HomeMy WebLinkAbout03.c. Authorize General Manager to execute a construction contract change order $800,000 with C. Overaa & Co. for Sludge Blending Tank under the Solids Handling Facility Improvements, Phase 1A, DP 7348Page 1 of 7
Item 3.c.
DCENTRALSAN
MEETING DATE: OCTOBER 2, 2024
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
SUBJECT: REVIEW DRAFT POSITION PAPER TO AUTHORIZE THE GENERAL
MANAGER TO EXECUTE A CONSTRUCTION CONTRACT CHANGE
ORDER IN THE AMOUNT NOT TO EXCEED $800,000 WITH C. OVERAA &
CO. FOR ADDITIONAL WORK FOR THE SLUDGE BLENDING TANK
UNDER THE SOLIDS HANDLING FACILITY IMPROVEMENTS, PHASE 1A,
DISTRICT PROJECT 7348
SUBMITTED BY: INITIATING DEPARTMENT:
CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS
DIVISION MANAGER
ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
ISSUE
Authorization from the Board of Directors (Board) is required to execute a construction contract change
order in an amount greater than $200,000.
BACKGROUND
The sludge blending tank (SBT), located at the Martinez wastewater treatment plant, is crucial for the
sludge dewatering process. On January 16, 2020, JDH Corrosion Consultants, Inc., performed an internal
condition assessment of the SBT at Central San's main treatment plant.
The composite steel/concrete cover was found to be in poor condition with severe corrosion of the steel
structural members. Replacement of the cover was included in the Solids Handling Facility
Improvements, Phase 1 A Project and work is currently underway. The existing cover was demolished, and
a new cover is being fabricated.
The SBT was constructed in the 1960s as a sludge digester and was converted into a blending tank in
1980s. The tank was originally constructed as a post -tensioned tank with steel post -tensioning cables
which allows for thinner concrete walls. Once installed, post -tensioning cables cannot be cut without
affecting the tank's structural properties. When it was converted, all of the side manways were utilized for
pipe penetrations, and the only access for inspection and maintenance is from maintenance hatches in the
cover, which makes it extremely difficult to inspect and maintain the tank interior.
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 24 of 42
Page 2 of 7
The demolition of the existing cover allowed full access to the tank interior for visual inspection. On August
12, 2024, the SBT was inspected by Central San, the construction management team (MW H
Constructors, Inc.), the contractor (C. Overaa & Co.) and Redwood Painting (coating subcontractor).
The interior of the tank is in very good condition given its age. There was minimal corrosion of the concrete
with no significant cracks or delamination observed. However, most of the original coal tar epoxy coating is
missing. With the tank fully accessible and the coating subcontractor onsite to coat the tank cover, now is
an opportune time to sandblast the tank walls to remove the remaining existing coal tar, prepare the tank
walls, and coat the walls. The most practical and cost-effective solution would be to use the same coating
being applied to the steel cover. The coating will be a glass flake containing epoxy, Sherwin Williams Sher -
Glass, which provides excellent resistance to hydrogen sulfide. Coating the tank walls with the cover off will
allow full access to all portions of the wall and will be much easier than coating the tank walls after the new
cover is in place.
In addition, the Maintenance Division has requested that the sludge blending piping inside and outside the
tank be cleaned. Central San adds carbide lime to the tanks to adjust the sludge pH for polymer activation,
and help the furnace process to produce consistent and acceptable ash to deliver off site (clinker control).
I n time, the lime builds up against the interior piping and reduces the internal diameter for flow causing
burden to the sludge blending pumps and potential failures related to over pressuring the system. Staff
recommends including this work as a change order so the tank can be cleaned while it is out of service.
The buildup of lime in the piping is in a state that requires immediate cleaning. The scope of work includes
disassembling the piping, transporting the piping out of the SBT, blasting the interior of the piping,
cleaning, and re -installing the piping back in the tank. The piping also extends into the basement and
nearby tunnels.
Both the coatings and cleaning of the piping are not included in the contract; however, they are within the
scope of the project work and can be included to the contract upon Board authorization as additional work
due to unforeseen conditions.
California Environmental Quality Act (CEQA)
Staff has concluded that this project is exempt from CEQA under Central San's CEQA Guidelines
Section because it involves minor alterations to existing public facilities involving no expansion of use.
Approval of this project will establish the Board's independent finding that this project is exempt from
CEQA.
ALTERNATIVES/CONSIDERATIONS
The proposed work is in the best interest of Central San to be implemented now under a change order to
the project. Any alternative to postpone the work will result in a significant cost increase and impact the
Operations Division by performing additional shutdowns and coordination.
FINANCIAL IMPACTS
The construction contract change order is estimated not to exceed $800,000. The coatings work is
approximately $380,000 and the piping work is $420,000. These costs have been reviewed by the
construction management team and are in line with the coatings work in the project, and past spending for
the pipe cleaning. The Solids Handling Facility Improvements, Phase 1 A Project has adequate
contingency approved by the Board at $13,000,000. Change orders total approximately $402,328 as of
September 2024.
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 25 of 42
Page 3 of 7
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on October 2, 2024 and
recommended
RECOMMENDED BOARD ACTION
Authorize the General Manager to execute a construction contract change order in the amount not to
exceed $800,000 with C. Overaa & Co. for additional work for the sludge blending tank under the Solids
Handling Facility Improvements, Phase 1A, District Project 7348.
Strategic Plan Tie -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3 - Maintain financial stability and sustainability
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness, Strategy 2 - Protect Personnel and assets from threats and
emergencies
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Presentation
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 26 of 42
Page 4 of 7
October 2, 2024
Construction Contract
Change Order Request
- Sludge Blending
Tank Additional Work
Engineering and Operations
Committee Meeting
Edgar J. Lopez, P.E.
Capital Projects Division Manager
Sludge Blending
Tank (SBA
Old digester repurposed to a storage
tank for blending solids/sludge prior
to the furnace handling process
Tank cover is being replaced under
the Solids Handling Facility
Improvements, Phase 1A with C.
Overaa & Co.
Tank exterior was retrofitted several
years ago with a fiber wrap,
including seismic considerations
Future plans to be an emergency
storage tank
Attachment 1
'IV,
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 27 of 42 1
Page 5 of 7
SBT Interior Wall
Condition
Very little coal tar epoxy coating
remaining
Operations has determined that the
operating level of the tank should
be lower than the previous decade,
and this is a likely cause of why the
tank interior is deteriorating faster
than anticipated
Coating now is the ideal time and
more cost effective than performing
the work later
Before Cleaning
t
0
I]
After Cleaning
s
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 28 of 42 2
Page 6 of 7
Current Nozzle
Buildup
Current condition:
Restricted nozzle reduces pump
mixing efficiency
Lime buildup in the piping
Maintenance has requested the work be
completed prior to returning the tank
back into service to avoid another shut
down and overall tank cleaning
Change Order Costs
Total estimate for the work is
$800,000:
$380,000 for specialty
coatings
$420,000 for pipe cleaning
Costs are in line with bid pricing
and previous cleaning efforts
conducted by Central San
r
Q�
0ICENTRALSAN
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 29 of 42 3
Page 7 of 7
Recommended Board
Action
0-
Authorize the General Manager
to execute a construction
contract change order in the `
amount not to exceed $800,000
with C. Overaa & Co. for
additional work for the sludge
blending tank under the Solids
Handling Facility Improvements,
Phase 1A, District Project 7348
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 30 of 42 4