HomeMy WebLinkAbout03.a. Receive 2024 Permitting Resource Management Review and Biannual Findings ReportingPage 1 of 12
Item 3.a.
F__1_448�411C_S0
September 3, 2024
TO: ADMINISTRATION COMMITTEE
FROM: BENJAMIN JOHNSON, INTERNALAUDITOR I DIVERSITY, EQUITY,AND
INCLUSION OFFICER
REVIEWED BY: PHILIPLEIBER, DEPUTYGM -ADMINISTRATION
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE 2024 PERMITTING RESOURCE MANAGEMENT REVIEW AND
BIANNUAL FINDINGS REPORTING
Enclosed is the 2024 Permitting Resource Management Review final report. The objective of this
engagement was to review the business structure of the permitting function, identify any gaps, and make
general recommendations where appropriate. This engagement aims to consider the management of
resources on the organizational level with respect to the permitting function. Internal Audit employed
several techniques to develop a best practice model, including survey data from sister agencies, industry
standards, internal metrics, and feedback from Central San leadership.
It is important to clarify that this engagement was not a formal audit. Instead, Internal Audit collaborated
with workgroup staff and leadership to develop a project addressing the organization's immediate needs
from both customer service and staffing perspectives. The recommendations in this report are intended to
guide prudent decision -making by leadership. They are general in nature and do not specify formal
remediation deadlines or responsible parties. Ultimately, this report offers stakeholders a broad overview
of the dynamics within this critical business line, with the goal of identifying opportunities for improvement.
Also included is the Biannual Findings Report ending Q2 2024. There are four findings open, which were
identified in Phase 1 of the Capital Projects audit.
Strategic Plan Tie -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 1 - Promote and uphold ethical behavior, openness, and accessibility, Strategy 3 - Maintain financial stability
and sustainability
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 3 of 50
Page 2 of 12
GOAL SEVEN: Innovation and Agility
Strategy 1 - Leverage data analytics to become a more efficient utility, Strategy 3 - Be adaptable, resilient and
responsive
ATTACHMENTS:
1. 2024 Permitting Resource Management Review F I NAL Report 8.19.24
2. Central San Internal Audit Findings Report
3. Presentation
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 4 of 50
Page 3 of 12
Attachment 1
110ENTRAL SAN
INTERNAL AUDIT REPORT
DATE: August 19, 2024
TO: Greg Norby, Deputy General Manager, Operations
Danea Gemmell, Planning & Development Services Division Manager
Kevin Mizuno, Finance Division Manager
Damasio Zepeda, Senior Engineer
Kim Stahl, Development Services Supervisor
FROM: Benjamin Johnson, Internal Auditor I Diversity, Equity, and Inclusion Officer
SUBJECT: 2024 PERMITTING RESOURCE MANAGEMENT REVIEW FINAL REPORT
Enclosed is the 2024 Permitting Resource Management Review FINAL Report. The objective of this
engagement was to review the business structure of the permitting function, identify any gaps, and
make general recommendations where appropriate. This engagement aims to consider the
management of resources on the organizational level with respect to the permitting function. Internal
Audit employed several techniques to develop a best practice model, including survey data from sister
agencies, industry standards, internal metrics, and feedback from District leadership.
It is important to clarify that this engagement was not a formal audit. Instead, Internal Audit
collaborated with workgroup staff and District leadership to develop a project addressing the
organization's immediate needs from both customer service and staffing perspectives. The
recommendations in this report are intended to guide prudent decision -making by District leadership.
They are general in nature and do not specify formal remediation deadlines or responsible parties.
Ultimately, this report offers stakeholders a broad overview of the dynamics within this critical business
line, with the goal of identifying opportunities for improvement.
Internal Audit would like to thank leadership and staff for their partnership during the length of this
project.
If you have any questions, please contact me at (925) 229-7120.
Benjamin Johnson, Internal Auditor I Diversity, Equity, and Inclusion Officer
Enclosure
cc: Roger S. Bailey, General Manager
Philip Leiber, Deputy General Manager, Administration
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 5 of 50
Page 4 of 12
2024 PERMITTING RESOURCE MANAGEMENT REVIEW FINAL REPORT
DATE: August 19, 2024
INTRODUCTION
Audit Objective The objective of this engagement was to review the business structure of the
permitting function, identify any gaps, and make general recommendations
where appropriate.
Background The permitting workgroup, comprised of five team members, provides high
quality customer service consistent with the District's compliance and regulatory
needs. The core functions performed at the permit counter include:
• Assisting the public with submitting and processing permit applications
related to wastewater management, such as for construction projects,
discharges, or modifications to existing facilities.
• Reviewing permit applications to ensure they are complete and
compliant with relevant regulations and assigning any relevant permit
conditions. This includes assessing proposed plans, specifications, and
environmental impact assessments for adherence to established
standards.
• Collecting permit fees in line with established schedules and regulations.
This involves calculating fees based on project scope, type of activity,
and regulatory requirements, and ensuring accurate documentation and
accounting of fee transactions.
• Providing responsive and courteous customer service to address
inquiries, resolve issues, and assist applicants and permit holders
throughout the permitting process. This includes handling phone calls,
emails, and in -person inquiries, as well as coordinating with other
departments or agencies as needed.
• Generating reports and summaries on permit activities, including
issuance, renewals, and compliance status, to support decision -making
and regulatory oversight.
• Updating billing system with new application data and parcel
information, collecting water data and reviewing water meter
information, administering rate information to perform production
billing annually.
• Educating the public about wastewater management practices, permit
requirements, and environmental impact.
Depending on the size and complexity of a plan submitted to the District, the
time needed to research, review, and respond to a customer can be
considerable. To complete plan reviews, the permit counter frequently
collaborates with various workgroups, including those handling fee review,
environmental review, development inspection, and right-of-way. Effective
coordination among these groups is essential for meeting the turnaround times
outlined in public -facing online resources. The permit counter aims to be a
trusted partner with the public, curating a vast collection of knowledge and
resources to meet the unique needs of each customer.
2024 Permitting Resource Management Review FINAL Report 08.19.24
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 6 of 50
Page 5 of 12
While the leadership and staff in permitting recognize the consistent pressures
of operational demands, a strong sense of teamwork persists, along with a
willingness to take on additional responsibilities during organizational changes.
For instance, they have absorbed external duties like overseeing regulatory
compliance reviews of mainline processes and sewer billing. Additionally, a more
thorough review of plans submitted for encroachment verification has
contributed to the workload due to complexity of development and projects.
However, these additional tasks may affect the timeliness of our customer
service.
In Q1 2024, the permitting function launched the Oracle Permitting and
Licensing (OPAL) software to better align related business processes with the
District's Oracle Fusion Cloud Enterprise Resource Planning software. In the
following months, permitting staff identified numerous critical system gaps and
bugs, while the accounting group observed improved efficiency in cash
management. Both groups have since noted a gradual reduction in system issues
leading up to Q3 2024.
Project Scope Internal Audit reviewed the business design of the permitting function, with a
focus on the following subprocesses:
• Oracle permitting software implementation
• District processing time management
• Residential and commercial plan reviews
• Encroachment verifications
• Customer service interactions via walk-ins, email, phone, and potential
online presence
• Permit issuance at permit counter and via email
• Public mainline extensions
• Real property agreements coordination
• Cash management
This engagement was performed using the following methods:
1. Reviewed any available policies, guidelines, and procedures.
2. Interviewed and gathered input from workgroup leadership.
3. Interviewed staff and observed the processes within the scope of the
project.
4. Analyzed the design of the business, including relevant processes with
respect to meeting established operational objectives.
5. Reviewed internal output metrics and benchmarked data with sister
agencies.
6. Crafted and communicated results of the review, including general
recommendations, where appropriate.
2024 Permitting Resource Management Review FINAL Report 08.19.24
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 7 of 50
Page 6 of 12
ENGAGEMENT RESULTS
Summary Internal Audit's review of the permitting function's business structure reveals
several opportunities for positive change, contingent on the future availability
of District resources. The permitting workgroup not only maintains vital
relationships with customers and internal stakeholders, but also consistently
reports metrics for deliverables that significantly surpass those of sister
agencies in key categories. Our current public engagement figures include:
• Central San processes over 7,000 permitting applications annually,
including more than 3,000 new applications (3,317 in 2023) and
updates to existing ones.
• Over the past seven years, the group averaged 1,832 permits
processed each year.
• Annually, the group handles around 3,000 in -person visits and
responds to approximately 15,000 emails.
• When fully staffed, the group dedicates 200 staff hours each week to
serving the public.
With guidance from workgroup leadership, the District benchmarked its key
permitting metrics against five sister agencies in the Bay Area. The results
revealed that the District consistently outperformed other local wastewater
agencies in several areas: the number of new permit applications processed,
the number of permits completed per full-time employee, and overall annual
performance. While the closest figures from other agencies reported around
1,000 new applications and 700 permits processed annually, the District's
results were significantly higher. Permitting teams across all agencies typically
consisted of three to five employees.
Despite ongoing operational challenges with the implementation of the
Oracle Permitting and Licensing (OPAL) software, the permitting team
remains highly committed to customer service excellence and adheres to
established turnaround times. With support from the Information Technology
team, the permitting workgroup has successfully reduced the number of
outstanding critical system fix requests from double digits to single digits as
of the date of this report. The OPAL software is still a work in progress on
delivering an efficient and user-friendly platform. Oracle is looking at
addressing some of its deficiencies over the next two years.
When evaluating the annual output of this workgroup, analyzing the
intersection of District -level resource management and business
sustainability offers valuable insights for future planning and strategy. The
District benefits from a skilled and experienced permitting staff, dedicated to
meeting their established targets. Balancing customer and staff satisfaction
remains a key objective, and achieving this harmony continues to be a goal
the District strives to reach.
General Currently, customers must submit physical plans for review, but they have
Recommendations the option to email their simple and small plan sets if requested. As the
landscape of customer demand continues to evolve after the changes
introduced by the COVID pandemic, there may soon be opportunities to
2024 Permitting Resource Management Review FINAL Report 08.19.24
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 8 of 50
Page 7 of 12
expand the permitting function's online presence, particularly in permit
reviews. While optimizing OPAL to better serve the District remains a priority,
a growing number of customers have expressed a desire to submit plans
online and engage with staff remotely. If staff and leadership are confident in
their ability to meet turnaround commitments, transitioning to a parallel
electronic service through OPAL could be of value to ensuring business
sustainability moving forward.
Before this project began, it was generally expected that the permit counter
remained open to customers during District -wide employee events like
holiday parties and appreciation gatherings. However, after reviewing annual
output figures and consulting with workgroup leadership, the Executive Team
has formally recommended adjusting our business model to allow permitting
employees to attend these events. Maintaining effective communication on
such critical topics will help the District find meaningful solutions to both
historical and future challenges. Additionally, the data gathered by
workgroup leadership during this project may inform these ongoing
discussions.
Internal Audit recommends that the permitting workgroup and District
leadership maintain open and regular communication about operational
needs and their impact on customer service quality and staff. Given the high
level of annual output and frequent public engagement, and considering
future availability of District resources, there may be opportunities to further
enhance the District's ability to provide a robust suite of services while more
effectively distributing processing responsibilities among staff. Central to
these discussions will be an evaluation of staffing levels, which may be
considered low given the current output levels.
Leadership's The challenges of working with the interim OPAL software and ongoing
Response testing and training of staff is expected to last at least 1-2 more years as
Oracle works to finish development on this relatively new product. Today's
development projects are much more complicated than in the past, as many
projects are redevelopments that have conflicts with existing utilities and the
more challenging lots have not been cost effective until now. This results in
longer turnaround times to resolve site problems. Staff is committed to
enhancing the public experience for permitting, but likely will need additional
resources to help address these continued challenges until OPAL is improved.
Additionally, resources will be stretched with the next software initiative to
replace and/or upgrade the billing system.
- Danea Gemmell, Planning & Development Services Division Manager
Internal Audit's Leadership's response appears to appropriately outline current business
Response challenges and opportunities. Internal Audit is available to serve as a trusted
advisor when considering future conversations around positive change.
2024 Permitting Resource Management Review FINAL Report 08.19.24
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 9 of 50
Page 8 of 12
Attachment 2
Internal Audit Findings Report
Current as of: 08.19.24
Prepared by: Benjamin Johnson, Internal Auditor I Diversity, Equity, and Inclusion Officei
Risk Rating
Total
1 - High Risk
2
2 - Moderate Risk
2
3 - Low Risk
0
Total
4
Finding Title Audit Name
General Category of Observations
Total
Need for documentation of procedures or updates
1
Segregation of duties
1
IT -related controls
0
General process and/or control improvements
1
Automation opportunities
1
Finding
Number Finding Description
Risk Rating Observation
(Residual) Category Division
* Highlight Legend
Past Due
High Risk
Closed
Executive
Owner Manager Report Date Due Date Date Closed
Open
1
Engineering procedural
2023 Capital Projects Design -only Audit
1
There is a need to update the procedural
Need for
Capital Projects
Norby
Norby
11.03.23
06 :40 ct0 24
documentation is not
documentation surrounding Capital's
documentation
09.30.24
current
contract/agreement origination and project
of procedures or
(Extended)
management processes.
updates
2
There is a need to
2023 Capital Projects Design -only Audit
2
There is an opportunity for Capital to formalize and
1
Segregation of
Capital Projects
Norby
Norby
11.03.23
o6�3A24
standardize Capital
enhance reporting of capital project activity so that
duties
09.30.24
Projects' reporting to key
there is a formal source of project -related reporting
(Extended)
stakeholders
flowing through the Division to management and
executive management.
3
Agreement/contract drafts
2023 Capital Projects Design -only Audit
3
Capital shares and edits contract/agreement drafts
2
General process
Capital Projects
Norby
Norby
11.03.23
06.30i4
are edited and shared
internally through email, which may cause version
and/or control
09.30.24
internally via email, which
control issues.
improvements
(Extended)
may lead to version
control issues
4
Key stakeholders do not
2023 Capital Projects Design -only Audit
4
Purchasing does not regularly report details surrounding
2
Automation
Finance
Mizuno
Leiber
11.03.23
06.30 24
receive regular
the status of contract/agreement processing efforts to
opportunities
09.30.24
contract/agreement
stakeholders across the District, which may impact
(Extended)
processing status updates
projects that have more compressed timelines such as
District emergencies and special needs.
Closed in 2024
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 10 of 50
Page 9 of 12
1
September 3, 2024
2024 Permitting
Resource Management
Review and Biannual
Findings Reporting
Administration Committee
Benjamin Johnson
Internal Auditor I Diversity, Equity, and Inclusion Officer
Services Provided
Assist with submission of permit
applications
Review applications and plans
Collect permit fees
Responsive customer service
Generate activity reports
Educate the public
k
Attachment 3
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 11 of 50 1
PAUnkruent 3
Team Dynamics
Five permitting team members when
fully staffed
Collaborate with various internal
workgroups and local agencies
Strong focus on customer service and
often assist other workgroups
Oracle system rollout has been
challenging
Leadership is strong and staff are
dedicated/hardworking
3
Project Scope
Oracle implementation
Processing time management
Plan reviews and encroachment
verifications
Customer service interactions
Permit issuance
Public mainline extensions
Real property agreements coordination
Cash management coordination with
Accounting
4
1,
�o
Ali
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 12 of 50 2
PAU.sr.krne n t 3
Public Engagement Metrics -VVI ''
The District annually outperforms sister agencies in the
following key areas: Over 1,800 permits finalized
Over 350 permits per FTE completed
I
3,000 new applications processed
The permitting team annually fields:
3,000 in -person visits
15,000 emails
5
Challenges and
Opportunities
Challenges
Oracle implementation
Rising number of redevelopments
Staffing and related resources
Opportunities
Future consideration of resource allocation
Online presence
Streamlined Oracle system
L
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 13 of 50 3
PAUnkruent 3
Biannual Findings
Report: End of Q2 2024
As of August 19, 2024, all findings,
except four identified in phase I of the
capital projects audit, have been closed:
1— Update formal procedures
2 — Enhance reporting
3 — Contract drafting single source of truth
4 — Reporting Procurement's contract
origination timeline
All current findings have an extended
due date of September 30, 2024.
I
r t N ,,
M
September 3, 2024 Regular ADMIN Committee Meeting Agenda Packet - Page 14 of 50 4