HomeMy WebLinkAbout03.b. Construction Contract in the amount of $2246,800 with SDM Construction for the Laboratory Floor Replacement, DP 100008 and find the project is exempt from CEQAPage 1 of 10
Item 3.b.
CDr EENI RAL SAN BOARD OF •'
�J POSITION PAPER
CENTRAL CONTRA COSTA SANITARY DISTRICT �
� •
MEETING DATE: AUGUST 14, 2023
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $246,800 TO SDM CONSTRUCTION, THE
LOWEST RESPONSIVE AND RESPONSIBLE BIDDER FOR THE
LABORATORY FLOOR REPLACEMENT, DISTRICT PROJECT 100008; AND
FIND THAT THE PROJECT IS EXEMPT FROM THE CALIFORNIA
ENVIRONMENTAL QUALITYACT (CEQA)
SUBMITTED BY:
INITIATING DEPARTMENT:
MICHAEL CUNNINGHAM, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES -
ENGINEER CAPITAL PROJECTS
REVIEWED BY: NATHAN HODGES, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
GREG NORBY, DEPUTY GENERAL MANAGER
ROGER S. BAILEY, GENERAL MANAGER
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is also required for the General Manager to execute the Contract Documents subject to
submittal requirements.
BACKGROUND
The Environmental Laboratory building (Lab) is located within the Martinez campus and is a critical and
specialty facility used every day by staff for permitting, regulatory compliance, and process control. From
December 2022 to March of 2023, the Lab roof replacement and building seismic upgrades were
completed under the Laboratory Roof and Seismic Upgrades Project. While the floor was identified as
requiring replacement due to poor condition caused by a deficient moisture barrier, the roofing and seismic
upgrades were completed first to keep the Lab operational during construction, minimize impact on staff,
and protect high value and sensitive equipment.
The Laboratory Floor Replacement, District Project 100008 (Project) will replace the original flooring built
in the early 2000's with an upgraded moisture system to prevent delamination from the concrete
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 64
Page 2 of 10
subsurface. Attachment 1 shows the project location. The Lab is not expected to be closed during the
replacement work.
Calpo, Hom and Dong Architects, Inc. (CH&D) prepared the plans and specifications for the Project. The
Engineer's estimate for construction is $250,000. This Project was advertised on June 26 and July 1,
2023. Three bids ranging from $246,800 to $275,700 were received and publicly opened on July 21,
2023. The Capital Projects Division conducted a technical and commercial review of the bids and
determined that S D M Construction is the lowest responsive and responsible bidder. A summary of bids
received is shown in Attachment 2.
Central San will administer the construction contract and provide construction management, administration,
and submittal review. CH&D will provide technical assistance on an as -needed basis. Upon award, the
General Manager will execute the Contract Documents subject to submittal requirements.
CEQA
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15302 because it involves replacement of existing facilities at substantially the same locations and with the
same purpose and level of activity as the facilities being replaced. Approval of this Project will establish the
Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
An alternative would be to reject all bids. This is not recommended as the reflooring plans have been
designed to allow the Lab to remain operational throughout construction and the existing system is
deficient. I n time, the flooring could be a safety or tripping hazard as it continues to delaminate.
FINANCIAL IMPACTS
The total estimated project cost is $389,000 including design, bid price, contingency, construction
management, consultant costs, equipment purchase, workspace modifications as detailed in Attachment
3.
The replacement work is included in the Fiscal Year 2023-24 District Budget, shown on page 257 with a
total budget of $1,450,000 million. To date $1,296,000 million has been spent to complete the roof
replacement and building seismic upgrades. As part of the project, Central San will also replace laboratory
equipment at the end of its useful life ($50,000). Furthermore, the project will pay for conversion of a copy
machine area into two new office spaces using Central San's furniture vendor. Since these project costs
will be included, a total of $1,685,000 million will be needed to complete the entire scope for the Lab. A
balance of $235,000 is required to fund the Project and will be transferred under the General Manager's
delegated authority ($500,000 maximum) in the Capital Improvement Program for individual project
budgets. The transfer will be from the Capital I mprovement Budget Contingency account which has
adequate funds.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its August 14, 2023 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA; and
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 64
Page 3 of 10
2. Award a construction contract in the amount of $246,800 to SDM Construction, the lowest
responsive and responsible bidder, for the construction of the Laboratory Floor Replacement,
District Project 100008.
Strategic Plan re -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness
GOAL SIX: Infrastructure Reliability
Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post B id/P reconstruction Estimate
4. Presentation
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 64
Page 4 of 10
0 200 400
wFEET
r�
0�
L
IL .
OI
�. ❑
PROJECT AREA
LABORATORY BUILDING
Basin A South
CONSTRUCTION
STAGING AREA 11
/,
—ems,
MAIN GATE
\��oF7*
$o
CLATCIERS(SOUTr
SOLIDS
NDITIONI
3UILDINC
0 0 L---J,
❑ PUMP AND BLOWER
BUILDING
O POD
IMHOFF PLACE
70 SM.,
Central Contra Costa Attachment
Sanitary District Laboratory Floor Replacement
A190District Project 100008 1
' Location Map
Regular Committee Meeting Agenda Packet - Page 11 of 64
Page 5 of 10
ATTACHMENT 2
LABORATORY FLOOR REPLACEMENT
DISTRICT PROJECT 100008
SUMMARY OF BIDS
PROJECT NO.: 100008 NO. OF ADDENDA: 2 DATE/TIME: JULY 21, 2023/2:00 PM
PROJECT NAME: LABORATORY FLOOR REPLACEMENT
PROJECT MANAGER: MICHAEL CUNNINGHAM
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
ENGINEER'S ESTIMATE: $250,000
NO.
BIDDER
BID PRICE
1
SDM Construction
$246,800
Concord, California
2
CWS Construction Group, Inc.
$257,000
Novato, California
3
Aztec Consultants, Inc.
$275,700
San Ramon, California
BIDS OPENED BY: /s/Eileen Hansen
DATE: July 21, 2023 / 2:00 PM
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 64
Page 6 of 10
ATTACHMENT 3
LABORATORY FLOOR REPLACEMENT
DISTRICT PROJECT 100008
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Of
Construction
Cost
1.
CONSTRUCTION
a. Construction Contract
$246,800
b. Contingency at 15%
$37,200
c. Equipment
$50,000
d. Furniture convert copy area to two workshpaces
$11,000
SUBTOTAL - CONSTRUCTION COST
$345,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management
$15,000
b. Consultants
- Consultants
$5,000
- Inspection
$9,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$29,000
8%
3.
PREBID EXPENDITURES
a. Staff Engineering
$5,000
b. Consultant Fees
$10,000
SUBTOTAL - PREBID EXPENDITURES
$15,000
4%
4.
TOTAL ESTIMATED PROJECT COST
$389,000
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 64
Attachment 4 Page 7 of 10
Background
Floors installed in early 2000's and are now in poor /
condition. Typically, warrantied life is 15 years.
The existing rubber flooring adhesive is failing and
causing delamination throughout the Laboratory.
The existing adhesive will be removed, a new
moisture mitigation epoxy and new rubber floor will
be installed. Carpets in the office area and
breakroom will also be replaced.
Cubicle with copy machine and mailbox will be
converted into two new workspaces to better meet
staffing needs.
The Laboratory is not expected to be closed during
the replacement work. Select laboratory equipment
at the end of its useful life is being replaced to
improve reliability of the Lab.
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 14 of 64
Page 8 of 10
Lab flooring has
performed well over
-2O years. However,
moisture issues
especially at seams
have caused
delamination
Bid Results
Engineer's Estimate: $250,000
Three bids received and opened on July 21, 2023 at 2 p.m. One bid arrived late on
July 24, 2023 and was returned unopened to bidder.
Lowest Bidder: SDM Construction
I SDM Construction $246,800
2 CWS Construction Group, Inc. $257,000
3 Aztec Consultants, Inc. $275,700
k6homb - -
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 15 of 64 2
Page 9 of 10
Total Estimated Project Cost
No.
Item Description
Amounts
of
Construction
at
T.
CONSTRUCTION
a. Construction Contract
$248,800
b. Contingency at 15 %
$37,200
c. Equipment
$50,000
d. Fumilom convert copy area to two workshpaces
$11 000000
SUBTOTAL- CONSTRUCTION COST
$345,000
100%
2-CONSTRUCTION
MANAGEMENT
a. District Forces
- Construction Management
$15,000
b. Consu3ants
- Consultants
$5,000
-Inspection
9 000
SUBTOTAL -CONSTRUCTION MANAGEMENT
$29,000
0%
3_
PREBID EXPENDITURES
a_ Staff Engineenng
$5,000
b. Consultant Fees
$10 000
SUBTOTAL- PREBID EXPENDITURES
S15000
4%
4.
TOTAL ESTIMATED PROJECT COST
$389,000
Committee Recommendation:
Staff recommends the following:
Find that the Project is exempt from the California Environmental Quality
Act; and
Award a construction contract in the amount of $246,800 to SDM
Construction, the lowest responsive and responsible bidder, for the
construction of the Laboratory Floor Replacement, District Project
100008.
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 16 of 64 3
Page 10 of 10
August 14, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 17 of 64