HomeMy WebLinkAbout09. Approve a $650,000 contingency project for the Tappan Terrace Sewer ReplacementDCENTRALSAN
MEETING DATE: JULY6, 2023
BOARD OF DIRECTORS
POSITION PAPER
Page 1 of 6
Item 9.
SUBJECT: APPROVE A$650,000 CONTINGENCY PROJECT FOR THE TAPPAN
TERRACE SEWER REPLACEMENT; FIND THATTHE PROJECT IS
EXEMPT FROM PUBLIC BIDDING BASED ONA LANDSLIDE MAKING THE
WORK IMPRACTICALAND A DISADVANTAGE; AUTHORIZE THE
GENERAL MANAGER TO EXECUTE A CONSTRUCTION CONTRACT IN
THE AMOUNT OF $498,000 WITH ENGINEERED SOIL REPAIRS, INC.;
TRANSFER $650,000 FROM THE CAPITAL IMPROVEMENT BUDGET
CONTI NGENCYACCOUNT TO FUND THE PROJECT; AND FI ND THAT THE
PROJECT IS EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL
QUALITYACT (CEQA)
SUBMITTED BY:
INITIATING DEPARTMENT:
JASON FITCH, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, PROVISIONAL DIRECTOR OF ENGINEERING AND
TECHNICAL SERVICES
KENTON L. ALM, DISTRICT COUNSEL
Roger S. Bailey Kenton L. Alm
General Manager District Counsel
ISSUE
The Board of Directors (Board) approval is required for any new project in an amount over $200,000,
which is not identified in the Capital Improvement Budget (CI B) and Cl B transfers in an amount over
$500,000.
July 6, 2023 Regular Board Meeting Agenda Packet - Page 45 of 151
Page 2 of 6
BACKGROUND
In March of 2020, several properties in the Tappan Terrace subdivision in Orinda were damaged due to a
landslide. Central San owns and operates a 8 -inch public sewer within Tappan Terrace (private road) and
sewer easements on 315 and 318 Tappan Terrace, and 99 Tappan Lane, which were granted by the
subdivision developer in 1978, as shown in Attachment 1 -Project Location Map.
Central San was unaware of the landslide until early July 2020 when notification was provided of a
landslide design repair that would impact the utilities in the area, most specifically the East Bay Municipal
Utility District's (EBMUD) waterlines and Central San's sewer facilities. By the end of July 2020, Central
San had found multiple damages to its sewers caused by the landslide and determined that approximately
300 feet of the sewer line would have to be out of service as repairs were infeasible. This sewer line
serves the three properties, 315 and 318 Tappan Terrace and 99 Tappan Lane, resulting in temporary
above ground sewers installed by the Collection System Operations division to provide reliable sewer
service.
On April 23, 2022, a settlement agreement was made between EBMUD, multiple property owners,
insurances, and the homeowner association in the Tappan Terrace subdivision. Engineered Soil Repairs,
I nc. (ESR) was named in the settlement agreement as the specialty contractor for repairing the property
related to the landslide by installing retaining walls, site restoration, and roadway repair. Permanent repair
of the utilities was not included in the settlement. ESR has applied for permits for the work identified under
the settlement, and Central San has reviewed and allowed the encroachments within the sewer
easements.
Central San has been coordinating with EBMUD, ESR, and PG&E for the landside repair and new
utilities. PG&E elected to replace its own utilities. EBMUD and Central San explored the possibility of a
joint agreement for one contractor to repair both utilities as a subcontractor to ESR, however, was
unsuccessful since several pipeline contractors were not interested and did not provide bid pricing.
Feedback received from those contractors was focused on the difficulty in open -trench construction on
hillsides and coordination required with the landslide repair or risks involved with restoration. After which,
EBMUD decided to procure ESR to perform the work, with support from EBMUD's pipeline crews. ESR
intends to install the water utility as they perform the landslide repair and has provided a proposal in the
amount of approximately $498,000 to Central San to install the sewer at the same time.
Although as a general rule, competitive bidding for District projects is mandatory; however, there are
certain well recognized exceptions to that requirement. One exception is where the nature of the contract
subject is such that "...competitive proposals would be unavailing or would not produce an advantage, and
the advertisement for competitive bid would thus be undesirable, impractical or impossible." ( Kennedy v.
Ross (1946) 28 Cal 2nd 569). Staff has evaluated multiple alternatives as noted below, and staff and
District counsel have concluded that it is necessary to conduct the sewer replacement in a fashion that
does not interfere with or compromise the overall slide repair. Having the slide repair contractor integrate
the sewer work into its overall landslide repair meets that objective.
ESR is a specialty contractor that is well known in the San Francisco Bay Area for repairs associated with
landslides and has the qualifications and experience as a general contractor to install pipelines such as
gravity sewers and related sewer structures. The scope of work for the sewer replacement includes, but is
not limited to, installation of 300 feet of 8 -inch sewers, two new sewer structures, reconnecting side
sewers, and other related sewer activities.
Staff reached out to other sewer contractors for additional pricing to verify the proposed ESR price or find
other construction methods but received limited responses and interest due to the landslide repair. The
price offered by ESR is reasonable considering the complexities involved with replacing the sewer
facilities such as the topography (steep hillsides), equipment access, deep excavations (10 feet), and the
July 6, 2023 Regular Board Meeting Agenda Packet - Page 46 of 151
Page 3 of 6
amount of grading required for the construction work is extensive.
Central San staff designed the new sewer facilities and plans to administer the construction contract and
provide construction management, resident engineering, survey, administration, and submittal review.
Construction inspection will be performed by one of Central San's consultant inspection service contracts.
CEQA
Staff has concluded that this project is exempt from CEQA under Central San CEQA Guidelines Section
15302 because it involves replacement of existing facilities at substantially the same locations and with the
same purpose and level of activity as the facilities being replaced. Any capacity increases are for non -
growth inducing, wet weather purposes. The project also is exempt under Central San CEQA Guidelines
Section 15061(b)(3), since it can be seen with certainty that there is no possibility that the activity in
question may have a significant effect on the environment. This certainty is based on Central San's
experience with numerous sewer construction projects of this nature, the relatively short distance involved,
and Central San's mitigating construction specifications. These specifications are standardized general
and special conditions that are made part of the project bid documents to address environmental
considerations, such as protecting trees and riparian areas, as well as compliance with applicable federal,
state, county, district, municipal and local laws, ordinances, orders, and regulations. Approval of this project
will establish the Board's independent finding that this project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
ESR is currently awaiting responses or contract agreements from EBMUD and Central San. EBMUD is
scheduled to get approval in July and Central San staff is recommending to do the same as ESR plans to
start the landslide repair by late July. Performing the sewer work after ESR's work is not recommended.
Staff considered and evaluated several alternatives, including the following:
1. Perform and contract the entire sewer work as a public bid, but due to the complications and risks
involved with impacting the landslide repair, this alternative is not recommended as is considered by
staff as impractical and a disadvantage to Central San to hire another outside contractor.
2. Staff considered other methods besides open -trench construction but due to site constraints, were
unable to recommend any that could help reduce or lessen the construction impacts.
3. Staff considered coordinating the work partially with another contractor. Staff does not recommend
this approach due to the slow pace anticipated with the pipeline installation. ESR plans to build the
hillside and install the water and sewer at 18-20 feet intervals to coordinate with the landslide repair.
4. Staff considered alternative sewer alignments and pumping systems. Staff does not recommend
this approach due to timing and increased capital cost or lifecycle costs and work to install a small
pumping station, additional sewer mains, both force main and gravity, and acquisition of additional
easements.
FINANCIAL IMPACTS
The total estimated project cost is $650,000 which includes design, ESR price, contingency, construction
management, and consultant costs as detailed in Attachment 2.
This project is not included in Central San's Fiscal Year 2023-24 Budget. The contingency project will be
funded by the Capital Improvement Budget Contingency account, which to date has over $12,000,000 and
has adequate funding for the project.
July 6, 2023 Regular Board Meeting Agenda Packet - Page 47 of 151
Page 4 of 6
COMMUNITY OUTREACH
Central San staff did extensive coordination with EBMUD, the lead agency, and ESR, the lead contractor,
on the landslide repair project. Throughout the course of design, staff addressed email and phone
inquiries regarding the project. To date, all questions and concerns received have been answered and
addressed.
Upon approval by the Board, staff plans to reach out to provide reminders, suggesting and recommending
that the private side sewers be inspected by the property owners prior to ESR completing the work.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on June 12, 2023, and
Special Engineering and Operations Committee Meeting on June 20, 2023 and recommended Board
approval.
RECOMMENDED BOARD ACTION
Staff recommends the following:
Approve a $650,000 contingency project for the Tappan Terrace Sewer Replacement;
2. Find that the Project is exempt from public bidding based on a landslide making the work impractical
and a disadvantage;
3. Authorize the General Manager to execute a construction contract in an amount of $498,000 with
Engineered Soil Repairs, Inc.;
4. Transfer $650,000 from the Capital Improvement Budget Contingency account to fund the project;
and
5. Find that the project is exempt from the California Environmental Quality Act (CEQA)
Strategic Plan Tie -In
GOAL ONE: Customer and Community
Strategy 1— Deliver high-quality customer service, Strategy 3 - Build neighborhood and industry relations
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 2 - Protect personnel and assets from threats and emergencies
ATTACHMENTS:
1. Project Location Map
2. Post-Bid/P reconstruction Estimate
July 6, 2023 Regular Board Meeting Agenda Packet - Page 48 of 151
Page 5 of 6
Tappan Terrace Sewer Replacement
Map Date: 5/24/2023
❑Detail Walnut Creek
Area
Orinda Lafayette
Moraga
tea,
q,
m
Tappaq-
olw �A
/ d4,
f = p�7
a �7
CD
ehabod �n
Vashingtoo II
Ln
r
Ii
Son ,Nbefry
Gt
Gravity Main
Mains to be Renovated
S/�ee�eq
Note: 0 500 Map Displayed in North American Datum of 1983 Attachment
Central San data as of May, 2023. Feet California State Plane, Zone III RIPS 0403, US Feet 1
July 6, 2023 Regular Board Meeting Agenda Packet - Page 49 of 151
Page 6 of 6
ATTACHMENT 2
TAPPAN TERRACE SEWER REPLACEMENT
DISTRICT PROJECT TBD
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
% of
Construction
Cost
1.
CONSTRUCTION
a. Construction Contract
$498,000
b. 15% Contingency
$75,000
SUBTOTAL - CONSTRUCTION COST
$573,000
100%
2.
CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management (Engineering, Survey)
$18,000
b. Consultants
- Inspection
$35,000
- Material Testing/Geotech/Arborist/Others
$7,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$60,000
10%
3.
PREBID EXPENDITURES
a. Engineering (Design, Survey, Right -of -Way, Drafting)
$17,000
SUBTOTAL - PREBID EXPENDITURES
$17,000
3%
4.
TOTAL ESTIMATED PROJECT COST
$650,000
July 6, 2023 Regular Board Meeting Agenda Packet - Page 50 of 151