Loading...
HomeMy WebLinkAbout03.j. ADVISE THE BOARD OF THE CLOSEOUT OF THE TREATMENT PLANT PIPING RENOVATIONS, PHASE 4, DISTRICT PROJECT 7216Central Contra Costa Sanitary District ' BOARD OF DIRECTORS POSITION PAPER Board Meeting Dale: June 17, 2~1 ~ No.: 3. j . Consent Calendar Type of Action: INFORMATIONAL Subject: ADVISE THE BOARD OF THE CLOSEOUT OF THE TREATMENT PLANT PIPING RENOVATIONS, PHASE 4, DISTRICT PROJECT 7216 Submitted By: Initiating Dept./Div.: Clint T. Shima, Engineering/Capital Projects Provisional Associate Engineer REVIEWED AND RECOMMENDED FOR BOARD ACTION: C. Shima A. Antkowiak A. Farrell mes M. elly, eneral Manager ISSUE: All work has been completed on the Treatment Plant Piping Renovations, Phase 4, District Project 7216, and this project can now be closed out. RECOMMENDATION: Close out the project. FINANCIAL IMPACTS: This closeout will result in approximately $165,666 being returned to the Treatment Plant Program. Attachment 1 shows the project expenditures by category. ALTERNATIVES/CONSIDERATIONS: Not applicable. BACKGROUND: During the construction of the secondary treatment facilities in the early 1970s, numerous piping systems were installed throughout the treatment plant. These pipes carry the processed wastewater, sludge, steam, air, and other utility services between the various sections of the treatment plant. These pipes have been in place for over thirty years and are showing signs of deterioration. For example, the discharge piping in the north return activated sludge (RAS) pumping station has developed leaks through the pipe wall requiring patching by maintenance staff. On other more recently constructed piping systems, such as the ash collection and transport piping, leaks have developed as the ash has eroded through the steel pipe walls (see Attachment 2 for Project location). Phase 4 of the Piping Renovations Project focused on replacing the discharge piping at the RAS pumping station, the north and south ash pipelines from the furnaces up to the filters on the third floor of the Solids Conditioning Building (SCB), the polyvinyl chloride (PVC) piping on the sodium hydroxide storage and feed system at the Ultraviolet (UV) Facility, and two corroded drain lines in the SCB. In addition, six influent channel slide gates were replaced at the UV Facility. N:\PESUP\POSition Papers\Shima\7216-pp-closeoutFinal.doc Page 1 Of 4 POSITION PAPER Board Meeting Date: June 17, 2010 subjece ADVISE THE BOARD OF THE CLOSEOUT OF THE TREATMENT PLANT PIPING RENOVATIONS, PHASE 4, DISTRICT PROJECT 7216 On March 5, 2009, the Board of Directors authorized the award of a construction contract for this work to C. Overaa and Company. The Contractor was issued a Notice to Proceed that was effective April 24, 2009, with a completion date of January 24, 2010. The project was accepted by the Board on December 3, 2009. The original construction contract amount was $810,000. There were seven construction change orders issued in the total amount of $31,984. Change orders were issued to replace additional deteriorated pipe. The total amount paid to the Contractor was $841,984. The total authorized budget for the project was $1,350,000, which included a contingency of $162,000. The total project cost was $1,184,334, which is approximately 12 percent less than the budgeted amount. The project closeout will result in $165,666 being returned to the Treatment Plant Program (see Attachment 1 for Expenditure Summary). RECOMMENDED BOARD ACTION: This item is presented to the Board of Directors for information. No action is necessary. N:\PESUP\Position Papers\Shima\7216-pp-closeoutFinal.doc Page 2 of 4 ATTACHMENT1 EXPENDITURE SUMMARY TREATMENT PLANT PIPING RENOVATIONS, PHASE 4 DISTRICT PROJECT 7216 ACTIVITY COST Total Budget $1,350,000 Construction Contract $810,000 Change Orders $31,984 Change Order % of Construction 3.8% Total Construction Amount $841,984 Engineering, Design, CM, Admin. $342,350 Engineering, Design, CM, Admin. - % of Construction 36.6% TOTAL PROJECT EXPENDITURES $1,184,334 Amount to be Returned to Treatment Plant Program $165,666 N:\PESUP\Position Papers\ShimaV216-pp-closeoutFinal.doc Page 3 of 4 ATTACHMENT2 TREATMENT PLANT PIPING RENOVATIONS, PHASE 4 DISTRICT PROJECT NO. 7216 SITE MAP FIOLOr1A EN8l1 'R 9017tH SOLIDS CONDITIONING BUILDING ~ NORTH SOUTH GLARIFIERS CLARIFIERS e 0 UV ~ci17~'7iir~~ ~ '^: } J+-~- D 1m ~ Ifff .. ` ~~. \~~~\ '~~ TUNNELS '~. ~1 .*~\ ~\.`,t ~-j~ L ~ ~-~ i~ ~ 1j ~...~` ~` o ~ ~~7~~/ I ~~~.. N:\PESUP\Position Papers\Shima\7216-pp-closeoutFinal.doc Page 4 of 4