HomeMy WebLinkAbout03.b. Construction Contract to GSE Construction Company, Inc. for Return Activated Sludge (RAS) Piping Renovations; DP 100051Page 1 of 10
Item 3.b.
CDr EENI RAL SAN BOARD OF •'
�J POSITION PAPER
CENTRAL CONTRA COSTA SANITARY DISTRICT �
� •
MEETING DATE: MARCH 13, 2023
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $1,283,200 TO GSE CONSTRUCTION
COMPANY, INC., THE LOWEST RESPONSIVE AND RESPONSIBLE
BIDDER FOR THE RETURN ACTIVATED SLUDGE (RAS) PIPING
RENOVATIONS, DISTRICT PROJECT 100051; FIND THE PROJECT IS
EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT
(CEQA); AND AUTHORIZE UP TO A 25-PERCENT CONTINGENCY
SUBMITTED BY:
INITIATING DEPARTMENT:
WILLIAM GRANT, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
DANEA GEMMELL, PROVISIONAL DIRECTOR OF ENGINEERING AND
TECHNICAL SERVICES
ISSUE
On February 15, 2023, six sealed bids were received and opened for the construction of the RAS Piping
Renovations, District Project 100051 (Project). The Board of Directors (Board) must consider award of
the contract or reject bids within 50 days of the bid opening. Authorization is also required for the General
Manager to execute the Contract Documents and include up to 25-percent contingency.
BACKGROUND
This project is intended to improve the reliability of the RAS system within the treatment plant due to aging
piping and to reduce the risk of failure associated with deteriorated piping that is partially submerged in the
final effluent channel. The work generally consists of the replacement of several segments of RAS piping,
temporary systems to continue operations, removal of abandoned piping and appurtenances, and other
piping improvements. The Project is located within the Treatment Plant, as presented in Attachment 1,
Location Map.
Central San and HDR Engineering, Inc. (HDR) prepared the plans and specifications for the Project. The
Engineer's Estimate for the construction is $2,000,000. This Project was advertised on January 16 and
January 23, 2023. Six sealed bids ranging from $1,283,200 to $2,421,000 were received and publicly
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 6 of 43
Page 2 of 10
opened on February 15, 2023. A summary of bids received is shown in Attachment 2. The Capital
Projects division conducted a technical and commercial review of the bids and determined that GSE
Construction Company, Inc. (GSE) is the lowest responsive and responsible bidder. References were
provided for GSE, and staff received satisfactory feedback. Central San will administer the construction
contract and provide administration, inspection, survey, and office engineering. Consultants will provide
construction inspection services and submittal review to supplement staff on an as -needed basis. HID is
the project designer, and staff will issue an agreement amendment for engineering service during
construction within the General Manager's delegated authority.
California Environmental Quality Act (CEQA)
Staff has concluded that this Project is exempt from the California Environmental Quality Act (CEQA)
under Central San's CEQA Guidelines, Section 15301 since it involves minor alterations to existing public
facilities involving no expansion of use. Approval of this Project will establish the Board of Directors'
independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Staff is currently working with HDR and originally planned to perform the Project scope under the Aeration
Diffuser project. However, due to construction constraints and sequencing, staff decided to bid the work
separately to help construct both projects. An alternative would be to reject bids, which is not
recommended since the work received great bid pricing, and to reduce potential issues with contaminating
the final effluent quality
FINANCIAL IMPACTS
The total estimated project cost is $2,018,200. This includes design, the construction contract,
contingency, staff time, and third -party services. Staff recommends a 25-percent contingency for this
Project due to the potential for additional unforeseen demolition and repair work around the aeration basins
and to repair other piping that may be in need of replacement once inspected. See Attachment 3 for a
budget summary for the Project.
This Project will be funded by the Aeration Basins Diffuser Replacement, DP 100019 included in the
Fiscal Year (FY) 2022-23 Capital I mprovement Budget (CI B) on page 255 with a total estimated project
budget of $61,300,000, and has adequate funding for the next fiscal year.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee will review this matter at its meeting on March 13, 2023. Staff
will provide an update of the Committee's recommendation when brought before the Board of Directors
for approval.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA,
2. Award a construction contract in the amount of $1,283,200 for the construction of the RAS Piping
Renovations, District Project 100051, to GSE Construction Company, Inc., the lowest responsive
and responsible bidder; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to 25-percent contingency.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 43
Page 3 of 10
Strategic Plan Tie -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX. Infrastructure Reliability
Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post B id/P reconstruction Estimate
4. Presentation
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 43
Page 4 of 10
RAS Piping Renovations Project
District Project 100051 Location Map Date:2/23/2023
0
Martinez
detail Area
a
Concord
Pleasant Hill
Project
Location
0 '
C
❑ oM
0
o�a^ e��
0 �
Oo
0
Q Project Location `r
Q District -Owned Property
Note: /� 0 200 400 Map Displayed in North American Datum of 1983 Attachment
Central San data as of February 2023. IT Feet California State Plane, Zone III FIPS O403, US Feet 1
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 43
Page 5 of 10
ATTACHMENT 2
RAS PIPING RENOVATIONS
DISTRICT PROJECT 100051
SUMMARY OF BIDS
PROJECT NO.: 100051 NO. OF ADDENDA: 3 DATE/TIME: FEBRUARY 15, 2023/2:00 PM
PROJECT NAME: RAS PIPING RENOVATIONS
PROJECT MANAGER: WILLIAM GRANT
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ CA
ENGINEER'S ESTIMATE: $2,000,000
NO.
BIDDER
BID PRICE
1
GSE Construction Company, Inc.
$1,283,200
Livermore, CA 94551
2
C. Overaa and Co.
$1,588,000
Richmond, CA 94801
3
Gateway Pacific Contractors, Inc.
$1,630,000
Sacramento, CA 95832
4
W.M. Lyles Co.
$1,736,950
Fresno, CA 93711
5
Valentine Corporation
$2,365,369
San Rafael, CA 94901
6
GSW Construction, Inc.
$2,421,000
San Francisco, CA 94105
BIDS OPENED BY: /s/Katie Young
DATE: February 15, 2023 at 2:00 PM
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 43
Page 6 of 10
ATTACHMENT 3
RAS PIPING RENOVATIONS
DISTRICT PROJECT 100051
POST-BID/PRECONSTRUCTION ESTIMATE
No.
Item Description
Amounts
Construction
Cost
1
CONSTRUCTION
a. Construction Contract
$1,283,200
b. Contingency at 25%
$320,000
SUBTOTAL - CONSTRUCTION COST
$1,603,200
100%
2
CONSTRUCTION MANAGEMENT
a. District Forces
Construction Management
$85,000
Operations
$30,000
b. Outside Services
Construction Inspection
$65,000
Engineering Support As -needed
$55,000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$235,000
15%
3
DESIGN (PREBID ESTIMATE)
a. Staff & Consultant Costs
$180,000
SUBTOTAL - PREBID EXPENDITURES
$180,000
11%
4
TOTAL ESTIMATED PROJECT COST
$2,018,200
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 11 of 43
Page 7 of 10
Project Background
and Drivers
Over the years, Central San has replaced
portions of the Return Activated Sludge (RAS)
piping for the Aeration Basin Systems to
maintain reliability.
RAS is settled activated -sludge collected in the
secondary clarifiers. This biomass is returned
to the aeration basins, allowing for a
concentrated number of microorganisms back
to the process.
The RAS piping being replaced was identified
by staff, and the piping over the Final Effluent
(FE) channel is of urgent concern since any
type of failure would contaminate the
effluent.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 43
Page 8 of 10
Project Improvements
Bid Results
Engineer's Estimate: $2,000,000
Six (6) bids received
Lowest Bidder: GSE Construction Company, Inc.
RAS Piping
• Replace piping over FE channel
• Add new valves for better control
• Construct temporary system for
operations
Aeration Basin Deck
• Remove abandoned coarse bubble
piping, valves, and repair concrete
• Replace missing guard rails and toe
boards
• Remove crossover stairs where no
longer needed
South Selector Channel
• Demolition of abandoned piping
and coarse bubble diffusers
• Removal of deteriorated spray
piping —..ddm
No.
Bidder
Total Bid
I
GSE Construction Company, Inc.
$1,283,200
2
C. Overaa and Co_
$1,588,000
3
Gateway Pacific Contractors, Inc.
$1,630,000
4
W.M. Lyles Co.
$1,736,950
5
Valentine Corporation
$2,365,369
6
GSW Construction, Inc.
$2,421,000
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 43 2
Page 9 of 10
Total Estimated Project Cost
No.
Item Description
Amounts
Construction
Cost
1
CONSTRUCTION
a. Construction Contract
$1,283,200
b. Contingency at 25%
$320,000
SUBTOTAL -CONSTRUCTION COST
$1,603,200
100%
I
CONSTRUCTION MANAGEMENT
a. District Forces
Construction Management
$85,000
Operations
$30,000
b. Outside Services
Construction Inspection
$65 000
Engineering Support As -needed
$55 000
SUBTOTAL - CONSTRUCTION MANAGEMENT
$235,000
15°%
3
DESIGN (PREBID ESTIMATE)
a. Staff & Consultant Costs
$180 000
SUBTOTAL - PREBID EXPENDITURES
$180 000
1 t %
4
TOTAL ESTIMATED PROJECT COST
$2.018 200
Project Schedule
Award: March 16, 2023
Piping long lead item thus staff
recommended to post position paper
in parallel with Board Meeting
Anticipated NTP: April 24, 2023
Project Completion: December 2023 ti
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 14 of 43 3
Page 10 of 10
Committee Recommendation:
Staff recommends approval of the following:
Find that the Project is exempt from CEQA;
Award a construction contract in the amount of
$1,283,200 for the construction of the RAS Piping
Renovations District Project 100051, to GSE
Construction Company Inc., the lowest responsive and
responsible bidder; and
Authorize the General Manager to execute the Contract
Documents subject to submittal requirements and
include up to 25-percent contingency.
March 13, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 15 of 43 4