Item 9.a.
LICENTRAL SAN
October 19, 2023
FROM: CHARLES MALLORY, INFORMATION TECHNOLOGY MANAGER
REVIEWED BY: PHILIP LEIBER, DEPUTYGENERAL MANAGER -ADMINISTRATION
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: REVIEW INFORMATION TECHNOLOGYAND OPERATIONS
TECHNOLOGY (IT/OT) STRATEGIC PLAN
The Information Technology/Operational Technology (IT/OT) Strategic Plan was prepared by SDI
Presence, LLC (SDI) and Brown & Caldwell (BC) for Central San. The contract for this work was
approved by the Board in August of 2021.
The IT/OT Strategic Plan scope included Central San's use of information technology to support both its
administrative and operational business processes. An similar effort completed in 2015 focused on just
the IT related processes but did not review operational technology.
With the transformation of information technology from a "back-office" productivity tool to a mission -critical,
public -facing component for the delivery of information and services, I T strategic planning is no longer just
about information technology, but rather, must also address how organizations, such as Central San, can:
• More agilely respond to new and changed requirements.
• Align IT directions and priorities with organization directions and priorities.
• More effectively manage their total cost of ownership for information technology in the face of limited
budgets.
• More effectively manage the allocation of limited user and IT resources.
• Derive greater value for their investments in information technology.
• Better leverage information technology to optimize the ability of Central San to serve the community.
• Obtain greater value for its investments in information technology.
In the first phase, the SDI/BC team prepared a holistic assessment of Central San's current use of
information technology in support of its administrative functions (budgeting, finance, and payroll), and
operational functions (planning, management, and monitoring of the treatment plant and collection
systems), the challenges that the District is experiencing, and opportunities to use information technology
to improve the delivery of services to Central San's internal user and the public.
Based on the activities performed during that assessment, the SDI/BC team delivered two key reports that
document Central San's current information technology environment. The Business Opportunities Report
provided information for Central San regarding opportunities to utilize better its existing portfolio of
October 19, 2023 Regular Board Meeting Agenda Packet - Page 77 of 127
Page 2 of 13
enterprise, business, and operational applications. The IT Services Alignment report provided information
for Central San regarding the delivery of IT services to its users. Both reports provided findings and
actionable recommendations for the District.
Based on the information provided in the Business Opportunities and IT Services Alignment reports, the
SDI/BC team developed a portfolio of proposed projects to be considered in the Technology Strategic
Plan, which provided key metrics for each project, including descriptive information about the project,
range of cost, estimated business value, estimated level of risk, and estimated level of effort. The project
portfolio was reviewed with staff and revised as needed prior to a Project Prioritization Workshop with the
consultant and staff.
The final phase in the development of the Technology Strategic Plan included a workshop for Central
San's management team in which the SDI/BC team worked with the participants to arrive at a consensus
regarding the District's most critical operational priorities, what the information technology needs are, and
to shape the plan for responding to them.
As a result of the aforementioned activity, five roadmaps by project type were also created for tactical use,
and they are as follows:
1. Supervisory Control and Data Acquisition (SCADA)
2. Enterprise Asset Management (EAM)
3. Graphical Information System (GIS)
4. Business Intelligence (BI)
5. Cybersecurity
Those roadmaps serve as the overall header/grouping for sub -projects, which are further prioritized into
categories 1,2,3, with "1" representing most important. The presentation also includes a slide which
focuses on anticipated costs and resources needed to address the scope of projects identified. However,
this is not a request for incremental resources; most of these costs are included the current O&M
spending level, and Cl P. To the extent additional resources may be needed, these would be evaluated
during future budgeting processes, or project timelines adjusted to fit within existing resources.
The attached presentation provides an overview of the process used to develop the Information
Technology/Operational Technology (IT/OT) Strategic Plan, and a summary of the key project roadmaps
listed above.
Strategic Plan Tie -In
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3 - Maintain financial stability and sustainability
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally
GOAL SEVEN: Innovation and Agility
Strategy 1 - Leverage data analytics to become a more efficient utility, Strategy 2 - Implement organization -wide
optimization, Strategy 3 - Be adaptable, resilient, and responsive
ATTACHMENTS:
1. Presentation
October 19, 2023 Regular Board Meeting Agenda Packet - Page 78 of 127
Page 3 of 13
Attachment 1
z
tr
ASDI
5 D 1 P R E S E N C E L L C
Central SAN
IV IT/OT Strategic Plan
Project Review
i October 19, 2023
! odisory services. technology 1WI.entaVi --d
f
1
• IT/OT Strategic Plan Methodology
• High-level Review of Documents
• SWOT
• Next Steps
2
October 19, 2023 Regular Board Meeting Agenda Packet - Page 79 of 127
Page 4 of 13
3
Development of the IT/OT Strategic Plan
4
October 19, 2023 Regular Board Meeting Agenda Packet - Page 80 of 127
IT/OTStmtegic Plan Development
IT/OTStrategic Plan Implementation
Whereare we now?
How can we get there?
How do we implement the plan?
where ao we need to go?
'.,
❑ BI, E , GIS, SCADA
SecurkyhR..d..pAW�k,h.p,ORoadmap
ommitment Enabling
Ro dmaps
DIAd. T Anda❑Factors
Pd❑
Project DZp-d.n.ieaProjectBlue
Well"
Devel°P
ChartersnazeUpdateIT/OTP
p.
Central5an
radIT/OTIT/OT
PreliminaryAuaumark
d°dkzakan
wwkahop
Rasfew
Plan
WorkFlana
Workpkna
BudgetRaquast
Budnass
SarVices
"Blue Well"
Compl—d Projwt
R/OT StrataglcOPPorturikae
Prolan RewurcaIT/OT
Alignment Report
ject 5akadula
Shcadula
plan
ahtw Availability
Report
RakBFinal
OnftBFinal
DraftaFinal
Legend
Qatar
ILItpn/
4
October 19, 2023 Regular Board Meeting Agenda Packet - Page 80 of 127
Project Deliverables
❑ Voice of the Customer Survey Report - April 5, 2022
❑ Business Opportunities Report - August 12, 2022
❑ IT Services Alignment Report - September 15, 2022
❑ IT/OT Strategic Plan - August 14, 2023
❑ Tactical Roadmaps
• Network Security - March 16, 2023
• SMART - March 15, 2023
• Geographic Information System (GIS) - July 19, 2023
• Enterprise Asset Management (EAM) - July 19, 2023
• Business Intelligence (BI) - July 19, 2023
• SCADA - July 19, 2023
5
Page 5 of 13
0
October 19, 2023 Regular Board Meeting Agenda Packet - Page 81 of 127
Page 6 of 13
Voice of the User Survey
Centrel sol�Dy�
rbaeaipn
C,... ;drg61
❑ Level of participation: 106
Now sadsfwd are ypu whhthe med od used to report issues tp To request
Servlar fmm IR98
to IT Best Practices
responses out of 375 employees =
a ti;earemwthetma�aama�aem`°"`yam97
asPlow
28/
satisfied am lvdh ms rodvnunicauohs th-01 the—bleshomr,
prep 1
98
whhthetimeNnessandmrnpla—of fl's f&A -upf97[ M Calk on me serAce pfowdcd? as
19077/7
Hmvsa4:rad wr@ the Oist ,, ncewareavaifeaility?
0
/ eller MEN=
❑ Overall level of satisfaction with IT
Hm ftredareyrwwitthe Peed°fthao�dte,Inta?
Support = 99%
Ho Ifted areyou with tTs warm of spam end umran ede mail? 97
naw satisfied areypu with 71 pmmmuni-I rdon IA,rriceotltagesand
upcemirtg maintenanR?
49
of✓
Hmv satisfied are ypu with the use of —Isle, wirdess, antl/or remote a—,,services,coverage, and availabllCy in the 01"n.1
sd
7s
✓�
YYY�
How Satisfied are you with the training you received for Central San',, business
appriradpnsP
85
75
✓,l
Haw satisfied are you wiIh IT's control of malware antl prevention ul wruses1
300
90
✓
Hmv SatlsfiM are you wim IT's ability to rcrover a lost file fir rc[wer damaged
filesP
SIR
95
✓_�
Hmv satisfied a e ypu with the GIS apple Wtgns antl maps provided ,,he
oisairtT
300
75
✓'i
Htrwsati5fiad aRydu whhthe GISaupppttycu-arw?
97
75
✓
How satishetl re you with IT staff, undentaMing of I" OWI&,, business
oyecnvm?
42
75
Had satisfied are ypu with Rstars under ,,d1ng of ypnr depanmenrs
Cosi ness dWan°al
89
75
✓.
Hav satisfied are you whh[he 0lsvices Rchnnmey planning effu-7 as 80
Now u %f W are you with the overate support ypu rec from ff?
y9
g5
✓
�m
7
Central SAN's Conformance to the IT Best Practices
❑ Assessment based on SDI's model for IT Best Practice conformance
I
October 19, 2023 Regular Board Meeting Agenda Packet - Page 82 of 127
Conformance
to IT Best Practices
YYYYYYYYY
YY
/ eller MEN=
YYY�
—
=M�-�YY
YYYYYYYYYY
-
YYYYYYYYY
Basic Aligned /
Integrated
ji
❑ Assessment based on SDI's model for IT Best Practice conformance
I
October 19, 2023 Regular Board Meeting Agenda Packet - Page 82 of 127
Page 7 of 13
Central SAN's Conformance to the OT Best Practices
❑ Assessment based B&C's experience in working with similar organizations
Central SAN's Conformance to GIS Best Practices
Confornnance to GIS Best Practices
m GIS Gwernanoe
4i
a Data
r�
a A -
hca5ons
C7 PP
0
o Staffing
c
O
Infrastructure
Average Conformance
Maturity Levels 3 Reactive Proactive
III
o to za 3a na ca ea m
E Less Agile More Agile z3
% of GIS Best Practices Conformance
❑ Assessment based on URISA's GIS Capability Maturity Model (GISCMM)
10
October 19, 2023 Regular Board Meeting Agenda Packet - Page 83 of 127
Conformance to Operational
Technology Best Practices
�iii�■�■
il■iiii
_
lllllllllillllllllli lllllllllillllllllli
lllllllllillllllllli a�
iii■■®■
OT Administration
iiii�■®■
_ _
iiii�■�■
- Basic
_ Aligned /
Integrated
❑ Assessment based B&C's experience in working with similar organizations
Central SAN's Conformance to GIS Best Practices
Confornnance to GIS Best Practices
m GIS Gwernanoe
4i
a Data
r�
a A -
hca5ons
C7 PP
0
o Staffing
c
O
Infrastructure
Average Conformance
Maturity Levels 3 Reactive Proactive
III
o to za 3a na ca ea m
E Less Agile More Agile z3
% of GIS Best Practices Conformance
❑ Assessment based on URISA's GIS Capability Maturity Model (GISCMM)
10
October 19, 2023 Regular Board Meeting Agenda Packet - Page 83 of 127
SWOT Analysis
Present Use of Future Use of
Information Technology Information Technology
I I I I
I I I I
Lead Tod
Opportunities
I I I I
I I I I
, I L Limit � I
I I I I
I , I
Weaknesses Lead To
I I I I
I I I I
I I I I
I I I I
r -- — — — — — — — — — — —I -- — — — — — — — — — — — —
I
11
❑ Reviewed separately for IT
and OT
❑ Primary objectives are to:
✓ Leverage strengths
✓ Remediate weaknesses
✓ Mitigate threats
✓ Realize opportunities
Page 8 of 13
SWOT Analysis — Key IT Strengths, Weaknesses, Opportunities & Threats
Strengths:
■ Since the completion of the 2015 IT Master Plan Central SAN has made
considerable progress in improving the staffing and performance of its IT
organization and this is reflected in a high level of user satisfaction with the
services provided to them.
Weaknesses:
■ Central SAN has yet to implement a sustainable approach to the enterprise
governance of information technology.
■ Central SAN has experienced challenges in the implementation of the Oracle
Fusion Cloud ERP solution.
■ The continued retention and storage of hard -copy documents.
Opportunities:
■ Full and more effective use of Oracle Fusion Cloud ERP.
■ Increased efficiencies through the continuing adoption of digital documents and
automated workflows and the digitization of hard -copy documents.
Threats:
■ Increased cost of ownership for information technology without realizing increased
value for these expenditures.
■ Limited ability to agilely respond to new and/or changed requirements.
12
October 19, 2023 Regular Board Meeting Agenda Packet - Page 84 of 127
Page 9 of 13
SWOT Analysis — Key OT Strengths, Weaknesses, Opportunities & Threats
Strengths: ■ Working toward standardization of the plant and collections pumping station electrical
switchgears, MCCs, VFDs, PLCs, PLC 1/0, and networking equipment.
■ Awareness of "smart utility," with several initiatives in progress.
■ Strong GIS program.
Weaknesses: ■ Lack of documented plans for GIS and SCADA.
■ Lack of proper utility billing system and delays in the completion of the Permitting
solution.
■ The Dynac SCADA and Dynac Historian applications are approaching obsolescence and
have limited support
Opportunities: ■ Standardize SCADA on one product, one implementation.
■ Modernize the data historian to support sharing of data from SCADA with IT systems
to improve staff efficiencies.
■ Modernize the plant control room.
■ Staff members nearing retirement will limit Central SAN's ability to support
operational applications and sustain operations.
13
14
October 19, 2023 Regular Board Meeting Agenda Packet - Page 85 of 127
Page 10 of 13
Detailed Project Planning
15
Magnitude of Effort
❑ IT Strategic and SMART Utility - 35 projects
❑ OT Strategic and GIS - 27 projects
❑ IT Tactical Projects including foundational - 22 projects
❑ OT Tactical Projects including foundational - 31 projects
16
October 19, 2023 Regular Board Meeting Agenda Packet - Page 86 of 127
How do we implement the plan?
I ❑ B4 t-4, Gn, SCApA
I
I
I
❑ [ereene aesoq.«
i spe[iadzed Nee,
Commixmenu
EAa6lirtg
DistrictTechnro-
I Roadmdps
I
❑ Estimated Prajerl
FaMdx
Pf1OYl1ief
1 1eRiess
I
I
I
Regglremenu
I
I
❑ Prgjecx Dependencies
I
I
I
Project I
I
Devetgp
Charters I
CLntYai S.
RfOT Strategic
Update
Prelimlrldry
I
I
Review
Plan Develapmlttt
R(OT
I R/OT
I
W
I WDYkptans odq.lans
Budget I
I �
I
Requests
I
Completed Prpjectl
R/OT Sbate¢ic
I
I Project Resource
I
I
5[hlbdle J
Plan
I StaNs AVaiWORlty
I
I
I
I
I
Draft & Fina1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
15
Magnitude of Effort
❑ IT Strategic and SMART Utility - 35 projects
❑ OT Strategic and GIS - 27 projects
❑ IT Tactical Projects including foundational - 22 projects
❑ OT Tactical Projects including foundational - 31 projects
16
October 19, 2023 Regular Board Meeting Agenda Packet - Page 86 of 127
Magnitude of Effort
What it DOES and DOESN'T Represent
• Represents:
• Overall level of effort and cost for the
portfolio of potential projects,
prioritized into categories
• Recognition that some or even most
of the costs may already be included
in the existing 10 -year CIP and
current level of O&M funding
• A good check -point along the way in
the determination of "what" should
be done
17
• Does NOT Represent:
• An indication that INCREMENTAL
resources are needed
• A request for additional resources
• A completely planned out project
schedule, with precise resources
identified
• A fully executable and final plan
• The precise "when" & "at what
incremental cost"
Page 11 of 13
Magnitude of
Estimate
Cost
(This is a cost estimate of the total effort and is not a request for additional
funding. Most of the resources are budgeted.)
-
66
3.75 $
824,600
$ 253,000
$ 1,283,060
®BI
EAM 18
0.75 $
359,250
$ 80,000
$ 439,250
SCADA 75
1.05 $
712,506
$ 2,100,000
$ 2,812,500
Bi 33
6.5 $
2,855,000
$ 320,000
$ 3,175,000
EAM 45
3.25 $
1,051,500
$ 310,000
$ 1,361,500
GIS 57
6.7 $
2,554,250
$ 550,000
$ 3,104,250
SCADA 75
8.25 $
6,199,106
$ 4,056,666
$ 10,255,100
36
7 $
1,461,600
$ 200,000
$ 1,661,000
EBi
EAM 63
10.5 $
2,255,000
$ 390,000
$ 2,645,000
GIS 36
2 $
414,325
$ 150,000
$ 564,325
SCADA 66
3.7 $
3,445,750
$ 2,875,660
$ 6,326,756
MEAM 21
1.5 $
394,600
$ 305,000
$ 699,000
SCADA 60
2.8 $
1,323,000
$ 1,976,000
$ 3,299,000
Grand Total 645
57.75 $
23,848,675
$13,565,000
$ 37,619,675
* All programs will be assigned an owner
18
October 19, 2023 Regular Board Meeting Agenda Packet - Page 87 of 127
Page 12 of 13
Current Status of Projects and Recommendations
❑ Key IT/OT Strategic projects
• IT/OT Governance structure implemented
• Oracle ERP implementation and improvement on-going
• OT Network improvements underway
• Initial phases of SCADA project started
• Oracle Permits system being developed
• Detailed project charters and implementation plans being created
19
IT/OT Strategic Plan and Roadmap Enablers
❑ IT/OT Governance (Collaboration & Communication)
❑ Project Charters
• Scope and Objectives
• Critical Success Factors
• Cost
• Resource Requirements
• Schedule
❑ Organizational Change Management
❑ IT/OT Resources to meet new requirements and increased expectations
• Project Management
• Technical Resources
• IT/OT support organizations restructuring (Response and Agile)
❑ Budget
20
October 19, 2023 Regular Board Meeting Agenda Packet - Page 88 of 127
Page 13 of 13
21