HomeMy WebLinkAbout09. Receive Pre-Audit Fiscal Year 2022-23 Capital Improvement Budget Year-End Status Report Page 1 of 7
Item 9.
CENTRALSAN
Jdf A- hom
CENTRAL CONTRA COSTA SANITARY DISTRICT
November 16, 2023
TO: HONORABLE BOARD OF DIRECTORS
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: GREG NORBY, DEPUTY GENERAL MANAGER - OPERATIONS
PHILIP LEIBER, DEPUTYGENERAL MANAGER -ADMINISTRATION
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE PRE-AUDIT FISCAL YEAR 2022-23 CAPITAL IMPROVEMENT
BUDGET YEAR-END STATUS REPORT
The Board of Directors (Board) approves the Capital Improvement Budget (CIB) and Ten-Year Plan on a
yearly basis. At fiscal year (FY) end, staff reviews and compares the final revenues and expenditures,
based on the pre-audit financial reports, to update the Board on the progress of the Capital Improvement
Program.
A public hearing was held on June 16, 2022, after which the Board adopted the FY 2022-23 Cl B. The
proposed revenue and estimated expenditures for FY 2022-23 CI B were approximately
$100,787,570 and $89,341,000 respectively. Based on the pre-audit June 2023 financial statements, the
actual revenues and expenditures including carry-forward and budget transfers are $114,365,349 and
$59,097,479 as detailed in Attachment 1 - Pre-Audit FY 2022-23 CI B Year-End Status Report.
Revenues were higher than budgeted in nearly all categories, including higher interest income due to
increased earnings rates on deposits.
As to the carry-forward, any unused project budget is carried over to the next FY until the time of project
close out. When projects close out, any unspent budget remains in the Sewer Construction Fund. In
connection with the budget development for FY 2023-24, a one-time adjustment of roughly$18.5 million to
the project carry-forward amount was made, in recognition of more realistic project timelines and the need
to reduce the carry forward. Further, approximately$3.7 million of savings from project close outs
occurred at the end of Fiscal Year 2021-22. These savings were redirected as contingency for the Capital
Program moving forward to FY 2023-24.
Attachment 2 is the presentation staff will review with the Board.
Strategic Plan re-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
November 16, 2023 Regular Board Meeting Agenda Packet- Page 37 of 175
Page 2 of 7
GOAL TWO:Environmental Stewardship
Strategy 1 -Achieve compliance in all regulations, Strategy 3- Be a partner in regional development of local water
supply
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3- Maintain financial stability and sustainability
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness, Strategy 2- Protect personnel and assets from threats and
emergencies
GOAL SIX:Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2- Execute long-term capital renewal and replacement program
GOAL SEVEN:Innovation and Agility
Strategy 1 - Leverage data analytics to become a more efficient utility
ATTACHMENTS:
1. Pre-Audit FY2022-23 Year-End Status Report
2. Presentation
November 16, 2023 Regular Board Meeting Agenda Packet- Page 38 of 175
Page 3 of 7
Attachment 1
Pre-Audit Fiscal Year (FY) 2022-23 Capital Improvement Budget (CIB)
Year-End Status Report
Sewer Construction Fund (Fund 20):
(Variance) W_
'w*
Revenue
Sewer Service Charge $65,832,492 $67,227,158 2.1%
Ad Valorem Taxes $8,332,078 $11,028,136 32.3%
Capacity Fees $4,445,000 $6,734,381 51.5%
Pumped Zone Fees $134,000 $394,764 194.6%
Developer Fees $403,000 $372,482 -7.5%
Interest Income $140,000 $2,940,938 2000.7%
City of Concord $7,500,000 $9,956,648 32.8%
Other Revenue Sources $1,000 $122,136 >100%
Sub-total Revenue $86,787,570 $98,776,643 13.8%
State Revolving Fund o
Loan Proceeds $14,000,000 $15,588,706 11.3/o
Total Revenue Projected $100,787,570 $114,365,349 13.5%
FY
t1om Carry
. . I Budget* to-Actual to-Actual
. . -
Budget
Forward
Expenditures
Collection System $36,850,000 $51,773,217 $21,653,217 -41.2% -58.2%
Treatment Plant $39,981,000 $64,666,513 $25,953,891 -35.1% -59.9%
General
Improvements $3,795,000 $7,345,517 $3,099,336 -18.3% -57.8%
Recycled Water $8,715,000 $14,131,693 $8,391,035 -3.7% -40.6%
Total $89,341,000 $137,916,940 $59,097,479 -33.9% -57.1%
Expenditures
NOTES:
*The budgeted figures exclude project close-out savings of$1,568,238. These figures also include carry forward from
past fiscal years, transfers, and a $18,500,000 reduction of carry forward.
November 16, 2023 Regular Board Meeting Agenda Packet- Page 39 of 175
Page 4 of 7
Attachment 2
November 16,2023
PRE-AUDIT FISCAL
YEAR 2022-23
CAPITAL IMPROVEMENT
BUDGET YEAR-END
STATUS REPORT -
Board Meeting
\ z -
EdgarJ.Lopez,P.E.
Capital Projects Division Manager
1
PRE-AUDIT FY 2022-23
REVENUE
Sewer Construction Fund Fund 20:
Budget Actual Budget-to-
Actual
Revenue
Sewer Service Charge $65,832,492 $67,227,158 2.1%
Ad Valorem Taxes $8,332,078 $11,028,136 32.3%
Capacity Fees $4,445,000 $6,734,381 51.5%
Pumped Zone Fees $134,000 $394,764 194.6%
Developer Fees $403,000 $372,482 -7.5%
Interest Income $140,000 $2,940,938 2000.7%
City of Concord $7,500,000 $9,956,648 32.8%
Other Revenue Sources $1,000 $122,136 >100%
Sub-total Revenue $86,787,570 $98,776,643 13.8%
State Revolving Fund $14,000,000 $15,588,706 11.3%
Loan Proceeds
Total Revenue Projected $100,787,570 $114,365,349 13.5%
1
November 16, 2023 Regular Board Meeting Agenda Packet- Page 40 of 175 1
Page 5 of 7
PRE-AUDIT FY 2022-23
EXPENDITURES
to-ActualFY 2022-23 (Variance) (Variance)
Progra. FY 2022-23 Approved FY 2922-23 Budget- Carry
udget Budget* Actual to-Actual Forward-
Expenditures
Collection System $36,850,000 $51,773,217 $21,653,217 41.2% -58.2%
Treatment Plant $39,981,000 $64,666,513 $25,953,891 -35.1% -59.9%
General $3,795,000 $7,345,517 $3,099,336 -18.3% -57.8%
Improvements
Recycled Water $8,715,000 $14,131,693 $8,391,035 -3.7% -40.6%
Total $89 341,000 $137,916,940 $59,097,479 -33.9% -57.1%
Expenditures
*Includes a reduction of carry forward of$18.5 million
1
CAPITAL PROGRAM - MAJOR REASONS FOR
PROJECT VARIANCES IN FY 2023
• Several major construction projects have started,and
funds are committed.
• Timelines are being adjusted and slower starts due to
equipment and or materials delivery.
• Schedule adjustments made moving forward in FY
2023-24.
• Carry forward budgets lowered by $18.5 million and
plan is to lower previous budgets in FY 2023-24.
1
November 16, 2023 Regular Board Meeting Agenda Packet- Page 41 of 175 2
Page 6 of 7
MAJOR PROJECT VARIANCES (42 MILLION)
- COLLECTION SYSTEM PROGRAM
Pleasant Hill Sewer
Renovation Phase 2, $8,252,000 $850,216 Construction ongoing and
District Project(DP)5991 funds committed into 2024.
Pumping Station Upgrades $14,650,000 $7,967,271 Construction ongoing and
Phase 2A, DP 8457 funds committed into 2025.
Pumping Station Construction ongoing and
Upgrades, Phase 2B, DP $3,200,000 $125,802 funds committed into 2025.
100042
1
-TREATMENT PLANT PROGRAM
Solids Handling Facility $27,518,687 $23,944,964 Construction ongoing and
Improvements,DP 7348 funds committed into 2027
UV Disinfection Planning completed,final
Replacement,DP 100012 $6,000,000 $1,608,375 design in FY 2023 to FY
2024
Aeration Basins Diffuser $7,480,000 $2,403,362 Construction ongoing and
Replacement DP 100019 funds committed into 2025
SRol
eund l v mvag Pac i ir ioyii3iil
id ay
Improvements,Phase 2, $5,700,000 $1,605,220 Planning ongoing
DP 100030
Steam Renovations, $5,000,000 $982,075 Design delayed and bid in
Phase 1, DP 100032 FY 2023
mom,
November 16, 2023 Regular Board Meeting Agenda Packet- Page 42 of 175 3
Page 7 of 7
-RECYCLED WATER PROGRAM
Filer Plant and Clearwell
Improvements,Phase $40,389,000 $36,677,028 Construction ongoing and
1A, DP 7361 funds committed into 2024
1
Questions?
- - w
owl!
November 16, 2023 Regular Board Meeting Agenda Packet- Page 43 of 175 4