Loading...
HomeMy WebLinkAbout03.k. ADVISE THE BOARD OF THE CLOSEOUT OF THE LAFAYETTE SEWER' Central Contra Costa Sanitary District ' BOARD OF DIRECTORS POSITION PAPER Board Meeting Date: AprII 1, 2010 No.: 3.k. Consent Calendar Type of Action: INFORMATIONAL subject: ADVISE THE BOARD OF THE CLOSEOUT OF THE LAFAYETTE SEWER RENOVATIONS, PHASE 5, DISTRICT PROJECT 5977 Submitted By: Initiating Dept./Div.: Michael J. Penny, Associate Engineer Engineering/Capital Projects REVIEWED AND FOR BOARD ACTION: enny A. Antkowiak ecki A. Farrell Jame General Manager ISSUE: All work has been completed on the Lafayette Sewer Renovations, Phase 5, District Project 5977, and this project can now be closed out. RECOMMENDATION: Close out the project. FINANCIAL IMPACTS: This closeout will result in approximately $4,000 being returned to the Collection System Program. Attachment 1 shows the project expenditures by category. ALTERNATIVES/CONSIDERATIONS: Not applicable. BACKGROUND: The Lafayette Sewer Renovation, Phase 5 Project included renovating approximately 10,600 feet of 6-inch to 15-inch sewer in Lafayette and Moraga. Both open-cut and pipe-bursting methods were used. In addition, one emergency project and one urgent project were added to this project. The emergency repair was the replacement of a leaking creek crossing and adjacent piping in Lafayette off.of Mosswood Drive. In addition to replacing the creek crossing pipe, about 15 feet of the downstream sewer was replaced to eliminate a severe belly,. and a new manhole was installed upstream of the creek crossing to facilitate bypass pumping for replacement of the creek crossing pipe. The Board declared the emergency on November 13, 2008. The emergency work was completed on December 12, 2008, and the Board terminated the declared emergency on December 18, 2008. The total cost of the emergency work was $76,317. The urgent project was the pipe bursting of a 6-inch sewer on Contra Costa Boulevard in Pleasant Hill at Crescent Drive. The line was damaged by the installation of two grounding rods for a PG&E vault. On May 5, 2008, PG&E removed the two grounding rods that had been driven through the 6-inch sewer. The location of the damage was underneath a PG&E vault, and the sewer in this location is under ared-colored N:\PESUP\Cbradley\POSITION PAPERS\Penny\5977 Closeout PP,doc Page 1 of 3 POSITION PAPER Board Meeting Date: April 1, 2010 Subject. ADVISE THE BOARD OF THE CLOSEOUT OF THE LAFAYETTE SEWER RENOVATIONS, PHASE 5, DISTRICT PROJECT 5977 concrete sidewalk with six trees and two PG&E vaults. It was impractical to excavate for an open-cut repair. CSO attempted to repair the damage internally using its Perma-Liner cured-in-place pipe point-repair method with limited success. CSO was maintaining this line on a two-week basis and the line was getting progressively worse. CSO requested Engineering replace the 6-inch pipe. The pipe-bursting repair was added to this project as the Contractor was already doing extensive pipe bursting. The total cost of the urgent work was $41,200. District Risk Management staff is currently negotiating with PG&E for reimbursement of a portion of the construction costs. On July 3, 2008, the Board of Directors authorized the award of a construction contract for this work to K. J. Woods Construction, Inc. The Contractor was issued a Notice to Proceed that was effective August 18, 2008, with a completion date of February 6, 2009. The project was accepted by the Board on April 2, 2009. The original construction contract amount was $1,238,999. There were five (5) construction change orders, covering 16 separate items, issued in the total amount of $263,079. The total amount paid to the Contractor was $1,428,104. The total authorized budget for the project was $1,980,000, which included a contingency of $263,000. The total project cost was $1,976,059, which is approximately 0.2 percent less than the budgeted amount. The project closeout will result in $3,941 being returned to the Collection System Program (see Attachment 1 for Expenditure Summary). RECOMMENDED BOARD ACTION: This item is presented to the Board of Directors for information. No action is necessary. N:\PESUP\Cbradley\POSITION PAPERS\Penny\5977 Closeout PP.doc Page 2 of 3 ATTACHMENT1 LAFAYETTE SEWER RENOVATIONS, PHASE 5 DISTRICT PROJECT 5977 EXPENDITURE SUMMARY ACTIVITY COST Total Budget $1,980,000 Construction Contract $1,238,000 Change Orders • $263,079 Change Order % of Construction 21 Total Construction Amount $1,501,079 Engineering, Design, CM, Admin. $400,844 Engineering, Design, CM, Admin. - % of Construction 27% Right-of-Way Acquisition $93,111 Right-of-Way Acquisition - % of Construction 6% TOTAL PROJECT EXPENDITURES $1,976,059 Amount to be Returned to Collection System Program $3,941 N:\PESUP\Cbradley\POSITION PAPERS\Penny\5977 Closeout PP.doc - Page 3 Of 3