Item 3.a.
DCENTRALSAN
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: MARCH 6, 2024
SUBJECT: REVIEW DRAFT POSITION PAPER TO AUTHORIZE THE GENERAL
MANAGER TO EXECUTE A CONSTRUCTION CONTRACT CHANGE
ORDER IN THE AMOUNT OF $405,000 WITH AUBURN CONSTRUCTORS,
LLC TO REMOBILIZE AND COMPLETE CONSTRUCTION OF THE
ELECTRIC BLOWER IMPROVEMENTS, DISTRICT PROJECT 100015AND
TREATMENT PLANT PIPING RENOVATIONS, PHASE 10, DISTRICT
PROJECT 7369; AND AUTHORIZE A BUDGET TRANSFER IN THE AMOUNT
OF $895,000 FROM THE CAPITAL IMPROVEMENT BUDGET
CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
NANCY MOLINA, ASSOCIATE ENGINEER ENGINEERINGAND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
GREG NORBY, DEPUTY GENERAL MANAGER - OPERATIONS
ROGER S. BAILEY, GENERAL MANAGER
ISSUE
Authorization from the Board of Directors (Board) is required to execute a construction contract change
order in amount greater than $200,000 and to transfer funds more than $500,000 within the Capital
Improvement Program.
BACKGROUND
On July 15, 2021, the Board authorized a total estimated project budget of $18,845,000, including the pre-
purchase of $3,500,000 for three blowers, and awarded an installation and construction contract for
$9,594,300 to Auburn Constructors, LLC (Auburn) under the Electric Blower Improvements, District
Project 100015 and Treatment Plant Piping Renovations, Phase 10, District Project 7369 (Project). The
major Project components and improvements include the following:
• Electric Blower Improvements -Installation of three new 35,000 standard cubic feet per minute
electric blowers, variable frequency drives (VFDs), chillers, replacement filter houses, major
electrical components, and control equipment.
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 3 of 45
Page 2 of 13
Other facility improvements were required in the Pump and Blower Building to accommodate the
new large electrical transformers under the Project.
I n general, the new facilities will provide full redundancy for backup or emergency conditions for the
blowers and allow for safe and reliable operations with the existing standby generators during power
outages, PG&E Public Safety Power Shutoffs or planned shutdowns related to other projects like
the ongoing Solids Handling Facility Improvements, Phase 1 A.
Treatment Plant Piping Renovations, Phase 10 - Renovation and/or replacement of various piping,
instrumentation, and equipment in the treatment plant (plant) that have been identified by Engineering,
Operations, and Maintenance staff as in need of immediate replacement. This work included
replacement of the secondary scum piping system, replacement and improvements to the sodium
hypochlorite injection system, and various improvements to the potable water system. The project
also plans to replace electrical equipment such as the VFDs for the Primary Effluent pumps and
other equipment.
Construction of the Project commenced in September of 2021 and was originally scheduled to be
completed by November 1, 2022. To date, most of the improvement work in and around the Pump and
Blower Building and clarifiers has been completed.
The new electric blowers are in operation and the remaining work to be completed are related to the plant
renovation project and two long lead electrical items that have been extremely difficult to obtain as detailed
below:
New specialized and custom motor control centers that include built-in VFDs for the Hypo Chlorite
Site 1.
2. Replacement of a customized VFD for the 450 horse -power Primary Effluent Pump 3. This work
has also been postponed due to the operational constraint related to the wet weather season ending
in April -May.
Auburn demobilized from the plant as of September 2023. Staff has been working and negotiating a
change order with Auburn using the contract provisions allowed to complete the Project. After several
meetings, staff reached a cost to perform the remaining work noted above along with the associated
impacts and additional costs such as remobilization and demobilization, costs for subcontractors, time
extension, equipment, materials, and allowable costs for labor.
I n addition to the contractor's costs, staff is requesting additional funding to cover construction
management, staff, and other consultant costs previously spent and to close the project. The proposed
change order will include the time required to complete the work and will not commence until all equipment
is on site and Central San is ready for installation. As of now, Auburn is expected to return in May and
complete the work by August of this year.
CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA-
At its July 15, 2021 meeting, the Central San Board of Directors independently found that this Project is
exempt from CEQA under Central San's CEQA Guidelines Section 15301, since it involves replacement
of existing sewer facilities at substantially the same locations and with the same purpose and level of
activity as the facilities being replaced.
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 4 of 45
Page 3 of 13
ALTERNATIVES/CONSIDERATIONS
There is only one practical alternative outside staff's approach and is noted below:
Alternative 1 — Do not complete the remaining contract work with Auburn and do not authorize a
construction contract change order. This alternative would require staff to renegotiate final contract costs
and the remaining items would need to be installed by a different contractor through other contractual
solutions such as another project. The remaining work is a high priority and includes critical assets and
recommended to be replaced this summer. Auburn has purchased all equipment and other materials for
the Project, and their workmanship has been of high quality and very well received by staff. Auburn is also
already familiar with the site and the challenges associated with the construction sequence.
The change order being recommended is the most economical solution and lowers the risk of additional
delays or other complications for the needed replacement work.
FINANCIAL IMPACTS
The additional costs needed for the Project is $895,000, which includes the $405,000 change order,
$430,000 for construction management, and $60,000 for contingency to close the Project.
The current total estimated project budget is $18,845,000 and includes costs spent to date as follows:
• $13,104,000 construction costs including equipment contract (94 percent spent)
• $ 2,250,000 construction management (112 percent spent)
• $ 1,440,700 contract contingency (98% allocated for change orders)
• $ 2,050,000 planning and design (100 percent spent)
$18,845,000
Upon Board approval, the new total estimated project budget will be $19,740,000. The $895,000 funding
required will be transferred from the Capital Improvement Budget Contingency account, which has
$2,565,000 available this fiscal year.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its March 6, 2024 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
Authorize the General Manager to execute a construction contract change order in the amount of
$405,000 with Auburn Constructors, LLC to remobilize and complete the Electric Blower
Improvements, District Project 100015 and Treatment Plant Piping Renovations, Phase 10, District
Project 7369; and
2. Authorize a budget transfer in the amount of $895,000 from the Capital Improvement Budget
Contingency to fund the Project.
Strategic Plan Tie -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 5 of 45
Page 4 of 13
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Presentation
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 6 of 45
Page 5 of 13
March 6, 2024
Electric Blower Improvements,
District Project (DP) 100015 and
Treatment Plant (TP) Piping
Renovations, Phase 10, DP 7369
Additional Budget and Change
Order Request
Engineering and Operations Committee Meeting
Edgar J. Lopez, P.E.
Capital Projects Division Manager
1
Two Projects Combined
1.Electric Blower Improvements:
Three New 1MW Magnetic Bearing
Electric Blowers and Electrical Panels
Three New Chillers
Three New Filter Houses
Canopy Covered Medium Voltage
Switchgear and Transformers
2
Attachment 1
i Fkl
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 45 1
Page 6 of 13
New Electric Blowers
New Blower System Improvements
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 45 2
Page 7 of 13
Second Project Background
4
2. TP Piping Renovations, Phase 10:
Replaced Scum Piping, Gates, and Electrical for
Both North and South Quad Clarifiers
Replaced Centrate Piping in the Solids
Conditioning Building
Replaced 3W HP and LP Piping
Replaced Hydropneumatic 1W Tank, Piping,
Compressor, and Electrical Panels
3WHP Pumps 1 and 2 Variable Frequency Drive
(VFD) Replacements
Boiler Chemical Piping Replacementk4
S.
Hypo Site 1 Improvements
Replace Primary Effluent VFD
5
_PpWEREX ._
1 �
Awarded Project Budget July 2021
General Contractor: Auburn Constructors, LLC (Auburn)
Construction Contracts:
Contingency:
Construction Costs:
Construction Management:
Prebid Expenditures (Design):
Total Estimated Project Budget:
I
$ 13,104,300
$ 1,440,700 (10.9%)
$ 14,545,000 (100%) A
$ 2,250,000 (15.5%) B
S 2,050,000 (14.1%) C
$ 18,845,000 (A+B+C)
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 45 3
Page 8 of 13
Contract Status Today
Construction Contracts:
Contingency Approved:
Change Orders:
$13,104,000 ($800K remains)
$1,440,700 (98% allocated)
Agreed Extra Work at Roughly $970,000 To Date
$450,000 of Costs Being Reviewed
Time Extensions, Auburn Demobilized on September 1, 2023
Current Plan to Finish
Auburn Demobilized after Blowers
Commissioned
Waiting for Electrical Gear to Arrive and
Schedule Work after April
Issue a Change Order to Remobilize and
Complete the Remaining Work
All Equipment Must Be Onsite Prior to
Moving Forward to Be More Efficient and
Cost Effective_
Major Work includes Hypo Site 1
Improvements and Primary Effluent VFD ' �,
Replacement
E:3
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 45 4
Page 9 of 13
0
Change Order Scope
Total Cost of $405,000 and Includes:
Mobilization and Demobilization Costs
Costs for Subcontractors, Such as Coatings
Costs of Labor and Installation Equipment
Insurance and Bonding Costs
Extended Time to Complete the Work within
90 Calendar Days
Weather Related Construction Constraints
Prevents Future Claims
SI]
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 11 of 45 5
Page 10 of 13
Overall Budget Request
Change Order: $ 405,000
Additional Construction Management: $ 430,000 **
Contingency to Close Out: 60,000
Total Budget Needed: $ 895,000
Original Completion Date: November 1, 2022
Estimated Completion Date: August 1, 2024 (20 mo.)
* Change order costs of $405K and $800K contract work remaining, total of $1.2 million.
** CM budget overspent by $230,000 to date due to extended construction time.
11
Reasons for Extended Time
Major Electrical Equipment
Procurement
i
Electric Blower Improvements �.
MV Switchgear oil
Busway r�
Selector Panel
TP Piping Renovations, Phase 10►
VFDs (3) 07
Motor Control Centers (3)
12
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 45 6
Page 11 of 13
Reasons for Extended Time CIO
and Project Costs
COVID
Supply Chain Issues.,,
Operational Constraints and
Coordination —�
Complex Project
Specialized Equipment
Temporary Equipment Used..
Change Orders for Additional Work
Longer Duration for Construction
Management Costs
13
Revised Project Budget
Construction Contracts:
Change Orders:
Contingency Close Out:
New Construction Costs
Construction Management:
Prebid Expenditures:
14
$ 13,104,000
$ 1,840,000 (14.0%)
$ 60,000
$ 15,004,000 (100%)
$ 2,686,000 (17.9%)
$ 2,050,000 (13.7%)
$ 19,740,000 (4.7% Overrun)
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 45
Page 12 of 13
Bid Results and Initial Cost Savings
PROJECT NOS.: 100015 & 7369 NO. CF ADDENDA: 2 DATEFFIME: JULY 1. 2021112.00 PM
PROJECT NAME: ELECTRIC BLOWER IMPROVEMENTS&
TREATMENT PLANT PIPING RENOVATIONS. PHASE 10
PROJECTMANAGER: NANCYMOLINA
PROJECT LOCATION: 5019 IMHOFF PLACE MARTINEZ, CA
ENGINEER'S ESTIMATE: $14,000000
NO.
BIDDER
BID PRICE
1
Aubum Constructors, LLC
S9,394,390
Sacramento, Califomia
2
C. Overaa & Co.
510,462.,000
Richmond, California
3
Mountain Cascade, Inc.
510,979.,D47
Livermore, Califomia
15
A
Recommended Board Actions
Staff recommends the following:
Authorize the General Manager to execute a construction
contract change order in the amount of $405,000 with Auburn
Constructors, LLC to remobilize and complete the Electric
Blower Improvements, District Project 100015 and Treatment
Plant Piping Renovations, Phase 10, District Project 7369; and
Authorize a budget transfer in the amount of $895,000 from
the Capital Improvement Budget Contingency to fund the
Project.
16
;.f
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 14 of 45 8
Page 13 of 13
Questions?
17
March 6, 2024 EOPS Regular Committee Meeting Agenda Packet - Page 15 of 45 9