HomeMy WebLinkAbout03.a. Contract for $11,449,000 w/ Bid Add for $1,213,000 to C. Overaa & Co. for Aeration Basins Diffuser Replacement, Ph.1, DP100019; and a PE agreement to HDR Engineering for $1,000,000Page 1 of 7
Item 3.a.
DCENTRALSAN
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETINGDATE: JULY10,2023
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT I N THE AMOUNT OF $11,449,000 TO C. OVERAA & CO., THE
LOWEST RESPONSIVE AND RESPONSIBLE BIDDER FOR AERATION
BASINS DIFFUSER REPLACEMENT, PHASE 1, DISTRICT PROJECT
100019; INCLUDE AWARD OF AN ADDITIVE BID ITEM IN THE AMOUNT OF
$1,213,000 FOR SEISMIC UPGRADES; EXECUTE A PROFESSIONAL
ENGINEERING SERVICES AGREEMENT INANAMOUNT NOTTO EXCEED
$1,000,000 WITH HDR ENGINEERING, INC. TO PROVIDE ENGINEERING
SERVICES DURING CONSTRUCTION; AND FIND THE PROJECT IS
EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT
(CEQA)
SUBMITTED BY: INITIATING DEPARTMENT:
WILLIAM GRANT, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, PROVISIONAL DIRECTOR OF ENGINEERING AND
TECHNICAL SERVICES
GREG NORBY, DEPUTY GENERAL MANAGER
ISSUE
The Board of Directors (Board) must consider award of the contract or reject bids within 50 days of the bid
opening. Authorization is also required for the General Manager to execute a professional engineering
services agreement in an amount over $200,000.
BACKGROUND
The existing aeration system in the treatment plant (plant) is not able to reliably maintain consistent air
levels across the basins due to the deficient and fouling diffuser system. The concrete basin plenums
have been a problem for many years and waste energy. This has led to concerns over the ability to
consistently meet National Pollutant Discharge Elimination System (NPDES) discharge limits, future
nutrient removal requirements, and the overall useful life of the aeration basins system.
A detailed condition assessment of the aeration system was completed as part of the Steam and Aeration
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 3 of 45
Page 2 of 7
Blower Systems Renovations, District Project 7349. The assessment recommended diffuser
replacement, mechanical asset rehabilitation/replacement, controls upgrades, concrete repairs, and
structural improvements. This Project is intended to address these issues to prolong the remaining useful
life of the aeration basins and to continue meeting regulatory requirements and coordinate with potential
future changes in mind, such as nutrient removal.
This Project generally consists of the renovation of Aeration Basins Tank 1 A, 1 B, 1 C & 1 D, and includes
demolition, structural, mechanical, electrical, instrumentation, and controls associated with diffuser
replacement. The Project is located within the plant, as identified in Attachment 1.
Central San and HD Engineering, Inc. (HDR) prepared the plans and specifications for the Project. The
Engineer's Estimate for construction is $16,000,000. This Project was advertised on May 1 and May 8,
2023. Seven (7) sealed bids ranging from $11,449,000 to $17,885,100 were received and publicly
opened on June 6, 2023. The Engineering Department conducted a technical and commercial review of
the bids and determined that C. Overaa and Co. (Overaa) is the lowest responsive and responsible bidder.
A summary of bids received is shown in Attachment 2. The bids received were very competitive, and
Overaa has reviewed their escrow documents and has no issues with their pricing. Overaa is on site at the
plant and currently working on two other capital projects.
Bids for seismic strengthening with fiber -reinforced polymer (FRP), an additive bid item, ranged from
$445,129 to $1,408,000. The Engineer's Estimate is $2,200,000, and Overaa provided a bid price in the
amount of $1,213,000. This item was included in the Project as an additive item because there was
uncertainty whether the Contractors would be able to complete the work within the seasonal constraints
provided in the contract. Overaa, the specialty FRP contractor, and staff have discussed this topic, and the
schedule can accommodate the proposed work. Therefore, staff recommends including this work to
improve seismic performance of the structures and due to the savings received in the low bid.
Central San will administer the construction contract and provide contract administration, survey, office
engineering, and submittal review. Construction inspection will be provided by a third party who will
supplement staff on an as -needed basis. Staff recommends that HDR, the designer of the Project, be
retained to provide engineering services during construction (ESDC) for Phase 1, as well as RAS Piping
Renovations, DP 100051, which was awarded at the March 16, 2023 Board Meeting. Staff has negotiated
the scope of work and fees for the ESDC work to be performed on an as -needed basis.
CEQA:
Staff has concluded that this Project is exempt from the California Environmental Quality Act (CEQA)
under Central San's CEQA Guidelines Section because it involves minor alterations to existing public
facilities involving no expansion of use. Approval of this Project will establish the Board of Directors'
independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
1. Reject all bids, which is not recommended because of the favorable bid pricing and the need to
restore reliable aeration air to the biological process within the basins.
2. Reject the additive bid item for seismic strengthening of the basin structures with FRP in the amount
of $1,213,000. This work is a preventative measure to protect the aeration basins in the event of a
seismic event and to upgrade the structures to current seismic code for underground tanks.
Preparing the basins for this type of work or any shutdown requires a significant amount of work by
staff. Postponing the seismic improvements and conducting the work as a standalone Project would
significantly increase the project costs for the work, as additional cleaning and protecting the new
diffuser system would be required along with other activities. Allowing the FRP work to be installed
before the new diffuser system is installed is a cost -benefit to the Project.
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 4 of 45
Page 3 of 7
FINANCIAL IMPACTS
The total estimated project cost is $20,879,000, which includes the planning, design, bidding, construction
contract, District -furnished equipment (diffuser system), construction management, consultants, and
contingency, as detailed in Attachment 3.
This Project is a phase of the Aeration Basins Diffuser Replacement, DP 100019, included in the Fiscal
Year (FY) 2023-24 Capital I mprovement Budget (CI B) on page 266 with a total estimated project budget
of $59,480,000. This Project, Phase 1, was estimated at $25,000,000; therefore, a savings of upwards of
$4,121,000 is expected. The adjustments to future budgets will be made after the award of the Project.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on July 10, 2023, and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Award a construction contract in the amount of $11,449,000 for the construction of the Aeration
Basins Diffuser Replacement, Phase 1, District Project 100019, to C. Overaa & Co., the lowest
responsive and responsible bidder;
2. Award the additive bid item for fiber -reinforced polymer seismic strengthening in the amount of
$1,213,000, increasing the construction contract to $12,662,000;
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements: and
4. Authorize the General Manager to execute a professional engineering services agreement in an
amount not to exceed $1,000,000 with HDR Engineering, Inc. to provide engineering support during
construction services; and
5. Find the project is exempt from the California Environmental Quality Act (CEQA)
Strategic Plan Tie -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high -quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations, Strategy 4 - Identify and advance sustainability initiatives, including
reducing energy usage and emissions
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 5 of 45
Page 4 of 7
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post B id/P reconstruction Estimate
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 6 of 45
Page 5 of 7
Aeration Basins Diffuser Replacement, Phase 1
District Project 100019
Map Date: 6/21/2023
rro
Martinez
fr
Project
Location
Detail
Area
Concord
Pleasant Hill
0
_ o
O o q)
Q�
3 o Coo
c
❑
0 OJ 0
as
Q Project Location
Q District -Owned Property
Note: 0 200 400 Map Displayed in North American Datum of 1983 Attachment
Central San data as of June 2023. H Feet California State Plane, Zone III FIPS O403, US Feet 1
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 45
Page 6 of 7
ATTACHMENT 2
AERATION BASINS DIFFUSER REPLACEMENT, PHASE 1
DISTRICT PROJECT 100019
SUMMARY OF BIDS
PROJECT NO.: 100019 NO. OF ADDENDA: 3 DATE/TIME: JUNE 6, 2023 /2 PM
PROJECT NAME: AERATION BASINS DIFFUSER REPLACEMENT, PHASE 1
PROJECT MANAGER: WILLIAM GRANT
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
ENGINEER'S EST.: $16,000,000
NO.
BIDDER
BID PRICE
1
C. Overaa & Co.
$11,449,000
Richmond, CA 94801
2
GSE Construction Company, Inc.
$12 996 600
Livermore, CA 94551
'
3
W.M. Lyles Co.
$14,444,800
Fresno, CA 93711
4
Mountain Cascade, Inc.
$15,290,964
Livermore, CA 94550
5
Garney Pacific, Inc.
$16,070,000
Tracy, CA 95391
6
Anvil Builders, Inc.
$16,963,000
Emeryville, CA 94608
7
Myers & Sons Construction LLC
$17 885 100
Sacramento, CA 95838
'
BIDS OPENED BY: /s/Eileen Hansen
DATE: 6/6/23
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 45
Page 7 of 7
ATTACHMENT
AERATION BASINS DIFFUSER REPLACEMENT, PHASE 1
DISTRICT PROJECT 100019
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% Construction
Cost
1
CONSTRUCTION
a. Construction Contract
$11,449,000
b. Additive Bid Item - Seismic FRP
$1,213,000
c. Contingency at 15%
$1,717,000
d. Equipment Pre -purchase (Diffuser/Breakers)
$950,000
SUBTOTAL - CONSTRUCTION
$15,329,000
100%
2
CONSTRUCTION MANAGEMENT
a. District Forces
Operations
$250,000
Construction Management
$1,050,000
b. Outside Services
Inspection
$650,000
Specialty inspection and material testing
$250,000
Engineering Support (HDR)
$1,000,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$3,200,000
21 %
3
PREBID EXPENDITURES
a. Engineering (Staff and Consultant)
$2,350,000
SUBTOTAL - PREBID EXPENDITURES
$2,350,000
15%
4
TOTAL PROJECT COST
$20,879,000
July 10, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 45