HomeMy WebLinkAbout06.a.3) Handout-CSOD Construction Updatel o.4 4Nonleut
CSOD Facility
Construction Update
November 4, 2010
CSOD Administration, Crew and
Warehouse Facility
• Original Contract Time
• Time added
• Current Contract Time
• Time Elapsed
• Construction Delay
547 days
23 days
570 days
298 days - 52%
32 days
CSOD Administration, Crew and
Warehouse Facility
• Original Contract Amt $8,455,000
• Change Orders
• Total Project Amt
• Total Paid to BCI
15 / $105,118 / 1.2%
$8,560,118
$2,519,387
Issues of Concern
• Construction is behind schedule
— CCCSD and Contractor are evaluating
schedule to determine if adjustments to
sequence of activities or activity durations
are appropriate
• Preparing the site for winter weather
— Installed BMPs to protect against sediment
pollution in storm water runoff. Placed
aggregate base at entrance and parking