November 6, 2024
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE REPORT ON FISCAL YEAR 2023-24 CLOSEOUT OF CAPITAL
IMPROVEMENT PROJECTS
Twelve capital improvement projects were closed in Fiscal Year 2023-24. Attachment 1 lists the
expenditures and budget underrun or overrun for each project. All expenditures are based on the pre -audit
financial reports ending June 30, 2024. Attachment 2 contains a brief summary of the work completed
under each project. For project budget details, please reference the information provided under the
Financial Statements.
Strategic Plan Tie -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness, Strategy 2 - Protect Personnel and assets from threats and
emergencies
GOAL SIX., Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Expenditure Summary
2. Project Descriptions
3. Presentation
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 17 of 64
Page 2 of 13
Attachment 1
Expenditure Summary
Fiscal Year 2023-24 Closed Projects
TREATMENT PLANT PROGRAM
DISTRICT
PROJECT
NO.
PROJECT TITLE
AUTHORIZED
BUDGET
EXPENDITURES
AS OF 6/30/24
UNDERRUN
OVERRUN
(OVERRUN)
7328
Influent Pump Electrical Improvements
$10,886,000
$11,185,829
$(299,289)
100008
Laboratory Roof & Seismic Upgrades
1,685,000
1,694,454
(9,454)
100009
Hearth Replacement
500,000
542,380
(42,380)
Program Totals
$13,071,000
$13,422,663
$(351,663)
COLLECTION SYSTEM PROGRAM
DISTRICT
PROJECT
NO.
PROJECT TITLE
AUTHORIZED
BUDGET
EXPENDITURES
AS OF 6/30/24
UNDERRUN
(OVERRUN)
8436
Pump Station Upgrades, Phase 1
$35,451,000
$35,403,429
$47,571
8449
Collection System Modeling Support
543,000
317,341
225,659
8464
Martinez Sewer Renovations, Phase 7
4,581,000
4,568,054
12,946
8466
Danville Sewer Renovations, Phase 4
5,202,000
5,141,385
60,615
100038
San Pablo Watershed Improvements
200,000
62,529
137,471
100053
Houston Court CAD
252,894
216,648
36,246
Program Totals
$46,229,894
$45,709,386
$520,508
GENERAL IMPROVEMENTS PROGRAM
DISTRICT
PROJECT
NO.
PROJECT TITLE
AUTHORIZED
BUDGET
EXPENDITURES
AS OF 6/30/24
UNDERRUN
OVERRUN
(OVERRUN)
8253
COVID-19 Response
$275,000
$220,091
$54,909
8250
ERP Replacement
5,380,000
5,360,616
19,384
100043
Easement Acquisition
150,000
11,046
138,954
Program Totals
$5,805,000
$5,591,753
$213,247
RECYCLED WATER PROGRAM
DISTRICT
AUTHORIZED
EXPENDITURES
UNDERRUN
PROJECT
NO.
PROJECT TITLE
BUDGET
AS OF 6/30/24
OVERRUN
(OVERRUN)
None
$
$
$
TOTAL EXPENDITURES $65,105,894 $64,723,802 $382,092
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 18 of 64
Page 3 of 13
Attachment 2
Project Descriptions
Fiscal Year 2023-24 Closeouts
TREATMENT PLANT PROGRAM
Project No. Project Title
7328 Influent Pump Electrical Improvements
Several major improvements completed in the Headworks area, which included replacing the
influent pumps' VFDs and upgrading the PLCs, adding Influent Pump No. 6 for reliability and
redundancy during peak wet weather events, evaluating implementation of "Smart Utility" and use
of "Big Data" as part of this project, and adding submersible sump pump and wet well isolation
gates for flooding protection. During construction, modifications to the wet weather bypass
structure were added to the project. The bypass structure now has improved capabilities during
peak or intense wet weather events.
100008 Laboratory Roof & Seismic Upgrades
The Laboratory roof and seismic improvements were made to meet the Damage Control
Performance Level set by Central San. Modifications and the new roof consisted of new lateral
bracing, new columns at existing brace locations and other modifications as needed, replacement
of the existing roof membrane with a roof system that is more suited for the building, relocating an
existing air-cooled unit in the office area, and replacement of the Laboratory flooring.
100009 Hearth Replacement
This project rebuilt brick and masonry in an existing multiple hearth furnace (MHF) in the Solids
Conditioning Building. Work included confined space entry, demolishing and rebuilding a hearth
within MHF No. 1, and other identified repairs.
COLLECTION SYSTEM PROGRAM
Protect No. Project Title
8436 Pump Station Upgrades, Phase 1
This project included major renovation at the Orinda Crossroads, Flushkleen, and Moraga
Pumping Stations (PSs). Major elements completed were: adding grinder(s) at the Moraga
Pumping Station; constructing a surge tank and canopy at Orinda Crossroads PS; replacing wet
weather diesel engine driven pumps with electric motors at Moraga PS and Orinda Crossroads
PS; adding new backup generators and automatic transfer switch improvements at all three sites;
reconditioning or replacing pumps, valves, and gates; repairing/recoating piping and concrete;
replacing major electrical/controls, including Arc Flash Study recommendations; replacing worn
control panels and seismically bracing control panels and electrical cabinets; improving safety
devices such as replacement of gas detection systems and eye wash stations; coordinating with
the City of Orinda, Town of Moraga, and others; and updating PG&E services and service panels
for the increased electrical demand needed to safely operate the facilities.
8449 Collection System Modeling Support
The major elements included in the project: coordinating and updating the InfoWorks® model with
the Geographic Information System, considering expansion of the trunk sewer model into high
priority development areas where anticipated sewer capacity evaluations will be required,
identifying critical areas with model -predicted surcharge conditions, and installing remote level
monitors and/or flow monitoring equipment and rain gauges.
Page 1 of 2
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 19 of 64
Page 4 of 13
Attachment 2
Project Descriptions
Fiscal Year 2023-24 Closeouts
8464 Martinez Sewer Renovations, Phase 7
The Martinez Sewer Renovations, Phase 7 project replaced or rehabilitated up to approximately
6,400 feet of small diameter public sewers primarily along Alhambra Avenue, and 1,500 feet of
trunk sewers on Alhambra Avenue.
8466 Danville Sewer Renovations, Phase 4
The Danville Sewer Renovations, Phase 4 project replaced or rehabilitated approximately 9,200
feet of small diameter sewers located in both public right-of-way and easements within the Town
of Danville. This project also abandoned several back yard public sewers and relocated sewer
service from the public roadway, which included private agreements to modify and install new
private side sewers before quitclaiming the back yard property easements.
100038 San Pablo Watershed Improvements
The major elements included in this project were: locating and marking all Central San force
mains in the City of Orinda and Town of Moraga and installing permanent markers on or near
force mains in key locations.
100053 Houston Court CAD
The Houston Court Area CAD project provided construction and installation of approximately 636
linear feet of sanitary sewer line, together with appurtenant work and facilities to provide
wastewater service to properties along Quinnterra Lane and Houston Court in the Town of
Danville.
GENERAL IMPROVEMENTS PROGRAM
Project No. Project Title
8253 COVID-19 Response
This project paid for office and outdoor improvements related to the Covid-19 pandemic from
2019-2022. Work included employee signage, modular furniture modifications, replacing furniture
in breakrooms and other locations, building outdoor facilities for staff, and other improvements
needed to comply with Covid guidelines during the pandemic.
8250 ERP Replacement
The major elements included in this project were: conversion of data from the SunGard system to
the new Enterprise Resource Planning (ERP) system; implementation of Human Resources,
Finance, Payroll, Capital Projects, and related systems; and staff training and integration with
related Central San systems. This project included major efforts by staff and others during the
Oracle implementation. Central San's new ERP has automated and integrated many of the core
business processes, including accounting, procurement, budgeting, timecards, and more.
100043 Easement Acquisition
Examples of acquired easements through this project include easements for existing sewers
where no easements currently exist, easements for sewers relocated through other public
agency projects, upgraded easements or access rights for existing sewers, upgraded easements
for the Central San's outfall pipeline, and easements for recycled water distribution pipelines.
RECYCLED WATER PROGRAM
Project No. Project Title
None
Page 2 of 2
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 20 of 64
Page 5 of 13
November 6, 2024
Attachment 3
FISCAL YEAR 2023-24 I
CLOSED CAPITAL
PROJECT
Engineering & Operations
Committee Meeting
Edgar J. Lopez, P.E.
Capital Projects Division Manager
Total Expenditures by Capital Program
Program
Program
Expenditures
Underrun
(Overrun)
Treatment Plant
$13,422,663
$(351,663)
Collection System
$45,709,386
$520,508
General Improvements
$5,591,753
$213,247
Recycled Water (None)
-
-
Total Expenditures:
$64,723,802
$382,092
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 21 of 64 1
Page 6 of 13
Treatment Plant
Closed Projects
Program
> $1 Million
Project
Number
project Titie
Expenditures
7328
Influent Pump Electrical
$11,185,829
Improvements
100008
Laboratory Roof & Seismic Upgrades
$1,694,454
Influent Pump Electrical Improvements,
District Project (DP) 7328
Purpose:
Improve reliability and resiliency to the Influent Pump Station
Work Completed:
Rehabilitation of the motors for Influent Pumps 1-5
Installation of a new Influent Pump 6
Replaced all variable frequency drives for Influent Pumps 1-5
Installed hydraulically actuated isolation gates and walkways
for suction inlet ports to Pumps 1-4
Installation of a large capacity drain pump in the dry well
Improvements to the electrical and controls for the
headworks equipment
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 22 of 64 2
Page 7 of 13
Influent Pump Electrical Improvements,
DP 7328
Laboratory
DP 100008
Purpose:
Roof & Seismic Upgrades,
To replace the leaking laboratory roof and
perform minor structural modifications to
meet the seismic criteria
Work Comoleted:
Replaced the laboratory roof
Building seismic upgrades
Floor replacement
Minor office improvements
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 23 of 64 3
Page 8 of 13
Laboratory Roof
DP 100008
& Seismic Upgrades,
Collection System Program
Closed Projects > $1 Million
Project
Number
project Title
Expenditures
8436
Pump Station Upgrades, Phase 1
$35,403,429
8464
Martinez Sewer Renovations, Phase 7
$4,568,054
8466
Danville Sewer Renovations, Phase 4
$5,141,385
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 24 of 64 4
Page 9 of 13
Pump Station Upgrades, Phase 1
DP 8436
Purpose:
Modifications at Moraga, Orinda Crossroads, and FlushKleen
Pumping Stations to improve resiliency and reliability due to aging
and deficient infrastructure. Improve readiness to respond to
PG&E's Public Safety Power Shutoff events.
Work Completed:
Upgrades to emergency generators and emergency power systems
Installation of new electric driven wet weather pumps
Major electrical, instrumentation, and controls (EI&C) replacement
and rehabilitation
New grinders at Moraga Pumping Station
Upgrades to various piping, valves, and controls
Pump Station Upgrades, Phase 1
DP 8436
irk ;,�.,
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 25 of 64 5
Page 10 of 13
Martinez Sewer Renovations, Phase 7, DP 8464
Purpose: To replace sewer mains within the Collection System that are near the end of
their useful lives and in poor condition.
Work Completed: Replaced or rehabilitated up to 6,800 feet of small diameter sewers.
Martinez Sewer Renovations, Phase 7, DP 8464
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 26 of 64 6
Page 11 of 13
Danville Sewer Renovations, Phase 4, DP 8466
Purpose: To replace sewer mains within the Collection System that are near the end of
their useful lives and in poor condition.
Work Completed: Replaced or rehabilitated up to 9,200 feet of small diameter sewers.
Danville Sewer Renovations, Phase 4, DP 8466
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 27 of 64 7
Page 12 of 13
General Improvements Program
Closed Projects > $1 Million
Project
Number
project Title
Expenditures
8250
ERP Replacement
$5,360,616
ERP Replacement, DP 8250
Purpose:
To replace legacy outdated Enterprise Resource Planning (ERP) System, SunGard, with a modern
cloud -based version (Oracle Fusion). To enhance security, availability, accessibility, and supportability.
Work Completed:
Implemented all the Financial and HR modules in Oracle Fusion and migrated all the data. Included
the following modules:
Core Human Resources
Time & Labor
Benefits
Payroll
Accounts Payable/Receivable/General
Procurement
Enterprise Performance Management (EPM) for Budgeting
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 28 of 64 $
Page 13 of 13
Recycled Water Program
Closed Projects > $1 Million
No closed projects to report for this program
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 29 of 64 9