MEETING DATE: DECEMBER 19, 2024
BOARD OF DIRECTORS
POSITION PAPER
Page 1 of 4
Item 6.
SUBJECT: CONSIDER THE RELOCATION OF CONTRA COSTA WATER DISTRICT'S
ALUM RESIDUAL PIPELINE LOCATED ON CENTRAL SAN'S TREATMENT
PLANT EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL QUALITY
ACT (CEQA)
SUBMITTED BY: INITIATING DEPARTMENT:
AMANDA CAUBLE, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
DAN FROST, SENIOR ENGINEER PDS-PLANNI NG AND APPLI ED RESEARCH
REVIEWED BY: DANEA GEMMELL, PLANNING AND DEVELOPMENT SERVICES DIVISION
MANAGER
GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
Roger S. Bailey
General Manager
ISSUE
Under CEQA, the term "lead agency" refers to the public agency that has the principal responsibility for
carrying out or approving a project that may have a significant effect on the environment. Central San is the
lead agency for treatment plant projects.
BACKGROUND
The Contra Costa Water District (CCWD) has been leasing a portion of Central San property to operate
drying basins used for times when the primary basins at the Bollman Water Treatment Plant reach capacity
or require maintenance. Alum and other coagulation process residuals from the Bollman Water Treatment
Plant are piped to the drying basins where they are air dried and then hauled off. The drying basins have
been in operation since 1997, and it is estimated that 64 cubic yards of solids are processed annually. The
current lease extends through December 13, 2026. CCWD transports the alum residuals through an eight -
inch diameter pipeline along the Walnut Creek channel on Central San's treatment plant property. The
lease states that "CCWD is solely responsible for the existing pipeline used to convey residuals from the
Bollman Water Treatment Plant to the Basins ... and that CCWD shall bear all expenses related to the
construction, maintenance, and modification of any and all capital improvements...."
December 19, 2024 Regular Board Meeting Agenda Packet - Page 33 of 97
Page 2 of 4
Central San's treatment plant is bordered by Walnut and Grayson Creeks with levees built by the Contra
Costa Flood Control District (FCD) and U.S. Army Corps of Engineers, which are currently owned and
operated by the FCD. Overtopping of the levee could catastrophically disable treatment plant operations.
Central San is working on this joint project with the FCD. The Walnut Creek/Grayson Creek Levee
Rehabilitation, District Project 7341 (Levee Project) plans are at the 95 percent design phase and have
identified a conflict with CCWD's eight -inch pipeline within the levee. U.S. Army Corps of Engineers
standards do not allow pressurized pipes to remain within the prism of the levee structure. Central San has
notified CCWD of the standards and requested that the pipeline be relocated (Relocation Project) before
the Levee Project begins construction. CCWD needs the relocated pipeline to ensure that its alum and
coagulation process residuals can continue to be delivered to the drying basins.
Aformal letter from Central San will be delivered to CCWD requesting the relocation of CCWD's alum
residual pipeline and documenting Central San's intent to execute a new lease that would allow CCWD to
continue its operations using Central San's drying basins for another five to ten years. The new lease
would require Board of Directors' (Board) authorization and would require a public hearing to declare the
property unneeded for Central San's purposes during the term of the lease. A right of entry permit will be
granted to CCWD's contractor selected to perform the relocation, which is within staff authority to execute.
CCWD has designed the relocation and will construct and pay for the new pipeline. The proposed pipeline
will be relocated approximately 20 feet to the west of the existing pipeline, as shown in Attachment 1. The
existing pipeline will be demolished, or properly abandoned if demolition is not feasible, as part of the
Relocation Project or Levee Project.
CEQA
As the owner and operator of the treatment plant, it is appropriate for Central San to take on the role of
lead agency for CEQA. CCWD will serve as a "responsible agency" for the Relocation Project since it will
perform the pipeline relocation work and maintain it in the future. This CEQA finding considers the
proposed pipeline relocation work and CCWD's continued use of Central San's drying basins through a
lease with Central San.
Staff has concluded that the Relocation Project is exempt from CEQA under CEQA Guidelines in the
California Code of Regulations Section 15302 since it involves the replacement of existing facilities at
substantially the same locations and with the same purpose and level of activity as the facilities being
replaced.
The Relocation Project is exempt under CEQA Guidelines Section 15061(b)(3) because with
minimization and avoidance measures, construction and maintenance of the pipeline should have no
significant effect on the environment. This conclusion is based on (1) Central San's extensive experience
with similar projects; (2) the relatively short distance involved; and (3) CCWD's construction experience in
this area and construction specifications, which require the contractor to protect natural resources,
including trees and riparian areas, and further requires compliance with all applicable federal, state, county,
district, municipal and local laws, ordinances, orders, and regulations. CCWD will conduct preconstruction
biological surveys prior to commencing work in the area. The new eight -inch pipeline is to be placed largely
in a gravel road and open land adjacent to the Walnut Creek flood control levee. The primary species of
concern are nesting birds that could reside near the creek or directly on the gravel road. Preconstruction
biological monitoring surveys will ensure no nesting birds or other sensitive species are impacted during
construction and future maintenance of the pipeline. Approval of the CEQA finding will establish the
Board's independent finding that the Relocation Project is exempt.
ALTERNATIVES/CONSIDERATIONS
The Board could decline to make the CEQA finding or could direct staff to do a more extensive review.
December 19, 2024 Regular Board Meeting Agenda Packet - Page 34 of 97
Page 3 of 4
FINANCIAL IMPACTS
Any costs associated with the CEQA filing will be included in DP 7341.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on December 4, 2024 and
recommended approval.
RECOMMENDED BOARD ACTION
Find the relocation of Contra Costa Water District's Alum Residual Pipeline Project located on Central
San's treatment plant, exempt from the California Environmental Quality Act.
Strategic Plan re -In
GOAL FIVE: Safety and Security
Strategy 2 - Protect personnel and assets from threats and emergencies
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally
ATTACHMENTS:
1. Project Map
December 19, 2024 Regular Board Meeting Agenda Packet - Page 35 of 97
Page 4 of 4
Alum Pipe Relocation
'
Map Date: 11/12/2024
x• i
y
Martinez
Detail
Area
k
k ;,A'
I�
k
Concord
Alum Ponds.•
i
n
Pleasant Hill
poll
} Approximately.20' Between
Newland E- xsting Alignment's
.,.
- �- �.
• _
• • tt•:3 •!� �•;e�j to
�
-
1
Basin A North"� F.-...
0IIOX�
V
�
Alum Pipe to Remain
Alum Pipe to be Removed
• .
, . -
New Alum Pipe Alignment
♦
}, `:.
— Existing Fence
=J
IiCounty
z,.
_
Quarry;;
' Products
Note:
w ' 0 100 200
Map Displayed in
North American Datum
of 1983