmJREEEE='!� 184,601,256 $ 66,971,S44 $ 117,629,412 36% Project Phase Bid & Award Construction Close-out Not Applicable* Total 0 0 E F G (F/E) H (F-E) J(I-H) APPROVED TOTAL TOTAL % KPI EXPENDITURES SPENT IN REMAINING SPENT IN FY 2024-25 FY 2024-25 FY 2024-25 FY 2624-25 FY 2024-25 $ 2,764,531 $ 49,583 $ 2,714,948 2% 0 48% $ 10,212,799 $ 4,718,038 $ 5,494,761 46% 4% $ 2,241,591 $ 271,152 $ 1,970,439 12%# 38% 110,120 $ 206,451 -96,331 187%0 -137% $ 18,219,937 $ 45,283 $ 18,174,654 0%0 50% $ 2,586,049 $ 205,263 $ 2,380,786 8% 0 42% $ 6,237,974 $ 490,483 $ 5,747,491 8% 0 42% $ 596,497 $ 495,689 $ 90,808 85% -35% $ 3,195,267 $ 2,961,294 $ 333,983 90%0 -40% $ 394,247 $ 377,117 $ 17,130 96%0 -46% $ 46,549,012 $ 9,720,343 $ 36,828,669 26%1!llp' 24% $ 55,371,314 $ 11,516,903 $ 43,654,411 21%_ff 29% No. of Projects Percent by No. of Projects 6 16% 10 27% 4 11% 11 30% 6 16% 0 0% 0 0% 37 100% Total Project Value $ 15,305,01 $ 124,455,256 $ 27,491,000 $ 194,601,256 Percent by Project Value 8% 5% 5% 67% 15% Capital Projects Quarterly Report I OCT-DEC 2024 Page 9 of 17 CE14SATRALCO NITARYY DISTRICT February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 33 of 43 Program Summary - Treatment Plant s AL The FY 2024-25 Treatment Plant (TP) Program prioritizes replacing aging equipment to prevent structural and mechanical failures, reduce downtime, and control maintenance costs. It includes rehabilitating infrastructure to ensure reliable process systems, meeting or exceeding employee safety standards, and responding to regulatory requirements for pending air emissions regulations. Additionally, the program emphasizes increasing sustainability efforts and implementing energy -related projects to support long-term environmental and operational goals. There are 33 active projects in the Treatment Plant Program. All are multi -year efforts that range from the project planning stage to nearing construction completion or yearly budgets for equipment or other needed functions at Central San. In all cases, performance can be tracked at the yearly spending level. In FY 2024-25, the emphasis is on 6 large projects which together account for $47.5 million or 78% of the total Treatment Plant Budget for the year. Each major project budget is shown below. Figure 9 displays the total budgets of active projects in each phase of the Treatment Plant Program as of December 31, 2024. The number of currently active projects in each phase is indicated in parentheses. (11), Construction, $248,527,058 (6), Close-out, $28,410,000 loop, A� I Completed, 'r-.00�0 [2(, Bid & Jg7A (0(,Not Award, a�4pplicable", $- $6,500,000 (9), Panning, (5), Design, $97,567,275 $136,75 , Figure 9 Total TP Program Budget for Active Projects in Each Phase Project Phase No. of Projects Percent by No. Total Project Percent by Project of Projects Value Value Planning 9 27% $ 97,567,275 191% Design 5 15% $ 136,750,000 26% Bid & Award 2 6% $ 6,500,000 1% Construction 11 33% $ 248,527,058 48% Close-out 6 18% $ 28,410,000 5% Completed 0 0% $ - 0% Not Applicable* 0 0% $ - 01/6 Total 33 100% $ 517,754,333 1000/0 "Not Applicable" category is for the project that does not include construction As of the end of the reporting period, nine (9) projects with a total value of $97.6 million are in the planning phase, five (5) project with a total value of $136.8 million is in the design phase, two (2) projects with a total value of $6.5 million are in the bid & award phase, eleven (11) projects with a total value of $248.5 million are in the construction phase, and six (6) projects with a total value of $28.4 million are in the close-out phase. Program Summary - General Improvements Ak The General Improvements Program focuses on property, administrative buildings, information technologies, asset management, and equipment and vehicle needs: • Vehicle Replacement Program: Annual replacement of vehicles, with a 30% budget increase this year for electric vehicles to meet new State Fleet Electrical regulations. • Equipment Acquisition: Purchases of new equipment approved annually. • Management Information Systems: Enhances IT operations with updates to the IT strategic plan and funding for future technology needs, integrated into the Ten -Year CIP. • General Projects: Includes property improvements, legal expenses, security system upgrades, and an Asset Management Program designed to optimize asset lifecycles and ensure sustainable, reliable services. There are 18 active projects in the General Improvements (GI) Program. All are multi -year efforts that range from the project planning stage to nearing construction completion or yearly budgets for equipment or other needed functions at Central San. In all cases, performance can be tracked at the yearly spending level. In FY 2024-25, the emphasis is on 5 large projects which together account for $6.3 million or 66.2% of the total General Improvements Budget for the year. Each major project budget is shown below. Figure 10 displays the total budgets of active projects in each phase of the General Improvements Program as of December 31, 2024. The number of currently active projects in each phase is indicated in parentheses. (a), aid & Award, -1 (11), Construction, $27,494,000 / (1), Close-out, $ 350,000 (0), Completed, S- (1), Not Applicable*, $775,000 Figure 10 Total GI Program Budget for Active Projects in Each Phase Project Phase No. of Projects Percent by No. Total Project Percent by Project of Projects Value Value Planning 4 22% $ 3,700,000 10% Design 1 6% $ 5,290,000 14% Bid & Award 4 0% $ - 01/. Construction 11 61% $ 27,494,000 731Y Close-out 1 6% $ 350,000 1% Completed 0 0% $ - 0% Nat Applicable* 1 6% $ 775,000 2% Total 18 100% $ 37,609,000 100% "Not Applicable" category is for the project that does not include construction As of the end of the reporting period, four (4) projects with a total value of $3.7 million are in the planning phase, one (1) project with a total value of $5.3 million is in the design phase, eleven (11) projects with a total value of $27.5 million are in the construction phase, and one (1) project with a total value of $0.4 million is in the close-out phase. Program Summary - Recycled Water The Recycled Water (RW) Program this fiscal year focuses on finalizing the construction and permitting of the Filter & Clearwell Improvements — Phase 1A project to upgrade recycled water treatment and storage facilities. Additionally, Phase 1 B will complete the design for electrical replacements and filter upgrades at the Filter Plant. Efforts will continue to attract new customers in Zone 1, pursue federal and state funding for recycled water projects, and collaborate with regional water supply agencies on alternatives like the Water Exchange Project with Contra Costa Water District and discussions with other districts including EBMUD and SFPUC. There are 5 active projects in the Recycled Water Program. All are multi -year efforts that range from the project planning stage to nearing construction completion or yearly budgets for equipment or other needed functions at Central San. In all cases, performance can be tracked at the yearly spending level. In FY 2024-25, the emphasis is on 2 large projects which together account for $2.1 million or 72.4% of the total Recycled Water Program Budget for the year. Each major project budget is shown below. Figure 11 displays the total budgets of active projects in each phase of the Recycled Water Program as of December 31, 2024. The number of currently active projects in each phase is indicated in parentheses. (2), Construction, $41,533,000 (0), Completed, (0), Close-out, (0), Bid & Award, (0), Not Applicable*, $- S- (1), Design, (2), Planning, $14,950,000 $1,575,000 Figure 11 Total RW Program Budget for Active Projects in Each Phase —Not Applicable" category is for the project that does not include construction As of the end of the reporting period, two (2) projects with a total value of $1.6 million are in the planning phase, one (1) project with a total value of $14.9 million is in the design phase, and two (2) projects with a total value of $41.5 million are in the construction phase. Page 14 of 18 Collection System Program Status as of Dec-24 Pump Station Upgrade - Phase 2A Scope Project Information The project involves replacing corroded steel dry pits with new wet wells at Program Mgr. Mark W Project number 8457 Fairview and Maltby Pumping Stations, backup generators, instrumentation, District Project Mgr. Mark W Priority Rank 3 pumps, valves, gates, all piping, and concrete. It also includes rehabilitating or Construction Mgr. Mark W Phase Construction replacing flow meters, updating major electrical controls per Arc Flash Study recommendations, replacing and seismically bracing worn control panels and Contractor C. Overaa & Co Concord Billing? No electrical cabinets, and improving safety devices such as gas detection systems Designer HDR %Cost Completion 59.2% and eye wash stations. • Poured generator pad, valve vault floor and walls at Maltby and Fairview • Installed interior piping and new pumps at Maltby. • Installed ductbanks and the majority of underground electrical at Maltby • Installed structural steel for monorail at Fairview • Ongoing review and work on electrical equipment submittals and procurement Inception to Date Cost Details Lookahead • Continue site improvements including electrical buildings, new PG&E service entrances, and flood wall (Maltby). • Install new generators. Anticipated completion by Fall 2025. Total Budget to Date Expenditure % Spent Phase (Thru Current FY) Future FY Total Budget TO DATE Total Remaining (Total Budget) Time Elapsed KPI Planning $ 150,000 $ 150,000 $ 38,826 $ 111,174 25.9% Design $ 3,900,000 $ 3,900,000 $ 3,517,041 $ 382,959 90.2% Construction $ 25,100,000 $ 8,850,000 $ 33,950,000 $ 20,099,372 $ 13,850,628 59.2% 71.5% 40 12.3% Total $ 29,150,000 $ 8,850,000 $ 38,000,000 $ 23,655,239 $ 14,344,761 62.3% 71.5% 40 9.3% Contract Financials Major Original Change Order Current Contract Total Invoiced % Spent Total# of Change Contracts Contract Amount Amount Amount TO DATE Remaining (Total Contract) Orders TBD Designer(s) $ 3,154,561 $ 160,000 $ 3,314,561 $ 2,746,265 $ 568,296 82.9% 6 Equipment $ 207,718 $ - $ 207,718 $ 207,718 $ - 100.0% General Contractor $ 27,608,204 $ - $ 27,608,204 $ 15,294,628 $ 12,313,576 55.4% CM $ 1,595,702 $ (10,072) $ 1,585,630 $ 1,183,933 $ 401,697 74.7% 2 Other $ - Total $ 32,566,184 $ 149,928 $ 32,716,112 $ 19,432,543 $ 13,283,568 59.4% 8 Major CO (over $200k) approved this period: Safety Record This Period Total to Date COxx - none Near Miss 0 0 First Aid 0 0 Project Budget FY 2024-25 Performance Property Damage 0 0 Total 0 0 Project Budget -Planned vs Actual 100% 80% 40% '.. 20% 0% _ Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 • • • • • Plan % Cum Spent % Cum Project Schedule Status Current Milestones Plan Actual Approved Date Forecast Date Variance Planning Start 11/1/2019 11/1/2019 Planning End Design NTP Design Completion Construction NTP Construction End 11/29/2022 11/29/2022 11/29/2022 10/31/2025 10/31/2025 10/31/2025 Site/Progress Photo Areas of Concern/Risks Risk Type -Electrical supply chain Schedule/Cost -Generator load bank changes to Schedule/Cost meet regulatory requirements CENTRAL SAN Capital Projects Quarterly Report I OCT - DEC 2024 February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 37 of 43 Page 13 of 17 Page 15 of 18 Collection System Program Status as of Dec-24 Pump Station Upgrade - Phase 213 Scope Project Information To address aging infrastructure and enhance reliability at the Martinez Pumping Program Mgr. Mark W Project number 100042 Station. The key elements include replacing critical instrumentation and District Project Mgr. Mark W Priority Rank 3 rehabilitating/replacing flow meters. Pumps, valves, and gates will either be reconditioned or replaced, and both piping and concrete will be repaired or Construction Mgr. Mark W Phase Construction recoated. The project also entails replacing major electrical components and Contractor C. Overaa & Co Concord Billing? No controls in accordance with Arc Flash Study recommendations, as well as replacing Designer HDR % Cost Completion 22.9% worn control panels and seismically bracing control panels and electrical cabinets. Safety devices will be improved through the replacement of gas detection systems and eye wash stations. Progress Summary Lookahead • Electrical Investigation • Equipment procurement and installation. • Electrical equipment submittals • Construct new service entrance. • Seal water piping work Inception to Date Cost Details Tota I Budget to Date Expenditure % Spent Phase (Thru Current FY) Future FY Total Budget TO DATE Total Remaining (Total Budget) Planning $ - $ $ $ Design $ $ - $ 42,465 $ (42,465) Construction $ 8,200,000 $ 2,331,000 $ 10,531,000 $ 2,410,044 $ 8,120,956 22.9% Time Elapsed KPI 62.0% 39.2% Total $ 8,200,000 $ 2,331,000 $ 10,531,000 $ 2,452,509 $ 8,078,491 23.3% 62.0% 38.8% Contract Financials Major Original Change Order Current Contract Total Invoiced %Spent Total N of Change Contracts Contract Amount Amount Amount TO DATE Remaining (Total Contract) Orders TBD Designer(s) $ 326,000 $ 326,000 $ 151,794 $ 174,206 46.6% Equipment $ - $ - $ - General Contractor $ 7,912,000 $ - $ 7,912,000 $ 1,715,000 $ 6,197,000 21.7% CM $ 500,000 $ 500,000 $ 88,391 $ 411,609 17.7% Other $ - $ - $ - Total $ 8,738,000 $ Major CO (over $200k) approved this period: COxx- none Project Budget FY 2024-25 Performance $ 8,738,000 $ 1,955,185 $ 6,782,815 Project Budget -Planned vs Actual 100% 80 % 60 % 40% 20% ... .. ..... 0%� Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 • • • • • Plan %Cum Spent %Cum Project Schedule Status 22.4 Safety Record This Period Totalto Date Near Miss 0 0 First Aid 0 0 Property Damage 0 0 Total 0 0 Site/Progress Photo Milestones Plan Actual Appr Variance Planning Start 11/1/2019 11/1/2019 Areas of Concern/Risks Planning End -Electrical supply chain Design NTP -PG&E coordination Design Completion Construction NTP 5/16/2023 Construction End 12/30/2025 12/30/2025 Risk Type Schedule/Cost Schedule Capital Projects Quarterly Report I OCT - DEC 2024 Page 14 of 17 ,tam ruary 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 38 of 43 Page 16 of 18 Treatment Plant Program status as of Dec-24 Solids Handling Facility Improvements — Phase 1A Scope Project Information To rehabilitate and replace the sludge dewatering centrifuges, cake pumps, and furnace Program Mgr. Craig M Project number 7348 air pollution control equipment. The project involves replacing the existing wet scrubber District Project Mgr. Will G Priority Rank 1 with a new Venturi scrubber capable of bypassing the waste heat boiler, along with the replacement of centrifuges and cake pumps. It also includes upgrading furnace burners Construction Mgr. MWH Phase Construction and electrical and control systems to accommodate the new equipment. Additionally, Contractor Overaa Concord Billing? Yes seismic upgrades will be implemented as part of Solids Phase 1B. Designer CDM Smith % Cost Completion 28.2% Progress Summary • Infill Floor Slab was poured on 1st floor. • Wet Scrubber is being assembled. • Sludge Blend tank has been cleaned, coated and a new lid has been placed • Seismic buttress work on South and East side continue to make progress. Lookahead • Complete sludge blending tank cover including additional work by April 2025. • Continue concrete work for structural buttresses. • Continue structural for interior seismic • Preparing for demolition of furnace #2 train. Continue workong on Electrical Submittals Inception to Date Cost Details Total Budget to Date Expenditure %Spent Phase (Thru Current FY) Future FY Total Budget TO DATE Total Remaining (Total Budget) Time Elapsed KPI Planning $1,000,000 $ 1,000,000 $74,779 $927,886 7.5% Design $15,000,000 $ 15,000,000 $20,271,312 ($5,241,917) * 135.1% Construction $64,518,687 $119,445,000 $ 183,963,687 $51,860,103 $153,186,034 28.2% 29.2% 0 1.0% Total $ 80,518,687 $ 119,445,000 $ 199,963,687 $ 72,206,194 $148,872,003 36.1% 29.2% -6.9% *Overrun due to rebidding and redesign/repackaging Phase 1A and other solid related projects Contract Financials Total Major Original Contract Change Order Current Contract Expenditure % Spent Total # of Change Contracts Amount Amount Amount TO DATE Remaining (Total Contract) Orders TBD Designer(s) $ 8,784,320 $ 5,214,162 $ 13,998,482 $ 9,655,348 $ 4,343,134 69.0% Equipment $ 9,130,726 $ 3,223,814 $ 12,354,540 $ 4,384,895 $ 7,969,645 35.5% General Contractor $ 126,288,000 $ 402,328 $ 126,690,328 $ 22,964,150 $ 103,726,178 18.1% CM $ 457,206 $ 11,355,084 $ 11,812,290 $ 2,362,551 $ 9,449,739 20.0% Others $ 26,435 $ 26,435 $ - $ 26,435 0.0% Total $ 144,686,687 $ 20,195,389 $ 164,882,076 $ 39,366,944 $ 125,515,132 23.9% Major Change Orders (over $200k) approved this period: Safety Record This Period Total to Date None Near Miss 0 0 First Aid 0 0 Project Budget FY 2024-25 Performance Property Damage 0 0 Project Budget -Planned vs Actual Total 0 0 100% Site/Progress Photo 50% 0% i Jul-24 •Aug-24 Sep-24* Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 "�•— • • • • • Plan %Cum —Spent %Cum *Sep2024 Spent to Cum % includes an accrual for $2,816,949 which was reversed in October. Project Schedule Status ctual Approved Date Forecast Date Varim Planning Start Areas of Concern/Risks Risk Type Planning Completion • None Design NTP Design Completion Construction NTP 7/1/2023 10/1/2023 Construction End 8/1/2025 10/30/2027 10/30/2027 Capital Pro'ects Quarter) Report I OCT - DEC 2024 Page 15 of 17 `moo• ruary 5, 2025 EOPS Regular pommitfee Meeting Agenda Packet -Page 39 of 43 Page 17 of 18 Treatment Plant Program Status as of Dec-24 Aeration Basins Diffuser Replacement - Phase 1 Scope Project Information This project includes mechanical rehab, concrete repairs, and seismic upgrades to Program Mgr. Will G Project number 100019 extend the life of aeration basins and diffuser systems. It involves replacing diffusers, District Project Mgr. Will G Priority Rank 8 some air piping, and large underground valves, optimizing sludge processing by reconfiguring unused channels, and upgrading controls for better air flow. Phase 1 Construction Mgr. Will G Phase Construction covers two aeration basins, with the remaining two in Phase 2. Seismic upgrades were Contractor Overaa Concord Billing? Yes added in Phase 1. Designer HDR % Cost Completion 58.4% Progress Summary Lookahead • Basin 1A and 1B were completed on schedule. Controls are being tweaked to • Prepare for the next basin to start in April 2025. opitmize new diffusers. • Continue making progress on electrical. -Electrical Ductbanks were installed. Inception to Date Cost Details Total Budget to Date Expenditure % Spent Phase (Thru Current FY) Future FY Total Budget TO DATE Total Remaining (Total Budget) Planning $200,000 $ 200,000 $562,381 $ (362,381) 281.2% Design $3,300,000 $ 3,300,000 $2,014,461 $ 1,285,539 61.0% Construction $11,480,000 $5,899,000 $ 17,379,000 $10,145,357 $ 7,233,643 58.4% Time Elapsed KPI 59.3% Q 0.9% Total $ 14,980,000 $ 5,899,000 $ 20,879,000 $ 12,722,199 $ 8,156,801 60.9% 70.7% Q Contract Financials Total Major Original Change Order Current Contract Expenditure %Spent Total # of Change Contracts Contract Amount Amount Amount TO DATE Remaining (Total Contract) Orders Designer(s) $ 1,111,000 $ 1,787,153 $ 2,898,153 $ 2,094,018 $ 804,135 72.3% Equipment $ 1,537,853 $ 1,537,853 $ 75,000 $ 1,462,853 4.9% General Contractor $ 12,723,245 $ 492,900 $ 13,216,145 $ 6,716,704 $ 6,499,441 50.8% CM $ 594,857 $ (2,547) $ 592,310 $ 309,170 $ 283,139 52.2% Others $ - $ - Total $ 15,966,955 $ 2,277,505 $ 18,244,460 $ 9,194,892 $ 9,049,568 Major Change Orders (over $200k) approved this period: COxx - Project Budget FY 2024-25 Performance Project Budget -Planned vs Actual 100 % 80% 60% 40% 20% ........ ..... 0 -20% Jul-24 Aug-24 Sep-24 Oct-24 Nov-24 Dec-24 Jan-25 Feb-25 Mar-25 Apr-25 May-25 Jun-25 • • • • • Plan % Cum Spent % Cum Project Schedule Status Milestones Approved Dat Variance Planning Start 7/1/2022 Planning Completion Design NTP Design Completion Construction NTP 8/28/2023 Construction End 12/24/2025 12/24/2025 21130 ruary 5, 2025 EOPS Regular ommi eetWaIngr�gegat�acket - ' ge �0 of 43 9.8 % TBD 50.4% Safety Record This Period Totalto Date Near Miss 0 0 First Aid 0 0 Property Damage 0 0 Total 0 0 Site/Progress Photo Areas of Concern/Risks Risk Type • Unknown condition of existing Schedule/Cost concrete and air leaks. • Completing renovation prior to Schedule wet weather (Oct 31st). Page 16 of 17 Page 18 of 18 This page intentionally left blank. Capital Projects Quarterly Report I OCT-DEC 2024 Page 17 of 17 CENTRAL CONTRA COSTA $ANRARY DISTRICT February 5, 2025 EOPS Regular Committee Meeting Agenda Packet - Page 41 of 43