Central Contra Costa Sanitary District
September 27, 2010
File: 8208.51.5.14
TO: HONORABLE BOARD OF DIRECTORS
VIA: JAMES M. KELLY, GENERAL MANAGER OK
ANN E. FARRELL, DIRECTOR OF ENGINEERING
TAD J. PILECKI, CAPITAL PROJECTS DIVISION MANAGER(
FROM: ALEX ROZUL, SENIOR ENGINEER
SUBJECT: CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
CONSTRUCTION PROGRESS, DISTRICT PROJECT 8208
At the September 16, 2010 Board meeting, staff reported on the construction
progress of the subject project and was asked to provide specific information on
how far the Contractor is behind schedule. The construction schedule is updated
monthly, and our consultant's analysis of the August 31, 2010, update indicates
the Contractor is 46 calendar days behind schedule, with 336 calendar days
remaining effective August 31, 2010. The Contractor is taking action to adjust
and modify planned construction activities in order to make up time on the
schedule.
Staff believes there is sufficient time (11 months) and construction activities (215)
remaining on the schedule to find opportunities to gain days on the schedule. It
should be noted that it is possible that construction progress may slip further due
to issues such as future rain delays, although that is less likely once the building
frame and exterior are completed. Staff will keep the Board updated on the
construction progress.
/cb