November 6, 2024
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE UPDATE ON STEAM RENOVATIONS, PHASE 1B PROJECT
The Steam Renovations, Phase 1, District Project No. 100032 is listed on page 275 of the Fiscal Year
2024-25 Budget. The scope of this project has been separated based on location and
coordination/conflicts with other renovation activities. Phase 1 A consists of improvements within the Pump
and Blower building and was recently awarded for construction by the Board of Directors.
Phase 1 B consists of improvements within the Solids Conditioning Building and staff will present a design
status update and approach for construction.
Strategic Plan Tie -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations, Strategy 4 - Identify and advance sustainability initiatives, including
reducing energy usage and emissions
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness, Strategy 2 - Protect Personnel and assets from threats and
emergencies
GOAL SIX., Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Presentation
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 64
Page 2 of 5
Attachment 1
November 6, 2024
Steam Renovations,
Phase 1B Iwo
District Project 100032
Update - Design Status -�
and Construction Solution
Engineering and Operations
Committee Meeting
Edgar J. Lopez, P.E.
Capital Projects Division Manager
Extensive Condition Assessments (Secondary and Steam Assets)
Sub 33
Aeration Basins Diffuser
1r
Replacement, Phase 1
A
District Project (DP)
100019
Sub 52
Sub 34
49 0
Electric Blower
� I
- `Vj t
Improvements, DP
}yt
100015
A�
111111OM i Sub 73
2
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 64 1
Page 3 of 5
Current Phase 1B Design Status
Steam Regulators
HDR Engineering, Inc. (Designer) completed 90%
Detailed Design submittal. Design includes
modifications to the boiler feedwater system
highlighted and presented at the May 2024 E&O
Committee Meeting.
Specialty design for boiler systems and safety codes.
The new boiler system improvements and its design is
highly impacted by the final construction of the Solids
Handling Facility Improvements, Phase 1A (Solids
Project).
Coordination with Solids Project work and schedule is
highly complex and has potential for delays or changes.
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 14 of 64 2
Page 4 of 5
Timeline for Phase 1B
The improvements are required within the next
three to four years. Several meetings with
Operations has confirmed the need to move
forward to complete the work due to known risks.
It is not practical or recommended to mobilize
another contractor into the SCB.
The Solids Project is under construction with major
improvements throughout the SCB, including
seismic modifications, new mechanical, piping,
and electrical. Expected completion is in 2028.
Path Forward for Phase 1B
Pump Replacement — Replace and
Upgrade Steam -Driven Pumps
IWAMMONNiii ! ..
Constructability and design assistance with C. Overaa
& Co. (Solids Project general contractor).
Schedule analysis with C. Overaa & Co. and MWH
Constructors (Central San's construction manager).
With input by the Solids Project team, HDR
Engineering, Inc. can finalize the design for Phase 1B.
Review and finalize costs for a construction contract
change order under the Solids Project.
Bring back to E&O in January 2025 and then for the
Board's consideration. Engineer's estimate is
$6.0 million.
MENOMPOT1170
November 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 15 of 64 3
Page 5 of 5
Questions/
Discussion