HomeMy WebLinkAbout08.a.1) Authorize Execution of Agmt. with Complete Project Solutions, Inc.Central Contra Costa Sanitary District
X��k BOARD OF DIRECTORS
POSITION PAPER
Board Meeting Date: September 2, 2010 No.:
Type of Action: AUTHORIZE AGREEMENT
Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH COMPLETE PROJECT SOLUTIONS, INC. FOR PROFESSIONAL
ENGINEERING SERVICES FOR PRELIMINARY DESIGN FOR THE SEISMIC
UPGRADES FOR THE PUMP AND BLOWER BUILDING, DISTRICT PROJECT 7291
Submitted By: Initiating Dept /Div.:
Nathan Hodges, Assistant Engineer Engineering / Capital Projects
REVIEWED AND RECOMMENDED FOR BOARD ACTION:
/t!'
_ T
Is T -
T�,
N. Hodges
B. Than�T.
Pilecki
A. Farrell Ja .Kelly,
General Manager
ISSUE: Board of Directors' authorization is required for the General Manager to
execute a professional services agreement in an amount greater than $50,000.
RECOMMENDATION: Authorize the General Manager to execute a professional
services agreement with Complete Project Solutions, Inc. with a cost ceiling of $60,000
for preliminary design work.
FINANCIAL IMPACTS: This preliminary design work is intended to more accurately
define potential costs for the design and construction of retrofits to the Pump and
Blower Building (PBB) to meet current seismic codes. Preliminary estimates are that
the construction of needed retrofits would cost in the $2 million range for the PBB. The
final design costs will depend on the type of retrofit design selected.
ALTERNATIVES /CONSIDERATIONS: The District could elect not to pursue this
preliminary design work. This is not recommended, because our preliminary analysis
indicates that significant damage could occur to the PBB in the event of a large
earthquake (magnitude of 6.7) on the Concord fault. If the project is to move forward,
outside consultants must be used because District staff does not have this specialized
expertise.
BACKGROUND: Design of structures to withstand forces generated by earthquakes is
a field which continues to evolve each time there is a significant seismic event. After
each such event, structural engineers review the forces and resultant damages and
reanalyze current codes. As a result of the Northridge Earthquake in 1994, significant
changes were recommended for the then current building codes. In January 2008,
California adopted updated building codes. Based on the knowledge that significant
changes in seismic codes had occurred, District staff determined that it would be
prudent to conduct a seismic analysis of District facilities.
N: \PESUP \Position Papers\ Hodges \7291_PBPredesign_CPS.doc Page 1 of 3
POSITION PAPER
Board Meeting Date: September 2, 2010
Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH COMPLETE PROJECT SOLUTIONS, INC. FOR PROFESSIONAL
ENGINEERING SERVICES FOR PRELIMINARY DESIGN FOR THE SEISMIC
UPGRADES FOR THE PUMP AND BLOWER BUILDING, DISTRICT PROJECT 7291
This seismic analysis has been completed. The analysis identified significant
deficiencies in many District facilities. Some improvements have been incorporated
into current capital projects such as Standby Power Facility Improvements and
HHWCF. Other facilities with deficiencies that should be addressed are the
Headquarters Office Building, Pump and Blower Building, Solids Conditioning Building
and Plant Operations Building. Staff recommends proceeding with the preliminary
design of the PBB due to the deficiencies found when compared to current seismic
design standards and the potential for significant damage to critical equipment housed
in the PBB in the event of a major quake on the Concord fault. The chance of such an
earthquake occurring is estimated to be 10 percent in the next 50 years.
The PBB has deficiencies when analyzed with the current code. The building consists
of two halves separated by a 1 -inch expansion joint. When displacements from a
design earthquake are calculated, the expected movement exceeds the 1 -inch
expansion joint. Earthquake loads are transferred from the roof diaphragm through the
steel moment frames. The frames deliver loads to the first floor diaphragm, to the
basement shear walls, and into the soil. The calculated stresses in the moment frames
exceed their design capacities. The worst case implication of this overstress would be
collapse of the PBB. A more likely scenario is that the building remains standing,
although severely damaged, after the initial earthquake. Subsequent aftershocks could
collapse the building or further damage the building.
This building houses critical treatment equipment such as primary and final effluent
pumps, aeration air blowers, and service air compressors. Treatment plant operations
would cease with the loss of any of this equipment. For this reason, additional
engineering analysis of this structure has been given high priority.
Complete Project Solutions, Inc. (CPS) has extensive experience in seismic analysis
and design and were selected to do the initial seismic analysis of all District structures.
Because of their expertise, their familiarity with District facilities and their preliminary
work on the PBB, staff recommends CPS performs the seismic preliminary design for
the PBB. A professional engineering services agreement with a cost ceiling of $60,000
has been negotiated with CPS. The scope of work also includes peer review of the
HOB Seismic Improvements preliminary design to be performed by KPFF Consulting
Engineers because CPS did the original seismic analysis of the HOB structure. This
preliminary design is the first step in the design process. The Board's Capital Projects
Committee has reviewed the proposed pre- design and recommends approval. Staff
will come back to the Board of Directors for approval of further design work when a
retrofit concept and a detailed design scope have been developed.
WPESUP \Position Papers\ Hodges \7291_PBPredesign_CPS.doc Page 2 of 3
POSITION PAPER
Board Meeting Date: September 2, 2010
Subject: AUTHORIZE THE GENERAL MANAGER TO EXECUTE AN AGREEMENT
WITH COMPLETE PROJECT SOLUTIONS, INC. FOR PROFESSIONAL
ENGINEERING SERVICES FOR PRELIMINARY DESIGN FOR THE SEISMIC
UPGRADES FOR THE PUMP AND BLOWER BUILDING, DISTRICT PROJECT 7291
The Seismic Upgrades for the Pump and Blower Building is included in the 2010 -2011
Capital Improvement Budget on pages TP -49 and TP -50. Staff has determined that
there are adequate funds available and that the expenditure requirements are
consistent with the Treatment Plant Program.
Staff has evaluated this action and concluded it is exempt from the California
Environmental Quality Act (CEQA) under CCCSD CEQA Guidelines Section 15262,
since the agreement would be used for design studies for possible future actions which
CCCSD has not approved, adopted, or funded, and the outcome of these tasks will not
have a legally binding effect on later activities. Approval of this action will establish the
Board of Directors' independent finding that the action is exempt from CEQA. The
Board of Directors further finds that CCCSD will produce appropriate CEQA compliance
documentation prior to undertaking any "project" arising from these design studies.
RECOMMENDED BOARD ACTION: Authorize the General Manager to execute a
professional services agreement with Complete Project Solutions, Inc. with a cost
ceiling of $60,000 for preliminary design of the Seismic Upgrades for the Pump and
Blower Building, District Project 7291.
NAPESUP \Position Papers\ Hodges \7291_PBPredesign_CPS.doc Page 3 of 3