POSITION PAPER
Board Meeting Date: September 16, 2010
Subject: AUTHORIZE THE SUBSTITUTION OF WHITING /STILLWATER
CONCRETE CONSTRUCTION, INC., THE LISTED SUBCONTRACTOR, WITH
MCKAY AND COMPANY CONSTRUCTION, FOR THE CONCRETE WORK ON
THE CSOD ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
DISTRICT PROJECT 8208
Submitted By: Initiating Dept. /Div.:
Alex Rozul, Senior Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
`1
A. Rozul i ecki A. Farrell K. Alm elly,
rner ager
ISSUE: Bobo Construction, Inc., general contractor, has requested substitution of a
subcontractor listed on its bid forms for the CSOD Administration, Crew, and
Warehouse Facility, District Project 8208. Board of Directors' authorization is required
for the substitution.
RECOMMENDATION: Authorize substitution of the concrete subcontractor on the
CSOD Administration, Crew, and Warehouse Facility, DP 8208.
FINANCIAL IMPACTS: The proposed substitution will not result in any additional cost
to the District.
ALTERNATIVES /CONSIDERATIONS: Bobo Construction, Inc. informed the District on
August 2, 2010, that its listed subcontractor, Whiting /Stillwater Concrete Construction,
Inc., has walked off the job and can no longer perform the work due to financial
problems. Under California Public Contract Code, Section 4107, substitution of a listed
subcontractor is permitted when the subcontractor fails or refuses to enter into a
contract with the general contractor. The awarding authority must consent to the
subcontractor substitution to effect the change.
BACKGROUND: Bobo Construction, Inc. listed Whiting /Stillwater Concrete
Construction Inc. as their subcontractor for the concrete work on its bid proposal to the
District for the CSOD Administration, Crew, and Warehouse Facility Project, DP 8208.
On August 2, 2010, Bobo Construction informed the District that Whiting /Stillwater
Concrete Construction, Inc. would no longer perform the work due to financial
problems, and due to its financial difficulties the subcontractor has failed to perform the
C: \Documents and Settings \tpilecki\ Desktop \Floodcontrol \8208- WhitingSubstitution PP.doc Page 1 of 4
POSITION PAPER
Board Meeting Date: September 16, 2010
AUTHORIZE THE SUBSTITUTION OF WHITING /STILLWATER CONCRETE
CONSTRUCTION, INC., THE LISTED SUBCONTRACTOR, WITH MCKAY AND
COMPANY CONSTRUCTION, FOR THE CONCRETE WORK ON THE CSOD
ADMINISTRATION, CREW, AND WAREHOUSE FACILITY,
DISTRICT PROJECT 8208
work by walking off the job (Attachment 1). The value of Whiting /Stillwater Concrete
Construction's work was $1,255,000 or 14.8% of the contract value of $8,455,000.
In order to keep the project on schedule, Bobo Construction self - performed the
concrete work until it could find a new concrete subcontractor. On September 2, 2010,
Bobo Construction informed the District that it now seeks Board approval to contract
with McKay and Company Construction for the necessary equipment, materials, and
labor to complete the concrete work (Attachment 2). McKay and Company
Construction will perform all site concrete work including curb and gutter, slabs, and the
specialty permeable concrete work. Timely completion of the site concrete work is
crucial to winterizing the site before the onset of wet weather. McKay and Company
Construction is a local contractor with extensive experience in this type of work.
Under California Public Contract Code, Section 4107, substitution of a listed
subcontractor is permitted only in certain situations, including situations where the
subcontractor fails to perform his contract work, or becomes insolvent or the subject of
an order for relief in bankruptcy. District staff has advised Whiting /Stillwater Concrete
Construction, Inc. of the requirement to notify the District in writing within five (5)
working days of any objection to this proposed action; no objections have been
received. District Legal Counsel has reviewed this issue and concurs with staff.
RECOMMENDED BOARD ACTION: Authorize the substitution of the listed
subcontractor, Whiting /Stillwater Concrete Construction, Inc., with a different
subcontractor, McKay and Company Construction, for the concrete work for the CSOD
Administration, Crew, and Warehouse Facility, District Project 8208.
CADocuments and Settings \tpilecki\ Desktop \Floodcontrol \8208- WhitingSubstitution PP.doc Page 2 of 4
ATTACHMENT 1
BOBO CONSTRUCTION, INC.
9728 KENT STREET, ELK GROVE, CALIFORNIA, 95624
PHONE 916 -685 -2285 FAX 916- 685 -7373
Monday, August 02, 2010
Mr. Paul Seitz
Central Contra Costa Sanitary District
5019 Imhoff Place
Martinez, Ce 94553
RE: General
Document Number GEN -008
CSOD Administration, Crow and Warehouse facility - 8208
Dear Mr. Seitz,
This letter is to inform you that Whiting Concrete has walked off the job and will not be
completing the concrete portion of the project. As of now Bobo Construction Inc is self performing the
concrete work in order to keep the project moving forward and we Intend on signing up another concrete
contractor to replace Whiting Concrete.
Respectfully,
Chris Baker
Page 3 of 4
ATTACHMENT 2
BOBO CONSTRUCTION, INC.
9728 KENT STREET ELK GROVE, CA 95624
PHONE (916) 685 -2285
FAX (916) 685 -7373
Thursday, September 02, 2010
Mr. Paul Seitz
Central Contra Costa Sanitary District
5019 Imhoff Place
Martinez, Ca 94553
CSOD Administration, Crew and Warehouse facility -8208
Mr. Seitz,
Please be advised that Bobo Construction Inc. will be using the following subcontractor to complete the
site concrete:
McKay & Co.
4095 Pacheco Blvd
Martinez, Ca, 94553
925 -229 -8900 fax 925 - 229 -8938
Lic # 623129
7
Respectfully,
eoz j
Chris Baker /
Page 4of4