SEISMIC IMPROVEMENTS
PROGRAM
Presentation to Board of Directors
September 2, 2010
Seismic Study has Identified Deficiencies
in Critical District Facilities
Concord Fault Proximity to District Facilities
Preliminary Seismic Status
• Work completed (HHWCF, Standby Power
Facility, and new CSOD Building)
• Pre - design
■ Headquarters Office Building (HOB)
■ Pump & Blower Building (PBB)
■ Defer
• Plant Operations Building (except critical works)
• Solids Conditioning Building (pending regulations)
■ 4737 Warehouse (work with Real Estate
Committee)
Headquarters Office Building (HOB)
■ Deficiency
■ Does not meet Life Safety: 2007 CBC, ASCE 41,
FEMA 351
• Flexible building structure
• Steel moment frames with wood diaphragm
■ Impact
■ Over 100 employees present
■ Disruption to customer service activity
Pump & Blower Building (PBB)
■ Deficiency
■ Does not meet Life Safety: 2007 CBC, ASCE 41,
FEMA 351
• Excessive displacements
• Steel moment frames
■ Columns over- stressed
■ Impact
■ Treatment Process: Aeration Air SteamTurbines,
Electric Blower, Primary Effluent and Final Effluent
Pumps, and Service Air Compressors.
Recommendation
■ Recommended by the Capital Projects
Committee
■ Approve the authorizations to perform seismic
pre- design for
■ Headquarters Office Building (DP 8226)
■ Pump & Blower Building (DP 7291)
■ Will return to Board with findings and determine
next steps