HomeMy WebLinkAbout03.f. Amend Professional Engineering Agreement with Carollo Engineers for the Design of the A-Line Sewer Relocation for Contra Costa Transportation Authority (CCTA) DP 100050Page 1 of 4
Item 31
DCENTRALSAN
MEETINGDATE: JULY15,2024
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
SUBJECT: REVIEW DRAFT POSITION PAPER TO AUTHORIZE THE GENERAL
MANAGER TO EXECUTE AN AMENDMENT TO THE PROFESSIONAL
ENGINEERING AGREEMENT WITH CAROLLO ENGINEERS, INC. IN THE
AMOUNT OF $780,000 FOR AN AMENDED AMOUNT NOT TO EXCEED
$1,880,000 FOR THE DESIGN OF THE A -LINE SEWER RELOCATION FOR
CONTRA COSTA TRANSPORTATION AUTHORITY (CCTA), DISTRICT
PROJECT 100050
SUBMITTED BY: INITIATING DEPARTMENT:
DANA LAWSON, SENIOR ENGINEER ENG-PDS-DIVISION MANAGER
REVIEWED BY: DANEA GEMMELL, PLANNING AND DEVELOPMENT SERVICES DIVISION
MANAGER
GREG NORBY, DEPUTY GM - ENGINEERING & OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
ISSUE
The Board of Directors (Board) authorization is required for the General Manager to execute amendments
to professional engineering agreements in an amount greater than $100,000 for agreements with an
original amount less than $2,000,000, in compliance with Board Policy 37, item 9b.
BACKGROUND
On September 7, 2023, the Board authorized the General Manager to execute a professional engineering
agreement in an amount not to exceed $1,100,000 as related to District Project (DP) 100050, A -Line
Sewer Relocation for CCTA. This effort is required by Contra Costa Transportation Authority (CCTA) to
accommodate their final phase of the improvements to the State Route 4/ Interstate 680 interchange and
will be reimbursed by CCTA, as required by California Streets and Highway Code Section 702. Utility
Agreement No. 633 between CCTA and Central San was executed on May 17, 2023 with an estimated
reimbursement amount of $1,907,032.
This amendment to the professional engineering agreement with Carollo Engineers will extend the design
of the relocation to the Treatment Plant's Influent Structure to obtain adequate clearance under Grayson
Creek where the low -flow channel has eroded below the flood control channel's design in 1960. When the
July 15, 2024 Special EOPS Committee Meeting Agenda Packet - Page 74 of 85
Page 2 of 4
A -Line Relief I nterceptor was installed in the early 1990s, it had to clear the eroded low -flow channel which
required lowering the invert elevation of the headworks intake. The relocation of the A -Line will take
advantage of this lower invert. This will extend the length of relocation/replacement from 2,000 LF to
approximately 3,500 LF and ensure that Central San is ensure that the system remains self flushing under
gravity flows.
After an initial investigation to verify this concept, Carollo Engineers prepared a scope and budget revision
which would increase the total agreement amount from $1,100,000 to $1,880,000. While this revised
consulting budget is within the Utility Agreement amount, there will also be internal staff time for project
management and coordination, so Central San will work with CCTA to confirm if they wish to execute an
amendment now or utilize the Utility Agreement terms, which allows for reimbursement of costs in excess
of the previously agreed upon amount in the final reimbursement claim package.
California Environmental Quality Act (CEQA)
At its meeting on June 15, 2023, the Board found this project to be exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board may decline authorization of the amendment. This is not recommended as the amendment is
necessary to provide a comprehensive design to ensure the relocation provides comparable operation;
meaning, the relocation has to extend from the upper reach on Berry Drive all the way to the Treatment
Plant's Influent Structure to obtain adequate clearance under Grayson Creek to ensure that the system
remains self flushing under gravity flows.
FINANCIAL IMPACTS
While this project is included in the FY 2024-25 Budget on page 244, there will be no net impact to the
Capital I mprovement Budget (CI B) or 10-Year Capital I mprovement Plan (Cl P) since the costs will be
reimbursed by CCTA as outlined in the Utility Relocation Agreement.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its special meeting on July 15, 2024,
and recommended
RECOMMENDED BOARD ACTION
Staff recommends the Board authorize the General Manager to execute an amendment to the
professional engineering agreement with Carollo Engineers, I nc. in the amount of $780,000 for an
amended amount not to exceed $1,880,000 for design of the A -Line Sewer Relocation for Contra Costa
Transportation Authority (CCTA), District Project 100050.
Strategic Plan Tie -In
Tie -In
GOAL ONE: Customer and Community
Strategy 3 - Build neighborhood and industry relations
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3 - Maintain financial stability and sustainability
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally
July 15, 2024 Special EOPS Committee Meeting Agenda Packet - Page 75 of 85
Page 3 of 4
ATTACHMENTS:
1. Map
July 15, 2024 Special EOPS Committee Meeting Agenda Packet - Page 76 of 85
tL
WON
Too
-0 Raymond Dr
S Temple Dr
OPW
Ix
_
via
ALIAP
w On
tit
III woof
IMM quill
.101
'
Sally Ride Dr
dw
----_-- --__--- ' - _---__---'- _ '-- .