HomeMy WebLinkAbout03.f. Accept work for Hall Dr. Sewer Ren'sCentral Contra Costa Sanitary District 3. ' BOARD OF DIRECTORS POSITION PAPER Board Meeting Date: October 21, 2010 subject: ACCEPT THE CONTRACT WORK FOR THE HALL DRIVE SEWER RENOVATIONS, PHASE 2B, DISTRICT PROJECT 5932, AND AUTHORIZE FILING OF THE NOTICE OF COMPLETION Submitted By: Initiating Dept. /Div.: Munawar Husain, Associate Engineer Engineering / Capital Projects REVIEWED AND RECOMMENDED FOR BOARD ACTION: Jk 0 6L I M. Husain A. Rozul ilecki A. Farrell James M. ally, General Manager ISSUE: Construction has been completed on the Hall Drive Sewer Renovations, Phase 213, District Project 5932, and the work is now ready for acceptance. RECOMMENDATION: Accept the contract work for the Hall Drive Sewer Renovations, Phase 2B, District Project 5932, and authorize filing of the Notice of Completion. FINANCIAL IMPACTS: None related to this action. ALTERNATIVES /CONSIDERATIONS: Not applicable. Filing the Notice of Completion is advisable under the California Civil Code, Section 3093. BACKGROUND: The project work included installation of 2,175 feet of 6 -inch HDPE pipe by horizontal directional drilling and pipe- bursting, and rerouting and replumbing ten house laterals and cleanouts. The work involved trenching, shoring, manhole installation, and paving. Construction of sewers required close cooperation with customers and the City of Orinda for site access and restoration. On May 20, 2010, the Board of Directors authorized the award of a contract for the construction of the project to McNamara and Smallman Construction, Inc. The Notice to Proceed was issued on June 24, 2010. The project was constructed with two major changes. First, an error in the drawings discovered during construction required reinstalling 380 feet of main line. Changes were made to the design and construction procedures for future projects to avoid a reoccurrence of this type of error. Second, in an easement at Camino Encinas, 600 feet of main line was not constructed due to right -of -way issues. Eminent domain procedures were started for the Camino Encinas sewer, and. it will be constructed in Summer 2011. The project was substantially completed on September 17, 2010. The remaining items of work consist of minor punch -list items, which do not affect the project acceptance. N: \PESUP \Cbradley \POSITION PAPERS \Husain \5932 Accept Contract Work.doc Page 1 of 2 POSITION PAPER Board Meeting Date: October 21, 2010 Subject.. ACCEPT THE CONTRACT WORK FOR THE HALL DRIVE SEWER RENOVATIONS, PHASE 213, DISTRICT PROJECT 5932, AND AUTHORIZE FILING OF THE NOTICE OF COMPLETION Immediately upon acceptance, the Contractor is relieved of the duty of maintaining and protecting the Contract work. Guaranty and warranty periods required by the Contract and the statutory period for filing of liens and Stop Notices start on the date of acceptance by the Board of Directors. Final payment to the Contractor is made after expiration of the statutory period for filing of liens and Stop Notices, provided no liens or Stop Notices have been filed, and provided the punch -list items have been completed. The total authorized budget for the project is $1,611,470. The budget includes the cost of engineering design, construction management and inspection, testing services, change orders, and contractor services. An accounting of the project costs will be provided to the Board at the time of project closeout. It is appropriate to accept the contract work at this time. RECOMMENDED BOARD ACTION: Accept the contract work for the Hall Drive Sewer Renovations, Phase 213, District Project 5932, and authorize filing of the Notice of Completion. N: \PESUP \Cbradley \POSITION PAPERS \Husain \5932 Accept Contract Work.doc Page 2 of 2