HomeMy WebLinkAbout03.c. Equipment Contract NTE $1.8 million with Xylem Water Solutions USA, Inc. for Fine Bubble Diffusers and Special Support Services Under Aeration Basins Diffuser Replacement Phase 1; DP 100019Page 1 of 8
Item 3.c.
DCENTRALSAN
MEETING DATE: MARCH 13, 2023
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
SUBJECT: REVIEW DRAFT POSITION PAPER TO AUTHORIZE THE GENERAL
MANAGER TO EXECUTE AN EQUIPMENT CONTRACT I N AN AMOUNT NOT
TO EXCEED $1.8 MILLION WITH XYLEM WATER SOLUTIONS USA, INC.
FOR FINE BUBBLE DIFFUSERS AND SPECIAL SUPPORT SERVICES
UNDER THE AERATION BASINS DIFFUSER REPLACEMENT PHASE 1,
DISTRICT PROJECT 100019
SUBMITTED BY: INITIATING DEPARTMENT:
WILLIAM GRANT, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
DANEA GEMMELL, PROVISIONAL DIRECTOR OF ENGINEERING AND
TECHNICAL SERVICES
ISSUE
The Board of Directors (Board) authorization is required for contracts above $200,000 in the Capital
Improvements Program.
BACKGROUND
In 2019, Central San initiated a comprehensive asset evaluation of the secondary process facilities at the
treatment plant, including its four aeration basins. The diffuser system within the basins was identified as an
aging asset that was beyond its remaining useful life. The system was tested by an independent party, and
it was determined to have an extremely low efficiency due to routine clogging and leaks. Many of the
diffusers have been found with irreversible fouling during routine inspection and maintenance.
The Aeration Basins Diffuser Replacement Phase 1, District Project 100019 (Project), has further
evaluated the existing diffuser system and associated piping, especially the large underground aeration
piping serving the basins. Full replacement of the aeration diffusers is recommended, and staff has
concluded that the underground piping has remaining life with no structural defects. The condition
assessment has also indicated that the air leaks are likely due to plenum cracks in the concrete and/or
coatings.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 16 of 43
Page 2 of 8
The Board authorized staff and the project designer, HDR Engineering, Inc. (HDR) to prepare the final
design for the four basins and related work on May 6, 2023. Since then, staff has recommended to
sequence the replacement work in two project phases. The first project, Phase 1, will consist of two
aeration basins, and then Phase 2 will replace the remaining two basins. This sequence allows Operations
the flexibility to meet the normal maintenance requirements or other associated improvements anticipated
during the project timelines. Due to the seasonal constraints and efforts to complete the project work,
replacing the diffusers in a basin is expected to be on a yearly basis.
Prior to finalizing the design, staff has decided to select the diffuser equipment to better ensure the design
accuracy and for consistency in diffusers or standardization across all four basins, as this Project will be
bid in phases. Pre -purchasing the diffuser equipment may alleviate potential construction schedule delays
and result in a lower construction cost to Central San allowing for consistent competitive pricing in the
future project. The final design should be ready by July of this year, and staff plans to purchase the
equipment after the award of the installation contract for the first basin to be retrofitted in 2024.
Staff, with the assistance of HDR, prepared the diffuser equipment procurement package which was
based on qualifications and low bid pricing. On November 21, 2022, staff advertised a formal public
solicitation and bid on PlanetBids and the District's website for fine bubble diffusers and special support
services. The Engineer's estimate is $1,500,000. Central San received two bids, $1,537,853 and
$1,880,274, on February 7, 2023. A summary of the bidders is shown in Attachment 1.
The Capital Projects Division conducted a technical and commercial review of the qualifications and bids,
and determined that Xylem Water Solutions USA, Inc. is the lowest responsive and responsible bidder
with a bid amount of $1,537,853.
ALTERNATIVES/CONSIDERATIONS
The Board could consider the following alternatives:
Reject bids, which is not recommended. This equipment contract will ensure continuity and costs for
the aeration basins improvements and increase reliability and efficiency in the secondary process
area in the treatment plant.
Staff plans to pre -purchase the equipment; however, an alternative would be to reject bids and
include the equipment into the bid for the installation contractor. This alternative doesn't allow Central
San to guarantee pricing for Phase 2 or staff would have to obtain the equipment under sole source
justification, if possible. The equipment contract allows for the designer and Central San to work
together with the vendor to fine-tune a system that would be optimal for the District's maintenance
staff and still meet the fabrication or delivery time for the contractor.
FINANCIAL IMPACTS
The total estimated cost for the equipment and services may reach $1.8 million which includes vendor
engineering, installation design assistance, diffuser equipment and material costs, sales tax, delivery, and
contract contingency.
Up to half of the contract costs, or $900,000 may be used under the Project. The overall contract
contingency is roughly $260,000 and will be potentially used for upgrading materials or diffuser equipment
changes requested by the District and for cost escalation if, for some reason, the project timelines are
postponed. The equipment contract has strict provisions for cost escalation and/or de-escalation.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 17 of 43
Page 3 of 8
The equipment contract will be funded by the Aeration Basins Diffuser Replacement, District Project
100019, and has an estimated total budget of $61.3 million. The project can be found on page 255 in the
Fiscal Year 2022-23 Budget and includes adequate available funding in the next two fiscal years for the
work.
COMMITTEE RECOMMENDATION
The Engineering & Operations Committee reviewed this matter at its March 13, 2023 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends authorizing the General Manager to execute an equipment contract in an amount not to
exceed $1.8 million with Xylem Water Solutions USA, I nc. for fine bubble diffusers and special support
services under the Aeration Basins Diffuser Replacement Phase 1, District Project 100019
Strategic Plan re -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations, Strategy 4 - Identify and advance sustainability initiatives, including
reducing energy usage and emissions
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
GOAL SEVEN: Innovation and Agility
Strategy 2 - Implement organization -wide optimization
ATTACHMENTS:
1. Summary of Bids
2. Presentation
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 18 of 43
Page 4 of 8
ATTACHMENT 1
REQUEST FOR QUALIFICATIONS AND BID:
DIFFUSER SELECTION & PROCUREMENT PACKAGE FOR THE
AERATION BASINS DIFFUSER REPLACEMENT PROJECT,
DISTRICT PROJECT 100019
SUMMARY OF BIDS
PROJECT NO.: N/A NO. OF ADDENDA: 2 DATE/TIME: FEBRUARY 7, 2023/2:00 PM
PROJECT NAME: RFQ AND BID: DIFFUSER SELECTION & PROCUREMENT PACKAGE FOR
THE AERATION BASINS DIFFUSER REPLACEMENT PROJECT, DISTRICT PROJECT 100019
PROJECT MANAGER: WILLIAM GRANT
PROJECT LOCATION: 5019 IMHOFF PLACE. MARTINEZ. CALIFORNIA
ENGINEER'S ESTIMATE: $1,500,000
NO.
BIDDER
BID PRICE
1
Xylem Water Solutions USA, Inc.
$1,537,853
Charlotte, NC 28217
2
SSI Aeration, Inc.
$1,880,274
Poughkeepsie, NY 12603
BIDS OPENED BY /s/ Katie Young
DATE: February 7, 2023
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 19 of 43
Page 5 of 8
March 13, 2023
Equipment and Special dw
Services Contract under the
Aeration Basins Diffuser
Replacement, District
Project 100019 IMM01ii,
Engineering and Operations
Committee Meeting
William Grant, P.E.
Associate Engineer
Edgar J. Lopez, P.E.
Capital Projects Division Manager
Background and Diffuser
Contract Drivers
In 2019 Central San initiated a comprehensive asset
evaluation of the secondary process facilities at the
treatment plant, and identified the Diffuser System
in the Aeration Basins as an aging asset that is
beyond its useful life.
Independent testing was performed, and the
Diffuser System was found to have extremely low
efficiency due to clogging, leaks, and irreversible
fouling. A new diffuser system will remedy these
issues.
The Aeration Project was split into two phases to
provide more flexibility in meeting maintenance
requirements. Pre -purchasing all diffuser
equipment alleviates schedule delays and
equipment inconsistencies between the two
phases. Furthermore, it allows for consistent
competitive pricing.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 20 of 43 1
Page 6 of 8
Existing Diffuser System
New Diffuser System
r
r,
t Manual Control
�^ r•t 1 Valve
EL108.0
TOC EL 106.5
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 21 of 43 2
Page 7 of 8
Bid Results
Engineer's Estimate: $1,500,000
Two (2) bids received
Lowest Bidder: Xylem Water Solutions USA, Inc.
No.
Bidder
Total Bid
1
Xylem Water Solutions USA, Inc.
$1,537,853
2
SSI Aeration, Inc.
$1,880,274
Project Schedule,'
Diffuser Contract Award: April 6, 2023_
Finish Aeration Design: by June 2023-—
Aeration Project Phase 1: 2023-2025
Aeration Project Phase 2: 2027-2028'�
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 22 of 43 3
Page 8 of 8
Committee Recommendation
Staff recommends approval of the following:
Authorize the General Manager to execute an equipment
contract with Xylem Water Solutions USA Inc., lowest
responsive and responsible bidder, for fine bubble diffusers
and special services in the amount not to exceedL
$1,800,000, under the Aeration Basins Diffuser Replacement
-r
Phase 1, District Project 100019.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 23 of 43 4