HomeMy WebLinkAbout16.c. Committee Minutes - Engineering & Operations 03-06-2024Item 16.c.
March 21, 2024
T O: HO NO R A B L E B O A R D O F D I R E C TO R S
F RO M :K AT I E YO UNG, S E C R E TA RY O F T HE D I S T R I C T
S UB J E C T: MA R C H 6,2024 - E NG I NE E R I NG & O P E R AT I O NS C O MMI T T E E - C HA I R
MC G I L L A ND ME MB E R W E D I NG TO N
Attached are minutes of the above C ommittee meeting.
AT TAC HM E NT S :
D escription
1. E ngineering & Operations Committee minutes 03-06-24
2. I tem 3.a. (Handout)
3. I tem 4.a. (Handout)
March 21, 2024 Regular Board Meeting Agenda Packet - Page 168 of 195
Page 1 of 28
REGULAR MEETING OF THE
CENTRAL CONTRA COSTA
SANITARY DISTRICT
ENGINEERING & OPERATIONS
COMMITTEE
MINUTES
Wednesday, March 6, 2024
8:30 a.m.
Committee:
Chair Mike McGill
Member Florence Wedington
Staff:
Roger S. Bailey, General Manager
Joan Cox, Assistant District Counsel (left after Item 3.a.)
Katie Young, Secretary of the District
Greg Norby, Deputy General Manager – Operations
Philip Leiber, Deputy General Manager – Administration
Edgar Lopez, Capital Projects Division Manager
Nancy Molina, Senior Engineer
Sasha Mestetsky, Senior Engineer
Karen DeLong, Administrative Services Assistant
Stacey Durocher, Administrative Services Assistant
1. Call Meeting to Order
Chair McGill called the meeting to order at 8:30 a.m.
2. Public Comments
None.
BOARD OF DIRECTORS:
MARIAH N. LAURITZEN
President
MICHAEL R. MCGILL
President Pro Tem
BARBARA D. HOCKETT
TAD J. PILECKI
FLORENCE T. WEDINGTON
PHONE: (925) 228-9500
FAX: (925) 372-0192
www.centralsan.org
March 21, 2024 Regular Board Meeting Agenda Packet - Page 169 of 195
Page 2 of 28
Engineering & Operations Committee Minutes
March 6, 2024
Page 2
3. Items for Committee Recommendation to Board
a. Review draft Position Paper to authorize the General Manager to execute
a construction contract change order in the amount of $405,000 with
Auburn Construction, LLC to remobilize and complete construction of the
Electric Blower Improvements, District Project 100015 and Treatment
Plant Piping Renovations, Phase 10, District Project 7369; and authorize a
budget transfer in the amount of $895,000 from the Capital Improvement
Budget Contingency.
Mr. Lopez provided an overview of the presentation included in the
agenda materials. He stated that two projects were bid under one contract
and awarded in July 2021. He explained that all improvements for the
Electric Blower project are complete, and the system is operational.
Mr. Lopez stated there will be planned shutdowns of the steam blowers
during upcoming projects but one of the major drivers of this project was
managing power during Pacific Gas & Electric (PG&E) shutdowns. The
new blowers have a soft start and are easier to control and manage under
various conditions.
Member Wedington asked if the new blowers are designed to become the
primary over steam. Mr. Lopez stated they are designed to be primary
and eventually that is the goal but that is still five to ten years out before
we consider the switch to primary.
Mr. Norby discussed the significant changes coming in electrification. The
energy profile for the plant is changing and the new blowers are a large
part of that transition for the District. There are a few things that must be
balanced and will not be easy, especially when considering how to make
these changes while maximizing the life-cycle value of current assets and
maintaining the steam driven blowers.
Chair McGill asked for a more detailed presentation to include all the
pieces and how they fit together. Mr. Norby stated that an energy roadmap
is being developed to identify all the pieces and will be presented to the
Committee at a future meeting.
Member Wedington asked if Auburn Construction, LLC has worked with
the District before. Mr. Lopez said yes, and they have been great to work
with. Chair McGill expressed concern about the way the draft Position
Paper was written, and sounded like there was some friction. He
recommended that staff try to be as transparent as possible.
March 21, 2024 Regular Board Meeting Agenda Packet - Page 170 of 195
Page 3 of 28
Engineering & Operations Committee Minutes
March 6, 2024
Page 3
Mr. Bailey asked that more information be added to the draft Position
Paper regarding demobilization. He also asked staff to include the
remaining work value or percentage.
There was a discussion regarding the construction management
consultant, Carollo Engineers, and some concern whether they were also
overbudget on their contract. Mr. Lopez stated that Carollo Engineers is
providing construction management services to the District’s Project
Manager, Nancy Molina and more information can be provided in the
Position Paper, however, no Board action for the contract is needed.
Mr. Norby stated that the Board often has questions about how the Capital
Improvement Budget contingency fund is being tracked and replenished.
Mr. Lopez stated that the Board does receive and track the contingency
account with the reports given at the Finance meeting. Staff can include
more information in the Position Papers or presentations going forward.
The Committee recommended the following changes.
• Add more details about the added construction management cost
of $430,000 to show consultant and staff costs.
• Add the total of the contingency fund and expenditures to date in
the presentation. (Post note; this was included in the draft Position
Paper)
• Add information about any problems staff experienced on the
project in the Position Paper similar to the presentation.
COMMITTEE ACTION: Recommended Board approval with the
recommended changes mentioned above.
4. Other Items
a. Receive the mid-year update on Fiscal Year 2023-24 Capital Improvement
Budget
Mr. Lopez provided an overview of the presentation included in the
agenda materials.
Mr. Bailey expressed concern about setting the rates against the target,
and that the urgency to fix this cannot be overstated.
Mr. Leiber stated that the question will be whether the Board will approve
the four percent needed now, because if the need for those funds is going
to be delayed then there is no need to increase the rates now.
March 21, 2024 Regular Board Meeting Agenda Packet - Page 171 of 195
Page 4 of 28
Engineering & Operations Committee Minutes
March 6, 2024
Page 4
A discussion ensued regarding the carry forward and budget in the current
fiscal year and the projected spending. Mr. Norby noted that the budget
plus the carry-forward funds reflected an annual spending pace higher
than what could be realistically expected. The intent is to only request
what can be spent each year and leave unneeded funds in reserve. This
pattern of overbudgeting in the early years of large capital programs is
common. Staff has been working since last budget cycle to make
necessary adjustments to close the gap and plans to continue such efforts
this year. These matters will be discussed at the April 4, 2024, Board
Financial Workshop. The new projections will also be received and
reviewed by this Committee in May.
COMMITTEE ACTION: Receive the update.
b. Hold a discussion with the Committee regarding Change Order Log.
Quarterly Reports, and Bid Schedules to compare budgeted vs. actual
costs including project status, close-outs, and status of current service
agreements
Due to time constraints, this item was not heard.
COMMITTEE ACTION: The Committee requested that this item be
postponed until the April 3, 2024 meeting.
5. Announcements
None.
6. Suggestions for Future Agenda Items
a. Receive list of upcoming agenda items and provide suggestions for any
other future agenda items
• Member McGill requested future plant tours.
COMMITTEE ACTION: Received the list and provided input to staff.
7. Future Scheduled Meetings
Wednesday, April 3, 2024 at 8:30 a.m.
Wednesday, May 1, 2024 at 8:30 a.m. (at CSO) (Special)
Wednesday, May 8, 2024 at 8:30 a.m. (Budget Review)
8. Adjournment – at 10:38 a.m.
March 21, 2024 Regular Board Meeting Agenda Packet - Page 172 of 195
Page 5 of 28
1
Electric Blower Improvements,
District Project (DP) 100015 and
Treatment Plant (TP) Piping
Renovations, Phase 10, DP 7369
Additional Budget and Change
Order Request
Engineering and Operations Committee Meeting
March 6, 2024
Edgar J. Lopez, P.E.
Capital Projects Division Manager
Two Projects Combined
1.Electric Blower Improvements:
•Three New 1MW Magnetic Bearing
Electric Blowers and Electrical Panels
•Three New Chillers
•Three New Filter Houses
•Canopy Covered Medium Voltage
Switchgear and Transformers
2
1
2
Attachment 1
Handout Item 3.a.
March 21, 2024 Regular Board Meeting Agenda Packet - Page 173 of 195
Page 6 of 28
2
3
New Electric Blowers
New Blower System Improvements
4
3
4
March 21, 2024 Regular Board Meeting Agenda Packet - Page 174 of 195
Page 7 of 28
3
Second Project Background
2. TP Piping Renovations, Phase 10:
•Replaced Scum Piping, Gates, and Electrical for
Both North and South Quad Clarifiers
•Replaced Centrate Piping in the Solids
Conditioning Building
•Replaced 3W HP and LP Piping
•Replaced Hydropneumatic 1W Tank, Piping,
Compressor, and Electrical Panels
•3WHP Pumps 1 and 2 Variable Frequency Drive
(VFD) Replacements
•Boiler Chemical Piping Replacement
•Hypo Site 1 Improvements
•Replace Primary Effluent VFD
5
•General Contractor: Auburn Constructors, LLC (Auburn)
•Construction Contracts: $ 13,104,300
•Contingency: $ 1,440,700 (10.9%)
•Construction Costs: $ 14,545,000 (100%) A
•Construction Management: $ 2,250,000 (15.5%) B
•Prebid Expenditures (Design): $ 2,050,000 (14.1%) C
Total Estimated Project Budget:$ 18,845,000 (A+B+C)
6
Awarded Project Budget July 2021
5
6
March 21, 2024 Regular Board Meeting Agenda Packet - Page 175 of 195
Page 8 of 28
4
•Construction Contracts: $13,104,000 ($800K remains)
•Contingency Approved: $1,440,700 (98% allocated)
•Change Orders:
•Agreed Extra Work at Roughly $1,333,000 To Date
•$450,000 of Costs Being Reviewed
•Time Extensions, Auburn Demobilized on September 1, 2023
7
Contract Status Today
Current Plan to Finish
•Auburn Demobilized after Blowers
Commissioned
•Waiting for Electrical Gear to Arrive and
Schedule Work after April
•Issue a Change Order to Remobilize and
Complete the Remaining Work
•All Equipment Must Be Onsite Prior to
Moving Forward to Be More Efficient and
Cost Effective
•Major Work includes Hypo Site 1
Improvements and Primary Effluent VFD
Replacement
8
7
8
March 21, 2024 Regular Board Meeting Agenda Packet - Page 176 of 195
Page 9 of 28
5
Major Contract Work Items Remaining
9
Change Order Scope
Total Cost of $405,000 and Includes:
•Mobilization and Demobilization Costs
•Costs for Subcontractors, Such as Coatings
•Costs of Labor and Installation Equipment
•Insurance and Bonding Costs
•Extended Time to Complete the Work within
90 Calendar Days
•Weather Related Construction Constraints
•Prevents Future Claims
10
9
10
March 21, 2024 Regular Board Meeting Agenda Packet - Page 177 of 195
Page 10 of 28
6
•Change Order: $ 405,000 *
•Additional Construction Management: $ 430,000 **
•Contingency to Close Out: $ 60,000
•Total Budget Needed:$ 895,000
•Original Completion Date: November 1, 2022
•Estimated Completion Date: August 1, 2024 (20 mo.)
* Change order costs of $405K and $800K contract work remaining, total of $1.2 million.
** CM budget overspent by $230,000 to date due to extended construction time.
11
Overall Budget Request
Reasons for Extended Time
Major Electrical Equipment
Procurement
•Electric Blower Improvements
•MV Switchgear
•Busway
•Selector Panel
•TP Piping Renovations, Phase 10
•VFDs (3)
•Motor Control Centers (3)
12
11
12
March 21, 2024 Regular Board Meeting Agenda Packet - Page 178 of 195
Page 11 of 28
7
Reasons for Extended Time
and Project Costs
•COVID
•Supply Chain Issues
•Operational Constraints and
Coordination
•Complex Project
•Specialized Equipment
•Temporary Equipment Used
•Change Orders for Additional Work
•Longer Duration for Construction
Management Costs
13
•Construction Contracts: $ 13,104,000
•Change Orders: $ 1,738,000 (13.3%)
•Contingency Close Out: $ 60,000
New Construction Costs: $ 14,902,000 (100%)
•Construction Management: $ 2,686,000 (18.0%)
•Prebid Expenditures: $ 2,050,000 (13.8%)
$ 19,638,000 (4.2% Overrun)
14
Revised Project Budget
13
14
March 21, 2024 Regular Board Meeting Agenda Packet - Page 179 of 195
Page 12 of 28
8
Bid Results and Initial Cost Savings
15
Recommended Board Actions
Staff recommends the following:
1.Authorize the General Manager to execute a construction
contract change order in the amount of $405,000 with Auburn
Constructors, LLC to remobilize and complete the Electric
Blower Improvements, District Project 100015 and Treatment
Plant Piping Renovations, Phase 10, District Project 7369; and
2.Authorize a budget transfer in the amount of $895,000 from
the Capital Improvement Budget Contingency to fund the
Project.
16
15
16
March 21, 2024 Regular Board Meeting Agenda Packet - Page 180 of 195
Page 13 of 28
9
Questions?
17
17
March 21, 2024 Regular Board Meeting Agenda Packet - Page 181 of 195
Page 14 of 28
1
Fiscal Year (FY)
2023-24 Capital
Improvement Budget
Mid-Year Update
Engineering & Operations Committee
Meeting
Edgar J. Lopez, P.E.
Capital Projects Division Manager
March 6, 2024
FY 2023-24 Capital Improvement Budget with Current
Expenditures as of 12/31/23 (November Billings)
2 2
% Actual
Budget Spent
to Date
Actual
Expenditures
Approved
Expenditures*Program
23%$15,613,585$67,604,000Collection System (CS)
23%$14,789,229$65,697,622Treatment Plant (TP)
26%$1,986,713$7,596,181General Improvements
37%$2,430,893$6,558,658Recycled Water
24%$34,820,420$147,456,461Totals:
* Includes FY 2024 and carry forward from FY 2023
1
2
Attachment 1
Handout Item 4.a.
March 21, 2024 Regular Board Meeting Agenda Packet - Page 182 of 195
Page 15 of 28
2
Collection System – Sewer Renovation and Pump Station
Projects
3 3
In Construction
•Pleasant Hill, Phase 2 – 6,600 feet of sewers (75% complete)
•Downtown Walnut Creek Locust – 1,500 feet of sewers (40% complete)
•Walnut Creek, Phase 16 – 11,000 feet of sewers (97% complete)
•Martinez, Phase 7 – 6,200 feet of sewers (100% complete)
•Martinez, Maltby, Fairview, San Ramon Pump Stations Replacement ongoing
•Martinez Urgent Force Main (FM) Replacement – construction this spring
•Urgent projects as needed
In Design
•Bid projects from Collection System Sewer Renovation, Phase 2, include the
next phases of Orinda, Walnut Creek, Pleasant Hill, and Lafayette
•Final design of abandonment of Buchanan Lift Stations
Pleasant Hill, Phase 2
44
3
4
March 21, 2024 Regular Board Meeting Agenda Packet - Page 183 of 195
Page 16 of 28
3
Downtown Walnut Creek Locust
5
Easement WorkPipebursting
Open Trench
Walnut Creek, Phase 16
6
Open CutOpen Cut
Cured-in-place pipe
6
5
6
March 21, 2024 Regular Board Meeting Agenda Packet - Page 184 of 195
Page 17 of 28
4
Martinez, Phase 7
Easement Work Easement Work
77
Martinez Urgent FM Replacement
Easement Work Easement Work
88
7
8
March 21, 2024 Regular Board Meeting Agenda Packet - Page 185 of 195
Page 18 of 28
5
Pump Station Upgrades
9 9
Phase 1 (Completed)
•Moraga
•Orinda Crossroads
•Flush Kleen
Phase 2 (Ongoing)
•San Ramon
•Fairview
•Maltby
•Martinez
Pump Station Upgrades, Phase 2A - Maltby
1010
9
10
March 21, 2024 Regular Board Meeting Agenda Packet - Page 186 of 195
Page 19 of 28
6
Pump Station Upgrades, Phase 2A - Fairview
1111
Pump Station Upgrades, Phase 2B - Martinez
1212
11
12
March 21, 2024 Regular Board Meeting Agenda Packet - Page 187 of 195
Page 20 of 28
7
Pump Station Upgrades - San Ramon
1313
Other CS Projects and Items to Come
Projects in Process
•Planning phase work for Large Diameter Pipeline Program
and update to the Collection System Master Plan
•39-inch sewer crossing Grayson Creek being evaluated
•Caltrans relocation of the A-line Sewer Interceptor
•Cedar Lane Sewer Modifications Project in Orinda
•Force main assessments
1414
13
14
March 21, 2024 Regular Board Meeting Agenda Packet - Page 188 of 195
Page 21 of 28
8
15
Solids Handling Facility Improvements,
Phase 1A (Phase 1A) Construction
•Contractor: C. Overaa & Company
•Contract Price: $126,288,000 (4% paid as of November)
•Total Estimated Project Budget: $199,964,000
•Schedule: October 1, 2023 - October 2, 2027 (4% spent)
•CDM/ArcSineDesigners and MWH Construction Manager
•Work Completed:
•Mobilized, schedule, submittals, etc.
•Site demolition for Seismic improvements ongoing.
•Utility re-routing ongoing.
•Electrical investigation and verification for submittals.
Phase 1A East Side Demo
16
15
16
March 21, 2024 Regular Board Meeting Agenda Packet - Page 189 of 195
Page 22 of 28
9
Phase 1A Utility Re-routing
17
Phase 1A Basement Floor Demo for Wet Scrubber
18
17
18
March 21, 2024 Regular Board Meeting Agenda Packet - Page 190 of 195
Page 23 of 28
10
Other Related Activities Taking Place
Major Equipment Procurement
•Updated major equipment contracts executed.
•Change orders have been executed to incorporate updates
made since bidding through the start of construction.
•Mechanical components have been released for fabrication
with vendors. Control shop drawings being coordinated
and finalized.
Staffing up with internal and outside resources
1919
Electric Blowers Improvements
Filter Door Modification
Blower 4 Commissioning
20
19
20
March 21, 2024 Regular Board Meeting Agenda Packet - Page 191 of 195
Page 24 of 28
11
Piping Renovations Phase 10
Hypo Site 1 and PE Pump
VFD Replacement
21
Filter Plant and Clearwell Improvements, Phase 1A
Substation & Electrical Bldg. – Busway Issues
Tracer Testing
22
21
22
March 21, 2024 Regular Board Meeting Agenda Packet - Page 192 of 195
Page 25 of 28
12
RAS Piping Renovations
23
RAS Piping Renovations
Bypass Piping
24
23
24
March 21, 2024 Regular Board Meeting Agenda Packet - Page 193 of 195
Page 26 of 28
13
Aeration Basin Diffusers Replacement, Phase 1
•C. Overaa & Company (Filter Plant, Pump Stations, Solids)
•Construction Contract $12,662,000
•Total Estimated Project Budget $20,879,000
•HDR - Design Engineer (Electric Blowers, RAS Piping)
•Construction over summers 2024 (Tank 1A/1B) and 2025 (1C/1D)
•Scope
•Seismic & Structural work including baffles
•Floor slab/plenum demolition
•Aeration Diffuser installation
•Sub 32 Electrical Work
25
Aeration Basin Diffusers Replacement, Phase 1
26
25
26
March 21, 2024 Regular Board Meeting Agenda Packet - Page 194 of 195
Page 27 of 28
14
Wet Weather Improvements
Wet Weather Improvements
Basin levee Raise
27
QUESTIONS?
2828
27
28
March 21, 2024 Regular Board Meeting Agenda Packet - Page 195 of 195
Page 28 of 28