HomeMy WebLinkAbout03.a. Award Construction Contract to JMB Construction for $2,343,000 for the Martinez Urgent Force Main Replacement DP100066; Additive Bid Item $180,000; Amend existing Carollo Engineers Agreement for $400,000; Transfer $3,762,000 from the CSS Reno Ph.2Page 1 of 13
Item 3.a.
CDrrEN1 RAL SAN BOARD OF •'
CENTRAL CONTRA COSTA SANITARY DISTRICT POSITION PAPER
DRAFT i
MEETING DATE: AUGUST21, 2023
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $2,342,000 TO JMB CONSTRUCTION,
INC., THE LOWEST RESPONSIVE AND RESPONSIBLE BIDDER FOR THE
MARTINEZ URGENT FORCE MAIN REPLACEMENT, DISTRICT PROJECT
100066; INCLUDE ADDITIVE BID ITEM FOR $180,000 FOR TEMPORARY
PIPELINES; AUTHORIZE THE GENERAL MANAGER TO AMEND AN
EXISTING CAROLLO ENGINEERS, INC. AGREEMENT FOR $400,000
INCREASING THE COST CEILING TO $2,900,000 TO INCLUDE
ENGINEERING SERVICES; TRANSFER $3,762,000 FROM THE
COLLECTION SYSTEM SEWER RENOVATION - PHASE 2 TO FUND THE
PROJECT; AND FIND THE PROJECT IS EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA)
SUBMITTED BY:
INITIATING DEPARTMENT:
KEITH GELLERMAN, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
GREG NORBY, DEPUTY GENERAL MANAGER
ROGER S. BAILEY, GENERAL MANAGER
ISSUE
On August 16, 2023, three bids were received for the construction of the Martinez Urgent Force Main
Replacement, District Project 100066 (Project). The Board of Directors (Board) must consider award of
the construction contract or reject bids within 50 days of the bid opening. Board authorization is also
required for the General Manager to amend a professional engineering services agreement above
$200,000 and transfer funds over $500,000 within the Capital I mprovement Program for individual project
budgets.
BACKGROUND
The existing dual 20-inch cement mortar -lined and coated steel force mains from the Martinez Pumping
Station were constructed in 1968 and convey raw wastewater to a discharge structure located within the
Martinez Refining Company's (MRC) property.
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 3 of 15
Page 2 of 13
Each force main is roughly a mile in length and situated on easements just North of Marina Vista Avenue in
Martinez and along the Union Pacific Railroad's (UPRR) right-of-way prior to entering the MRC secured
facility as shown in Attachment 1-Project Location Map.
I n November 2022, Engineering staff was notified of a small leak at one of the force mains on the UPRR
right-of-way. Operations staff quickly responded and stopped the leak by shutting down the force main and
draining the sewage within the pipeline back to the Martinez Pumping Station wet well. While the force
main was empty, staff CCTV'd the upper portion of the force main near the discharge structure, including
the failed pipe location. Based on the video and external inspection, staff determined that the force main
has various levels of corrosion with the most severe being observed internally at the top of the pipeline for
the last 300 feet. This type of corrosion is common for force mains that experience hydrogen sulfide gas
pockets or are not fully filled with wastewater, causing sulfuric acid build-up that deteriorates the cement
lining and steel pipe.
Capital Projects obtained a contractor to make an urgent repair that involved steel mesh, mortar, and a
carbon -reinforced fiber wrap. The repair was successful, and Operations returned the force main to
service before several large winter storms. Operations will routinely open both force mains during the wet
weather season for purposes of redundancy and to reduce flow velocities within the pipelines. The force
mains can experience a large range of flows from 1.0 million gallons per day (MGD) during dry weather to
over 12 MGD during peak wet weather events. After the repair and additional inspection of the aerial
crossings, staff identified a second failing location that has severe corrosion on the exterior of the pipe.
This second location could not be easily seen on the initial inspection due to difficulty in accessing the
aerial crossing in the refinery. Therefore, the force main has been turned off again until a contractor can be
hired to perform a more extensive repair and/or a full replacement of the aerial crossing.
Due to urgency of the situation, staff reached out to Carollo Engineers, Inc. (Carollo) to advise and provide
engineering services to permanently replace the corroded force main sections. Carollo is currently working
at the Martinez Pumping Station and at the MRC refinery for the Fairview Pumping Station replacement as
the construction manager. After reviewing several project alternatives, staff decided that the best
alternative was to remove and replace the last 650 feet of both existing force mains. This option will
remove the medium to more severe corroded sections and replace all of the force mains on UPRR's right-
of-way and MRC's property. The new pipeline is designed using PVC, and will be installed within steel
casings for the aerial crossings. Coordinating and obtaining permits with UPRR has been a long and
difficult process, and staff has been diligent with providing notifications and anticipates getting final
conditions once a general contractor is hired and on site to investigate the field conditions and utilities.
The location of the force mains adjacent to the railroads and nearby utilities makes the replacement work
very complicated and poses various construction challenges and risks. These challenges include limited
access for replacing the aerial crossing and building the new pipe supports. The risks include working near
high-pressure gas lines, Kinder Morgan pipeline, and other utilities. Staff has been coordinating with the
utilities and pipeline owners to safely perform the construction activities. A careful and highly qualified
pipeline contractor with relevant experience is needed to perform the construction work and within the
Project timelines. Staff is recommending the Project to be completed in two milestones. The first is for
repairs or a temporary pipeline to be installed so that the force mains care is reliable this upcoming wet
weather season. And the second milestone is to complete the permanent replacement by July of next
year. The Project is also offering incentives for the general contractor to complete any portion of the
permanent installation, especially the aerial crossings, to save time and costs for the temporary work and
overall project costs. An incentive of up to $200,000 is being proposed in the Contract.
Based on the Project complexity, Central San conducted a formal pre -qualification review of general
contractors, receiving statements of pre -qualifications from five interested general contractors: Cratus,
I nc., J MB Construction, I nc. (J MB), McGuire and Hester, Mountain Cascade, I nc., and Steve P. Rados,
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 4 of 15
Page 3 of 13
I nc. The solicitation was publicly advertised on PlanetB ids and shared with bidder exchanges, meeting the
notification requirements for public bidding and included a draft of the plans and specifications to allow
contractors to understand the challenges within the Project scope.
Upon review, all five general contractors were approved to participate in the bidding process.
Staff and Carollo prepared the plans and specifications for the Project. This Project was again advertised
on August 2, 2023, with the final bid plans and complete list of specifications for the vendors and
subcontractors. Three bids, ranging from $2,342,000 to $3,740,000, were received and opened on
August 16, 2023. The Engineer's estimate for the construction is $2,500,000. Capital Projects conducted
a technical and commercial review of the bids and determined that J MB is the lowest responsive and
responsible bidder with a bid amount of $2,342,000. A summary of bids received is shown in Attachment
2. J MB has been pre -qualified and meets the experience, safety, and other requirements. An additive bid
item was included in case temporary piping was required under the project. The Engineer's estimate for
the additive item is $300,000. The additive bids ranged from $180,000 to $500,000 and JMB priced the
work at $180,000. Staff recommends to include the additive item to the Project.
Capital Projects staff will provide oversight and construction management of the Project. Carollo will
provide technical support and engineering services, and inspection is planned to be conducted by staff or
may be supplemented by one of Central San's as -needed consultants. Operations staff will support the
Project as required to coordinate shutdowns and testing.
California Environmental Quality Act (CEQA)
Staff has concluded that this Project is exempt from CEQA under Central San's CEQA
Guidelines Section 15302, since it involves replacement of existing public facilities at the same location
and with the same purpose. Approval of this Project will establish the Board's independent finding that this
Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
The Board could consider the following alternatives or provide other direction:
1. Reject all bids which is not recommended. This Project will address the urgent need to replace
critical sewer infrastructure.
2. The Capital Improvement Contingency account has adequate budget and could be used to fund the
Project; however, it is not recommended since its early in the fiscal year and would deplete the
account significantly. The proposed funding source is a program budget used for sewer renovation
projects that currently has adequate projected cashflow for the sewer renovation projects planned
this fiscal year and for the urgent project.
FINANCIAL IMPACTS
The total estimated project cost is $3,962,000, which includes staff time, consultant costs, construction
contract, contingency, construction management, and other costs detailed in Attachment 3.
The Project was initiated under the General Manager's delegated authority for contingency projects at
$200,000. The remaining $3,762,000 needed to fully fund the Project will be transferred from the
Collection System Sewer Renovation - Phase 2, which has adequate funds in Fiscal Year 2023-24 at
$18,500,000 as detailed on page 231 of Central San's Budget.
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 5 of 15
Page 4 of 13
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee recommended to postpone this subject at the meeting on
August 14, 2023 and set a special meeting for August 21, 2023 to discuss this Project after bid opening.
The committee recommends of the Project.
RECOMMENDED BOARD ACTION
Staff recommends the following Board actions:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of $2,342,000 to J MB Construction, Inc., the lowest
responsive and responsible bidder, for the Martinez Urgent Force Main Replacement, District
Project 100066.
3. Include additive bid item for $180,000 for temporary pipelines;
4. Authorize the General Manager to amend an existing Carollo Engineers, Inc. agreement for
$400,000, increasing the cost ceiling to $2,900,000, to include engineering services; and
5. Transfer $3,762,000 from the Collection System Sewer Renovation -Phase 2 to fund the Project.
Strategic Plan re -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service, Strategy 3 - Build neighborhood and industry relations
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX: Infrastructure Reliability
Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post B id/P reconstruction Estimate
4. Presentation
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 6 of 15
Page 5 of 13
Martinez Urgent Force Main Replacement
District Project 100066
Map Date: 8/2/2023
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 7 of 15
Page 6 of 13
ATTACHMENT 2
MARTINEZ URGENT FORCE MAIN REPLACEMENT
DISTRICT PROJECT 100066
SUMMARY OF BIDS
PROJECT NO.: 100066 NO. OF ADDENDA: 1 DATE/TIME: AUGUST 16, 2023/2:00 PM
PROJECT NAME: MARTINEZ URGENT FORCE MAIN REPLACEMENT
PROJECT MANAGER: KEITH GELLERMAN
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
ENGINEER'S ESTIMATE: $2,500,000
NO.
BIDDER
BID PRICE
1
JMB Construction, Inc.
$2,342,000
2
Mountain Cascade, Inc.
$3,614,000
3
Cratus, Inc.
$3,740,000
BIDS OPENED BY: /s/Eileen Hansen
DATE: August 16, 2023 at 2.00 PM
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 8 of 15
Page 7 of 13
ATTACHMENT 3
MARTINEZ URGENT FORCE MAIN REPLACEMENT
DISTRICT PROJECT NO. 100066
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Of
Construction
Cost
1.
CONSTRUCTION
a. Construction Contract
$2,342,000
b. Additive Item - Temporary Pipelines
$180,000
c. 25% Contingency
$585,000
d. Permits
$40,000
SUBTOTAL - CONSTRUCTION COST
$3,147,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management (Engineering, Survey)
$100,000
- Public Relations/Right-of-Way
$5,000
- Operations
$10,000
b. Consultants
- Inspection (TBD)
$150,000
- ESDC (Carollo)
$150,000
- Material Testing/Special Inspection/Others
$20,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$435,000
14%
3.
PREBID EXPENDITURES
a. Engineering (Design, Survey, Right -of -Way, Drafting)
$180,000
b. Carollo Final Design (Post bid)
$200,000
SUBTOTAL - PREBID EXPENDITURES
$380,000
12%
4.
TOTAL ESTIMATED PROJECT COST
$3,962,000
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 9 of 15
Page 8 of 13
Project Background
Martinez Pumping Station (PS) has dual 20-inch, 1-
mile long force mains (FMs), that discharge into a
gravity structure at the Martinez Refining Company
(MRC).
In November 2022, staff was notified of a leak on one
of the FMs on Union Pacific Railroad's (UPRR) right -of
way. The pipe was immediately repaired with a
carbon fiber wrap.
CCTV on both FMs, as well as visual inspections,
showed various stages of corrosion with the aerial
and exposed pipelines.
Staff hired Carollo Engineers, Inc. (Carollo) to advise
on how to fix the FMs since they are currently
working on the Martinez PS projects.
Staff recommends to replace the last 650 feet of both
FMs, of which a portion will require UPRR permits.
Work will include temporary repairs or pipelines prior
to this wet weather season.
.,; •: .fit;
Attachment 4
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 10 of 15 1
Page 9 of 13
Martinez PS Force Mains
Project Area - Replace both sections of FM
r �C
5 _
uFeM it
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 11 of 15 2
Page 10 of 13
New Pipeline Design
Replace the last 650 feet (13%) of both FMs
with fusible PVC to prevent future corrosion
issues.
Steel casings for the aerial span.
Replace all cement -mortar lined pipe
between the end of the FMs and an access
vault that was installed on Waterfront Park.
This will allow for all the work to be
completed on and near the UPRR right-of-
way and MRC property.
Controlled low strength material backfill
required and concrete cap or encasement for
shallow trenches.
Work Completed or in
Progress
Notified and applied for an encroachment
permit with UPRR in May. Waiting for final
permit conditions.
Coordinating with MRC staff.
Pre -qualified five general contractors.
Staff and Carollo prepared the plans and
specifications for bidding purposes and
awa rd.
Final design will be completed with the
investigation/potholing with the contractor
due to the nearby high-pressure gas, fuel
pipelines, or other utilities.
V
L;
0
MARTINEZ
REFINERY
union PACIFIC kn kO
'
\ j
�l
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 12 of 15 3
Page 11 of 13
Schedule
August 2023: Advertise and Bid Opening
September 7, 2023: Authorize Budgets and Contractor
Awa rd
September/October 2023: Issue the Notice to Proceed
as soon as possible
July 2024: Project Completion
An early completion incentive up to $200,000 is being
offered to avoid temporary systems and construction
management costs.
Bids
Engineer's Estimate: $2,500,000
No.
Bidder
Total Bid
1
JMB Construction, Inc.
$2,342,000
2
Mountain Cascade, Inc.
$3,614,000
3
Cratus, Inc.
$3,740,000
Additive bid item for temporary piping for $180,000
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 13 of 15 4
Page 12 of 13
Total Estimated Project Cost
Project initiated with
$200,000 contingency
funds.
Remaining funding
from the Collection
System Sewer
Renovation - Phase 2;
adequate funds
available with no
impact to cashflow
with scheduled sewer
renovation projects.
Na.
Item Description
Amounts
%Cff
ConstruGion
cost
1.
CONSTRUCTION
a_ Cmstructm Cmtraa
52,3420011
h. AddNve Item - Temporary Pipelines
$100:000
a 25% Conbngency
$585,000
I Permits
"O.DDD
SUBTOTAL- GONSTRUCTI ON COST
$3,147,0D0
100%
2.
CONSTRUCTION MANAGEMENT
a. Usinct Forces
- Construction Management JEngineesirg. Survey)
$100,000
- Public RelatimslRght-af-Way
$5,D00
Oper-ato s
$1o.Doo
h. Consutants
- Inspection (TBD)
$150,000
- ESDC (CarolloE
$150,000
- Material Tesbngl5periaf InspectionlOthers
$20,0D0
SUBTOTAL- GONSTRUCTION MANAGEMENT
$435.0D0
14%
3.
PREBID EXPENDITURES
a. Engmn nng (Design, Survey, Right-0f--Way, Draffirg)
$180,OD0
h_ CarollD Anal Design (Post hid)
$200,000
SUBTOTAL- PREBI D EXPENDITURES
38s D.000
12%
4.
TOTAL ESTIMATED PROJECTCOST
$3.962.000
Recommended Board Actions
Staff recommends the following:
Find that the project is exempt from the California Environmental Quality Act;
Award a construction contract in the amount of $2,342,000 to JMB Construction,
Inc., the lowest responsive and responsible bidder, for the Martinez Urgent Force
Main Replacement, District Project 100066;
Include additive bid item for $180,000 for temporary pipelines;
Authorize the General Manager to amend an existing Carollo Engineers, Inc.
agreement for $400,000, increasing the cost ceiling to $2,900,000, to include
engineering services; and
Transfer $3,762,000 from the Collection System Sewer Renovation - Phase 2 to
fund the Project.
August 21, 2023 Special EOPS Committee Meeting Agenda Packet - Page 14 of 15 5
Page 13 of 13