HomeMy WebLinkAbout03.a. Award a construction contract in the amount of $1,056565 to Telstar Instruments, for the plant control system input and output (I/O) replacement, Phase 3 - Pump and Blower Building, DP 10057; and consider the project exempt from CEQAPage 1 of 11
Item 3.a.
CD BOARD OF •'
CENTRAL CONTRA COSTA SANITARY DISTRICT POSITION PAPER
DRAFT i
MEETING DATE: OCTOBER 2, 2024
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $1,056,565 TO TELSTAR INSTRUMENTS,
THE LOWEST RESPONSIVE AND RESPONSIBLE BIDDER, FOR THE
PLANT CONTROL SYSTEM INPUT AND OUTPUT (1/0) REPLACEMENT,
PHASE 3 - PUMP AND BLOWER BUILDING, DISTRICT PROJECT 100057;
AND CONSIDER THE PROJECT EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA)
SUBMITTED BY:
INITIATING DEPARTMENT:
NATE MORALES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
ISSUE
On September 4, 2024, four sealed bids were received and opened for the construction of the Plant
Control System 1/0 Replacement, Phase 3 - Pump and Blower Building, District Project 100057
(Project). The Board of Directors (Board) must consider award of the construction contract or reject bids
within 50 days of bid opening.
BACKGROUND
The wastewater treatment plant (plant) primarily uses programmable logic controllers (PLC) connected to
1/0 cards manufactured by Schneider Electric. PLC 1/0 cards are critical for equipment and
instrumentation communication for process control, monitoring, and data acquisition. The first plant PLC
1/0 cards were installed in the mid-1980s. Today, the number of 1/0 cards in use has grown to nearly
1,800. Approximately 700 of these 1/0 cards are outdated and replacement units cannot be purchased
from the manufacturer, and they are no longer supported by their service department. Central San
maintains an inventory of spare 1/0 cards to replace units as they fail, but that spare supply has depleted in
recent years.
This Project is the third of a multiphase effort to replace outdated PLC hardware with modern Schneider
Electric equipment at the plant. The Project will address long-term reliability for the PLC system by
replacing 1/0 cards in the Pump and Blower Building area and salvaging the old 1/0 cards to restock
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 3 of 42
Page 2 of 11
inventory. The effort will continue the implementation of modern PLC systems and will match the new
systems that were installed during phases 1 and 2 at the Filter Plant and secondary process area. The
Project site is identified in Attachment 1.
The Project also includes the replacement of a critical 1,000 horsepower variable frequency drive (VFD)
for the Final Effluent Pump 3. The existing VFD is obsolete; Central San's maintenance department can
no longer purchase replacement parts. Additionally, the Project will replace the aeration turbine vibration
systems, rewire motor control center controls, and make various other controls improvements in the Pump
and Blower Building.
Central San staff prepared the plans and specifications for the Project. The Engineer's estimate for
construction was $1,500,000. This Project was advertised on July 17 and July 24, 2024. Four sealed bids
ranging from $1,056,565 to $2,451,000 were received and publicly opened on September 4, 2024. The
Engineering Department conducted a technical and commercial review of the bids and determined that
Telstar Instruments is the lowest responsive and responsible bidder with a bid amount of $1,056,565. A
summary of bids received is shown in Attachment 2.
Central San will administer the construction contract and will provide contract management, administration,
office engineering, administer submittals and schedules, and provide construction inspection. Pending
Board award, the General Manager shall execute the Contract Documents subject to submittal
requirements.
CEQA
Staff has concluded that this Project is exempt from CEQA under Central San's CEQA Guidelines
Section 15301, since it involves minor alterations to existing public facilities involving no expansion of use,
and CEQA Guidelines Section 15302, since it involves replacement of existing public facilities at the
same location and with the same purpose. Approval of this Project will establish the Board's independent
finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board may elect to postpone or phase the construction which would require the Board to reject all
bids. This is not recommended since there are several project elements that should not be deferred
including a critical VFD replacement and associated control equipment and PLC work.
If the Final Effluent Pump 3 VFD and PLC scope were bid separately, there would be re -work associated
and the costs would ultimately increase. The Plant Control System 1/0 Replacement Project has already
been phased to effectively replace equipment while getting the maximum expected life out of the existing
equipment, and balancing an adequate spare parts inventory. Additional delays are not recommended.
FINANCIAL IMPACTS
The total estimated project cost is $1,964,000, which includes planning, design, construction contract,
contingency, and construction management costs as shown in Attachment 3. The Project is included in the
Fiscal Year 2024-25 Budget on page 284 with a total estimated project budget of $2,800,000. There is
adequate funding for the Project and the budget savings will be transferred to the Capital Project
contingency account.
Due to the competitive pricing, staff is including a 30-percent contingency budget since there are
significant project savings, and for unforeseen conditions if they arise.
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 4 of 42
Page 3 of 11
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on October 2, 2024 and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
Award a construction contract in the amount of $1,056,565 for the construction of the Plant Control
System 1/0 Replacement, Phase 3 - Pump and Blower Building, District Project 100057 to Telstar
Instruments, the lowest responsive and responsible bidder; and
2. Find that the Project is exempt from CEQA.
Strategic Plan re -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
GOAL SEVEN: Innovation and Agility
Strategy 2 - Implement organization -wide optimization
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post-B id/P reconstruction Estimate
4. Presentation
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 5 of 42
Page 4 of 11
�I
0
0
3
m
0
0
0 �6
e•
0
IOU C 3Q
a�','Opl�3
3:3.
P,VQ33
N
i
o 400 800
FEET
r 1 PROJECT
AREA
su
FILTER p
PLANT �\
ok,
NORTH
CLARIFIERS/
O
AERATION
TANKS
SOUTH
CLARIFI>SK,
&
o PUMP \
1 BLOWER
� BUILDING
c:i
PRIMARY
a
�\ TANKS
CENTRALSAN
'A�ENAINCSD-
CENTRAL jWRA C75 A
S
CLEARWELL
BASIN
NORTH
BASIN
CO
DRAIN BACK
CHANNEL
o li
SOUTH
BASIN
SOLIDS
BUILDING
PLANT CONTROL SYSTEM 1/0 REPLACEMENT,
PHASE 3 - PUMP AND BLOWER BUILDING
DISTRICT PROJECT 100057
gular Committee Meeting Agenda Packet - Page 6 of 42
Attachment
1
Page 5 of 11
ATTACHMENT 2
PLANT CONTROL SYSTEM 1/0 REPLACEMENT, PHASE 3 —
PUMP AND BLOWER BUILDING
DISTRICT PROJECT 100057
SUMMARY OF BIDS
PROJECT NO.: 100057 NO. OF ADDENDA: 5 DATE/TIME: SEPTEMBER 4, 2024/2 PM
PROJECT NAME: PLANT CONTROL SYSTEM 1/0 REPLACEMENT, PHASE 3 —
PUMP AND BLOWER BUILDING
PROJECT MANAGER: NATE MORALES
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
ENGINEER'S ESTIMATE: $1,500,000
NO.
BIDDER
BID PRICE
1
Telstar Instruments
$1,056,565
Sacramento, California 95834
2
Contra Costa Electric
$1,502 000
Martinez, California 94553
'
3
Vellutini Corporation dba Royal Electric Company
$1,759,000
Sacramento, California 95828
4
Saboo Inc.
$2,451,000
Brentwood, California 94513
BIDS OPENED BY: /s/ Katie Young DATE: September 4, 2024/2 PM
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 42
Page 6 of 11
ATTACHMENT
PLANT CONTROL SYSTEM 1/0 REPLACEMENT, PHASE 3 - PUMP AND BLOWER BUILDING
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Of
Construction
Cost
1
CONSTRUCTION
a. Construction Contract
$1,056,565
b. Contingency at 30%
$316,435
SUBTOTAL - CONSTRUCTION
$1,373,000
100%
2
CONSTRUCTION MANAGEMENT
a. District Forces
$160,000
b. Consultant - As -Needed Engineering Services
$45,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$205,000
15%
3
PREBID EXPENDITURES
a. District Forces
-Planning and Design
$180,000
-As-Built Documentation and Field Investigation
$90,000
-Associated PLC Programing
$75,000
b. Consultants
-Consultant Drafting
$23,500
-Laser Scanning of Pump and Blower Building
$17,500
SUBTOTAL - PREBID EXPENDITURES
$386,000
28%
4
TOTAL ESTIMATED PROJECT COST - PHASE 3
$1,964,000
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 42
Page 7 of 11
Attachment 4
October 2, 2024
Plant Control System
1/0 Replacement,
Phase 3 - Pump and
Blower Building,
District Project 100057
Engineering and Operations
Committee Meeting
Nate Morales
Senior Engineer
Background: Control System Basics
000
CONTROL ROOM
SCADA
=4=
E.
Supervisory Control and Data
SCADA SERVER
Acquisition
SCADA PCs
TREATMENT
PLANT I
I
NEWOTCRK
SWIH
PI -Cs
07
3'rogramable Logic Controllers
PLC,
PLC 2
I1
REMOTE I/O
In
Remote Inputs & Outputs
REMOTEVO
REMOTE110
NETWORK TCH
EQUIPMENT
z
PUMP
PUMP PUMP
PUMP
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 42 1
Page 8 of 11
Background: Control Panel Upgrade Example
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 42 2
Page 9 of 11
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 11 of 42
Page 10 of 11
Project Schedule
Contractor has 365 days
VFD Leadtime is 9 months
Expected Start — April 2025
Expected Finish — November 2025
Total Estimated Project Budget
No.
Item Description
Amounts
of
Construction
Cost
1
CONSTRUCTION
a. Construction Contract
$1,056,565
b. Contingency at 30 %
$316,435
SUBTOTAL - CONSTRUCTION
S1.373.000
100%
2
CONSTRUCTION MANAGEMENT
a. District Forces
$160,000
b. Consultant -As-Needed Engineering Services
S45.000
SUBTOTAL- CONSTRUCTION MANAGEMENT
$205.000
15%
3
PREBID EXPENDITURES
a. District Forces
-Planning and Design
$180.000
-As-Bu€It Documentation and Field Investigation
590.000
-Associated PLC Programing
575,000
b. Consultants
-Consultant Drafting
S23.500
-Laser Scanning of Pump and Blower Building
517.500
SUBTOTAL- PREBID EXPENDITURES
$386.000
28%
4
TOTAL ESTIMATED PROJECT COST - PHASE 3
51.964,000
,& dFQCENTRALSAN
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 42 4
Page 11 of 11
Recommended Board
Action
Award a construction contract in !
the amount of $1,056,565 for the ,
construction of the Plant Control
System 1/0 Replacement, Phase 3 -
Pump and Blower Building, District �•
Project 100057, to Telstar
Instruments, the lowest responsive
and responsible bidder; and
Find that the project is exempt
from the California Environmental
Quality Act.
Questions and Discussion
October 2, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 42 5