HomeMy WebLinkAbout05.a. Receive quarterly Develpment Report through December 2022 Page 1 of 5
Item 5.a.
CENTRAL SAN
February 22, 2023
TO: REAL ESTATE, ENVIRONMENTAL AND PLANNING COMMITTEE
FROM: DANA LAWSON, SENIOR ENGINEER
REVIEWED BY: DANEA GEMMELL, PROVISIONAL DIRECTOR OF ENGINEERING AND
TECHNICAL SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE QUARTERLY DEVELOPMENT REPORT
Please see the attached quarterly Development Report through December 2022. Staff will present the
material during the meeting and answer any questions.
Strategic Plan re-In
GOAL ONE: Customer and Community
Strategy 1 - Deliver high-quality customer service
ATTACHMENTS:
1. Development Quarterly Report
February 22, 2023 REEP Committee Meeting Agenda Packet- Page 7 of 21
Page 2 of 5
Department: Engineering&Technical Services ATTACHMENT 1
Division: Planning&Development Services
Section: Development Services
Development Quarterly Report
through December 2022
Development Activity
Development Activity Detail
Month Trend Over Year
1,000
900
800
700
600
500
400
300
200
100 '
c > on a w > v c > c ao a
i Q n O p f6 LL r° Q ca N OU o v
2021 2022
Sum of Permits-completed ■Sum of Applications processed
Development Activity Detail
Multi-Year Trend by Fiscal Year
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
1,000 ■
13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22 22-23
*July-Dec
■Sum of Permits-completed ■Sum of Applications processed
Page 1 of 4
February 22, 2023 REEP Committee Meeting Agenda Packet- Page 8 of 21
Page 3 of 5
Department: Engineering&Technical Services ATTACHMENT 1
Division: Planning&Development Services
Section: Development Services
General Plan Review
Plan Review Submittals
Monthly Trend over Year
350
300 _
250
200 _
150
100
50
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2022
■Sum of Encroachment Verifications ■Sum of New Residential(s)and Permits
■Sum of Commercial ■Sum of Revision by outside Agency
■Sum of Denied at intake
• Turnaround Times:
Business Encroachment New Commercial' Revisions by Outside
Days' Verifications Residential(s)' Agencies or Others
Ave Quarter 1 11 26 1 21 7
(Jul-Sep)
Ave Quarter 2 9 25 19 5
(Oct-Dec)
Target 5 5 single-homes 10-15 5
10-15 subdivision S2
1. Business day turnaround is a conservative calculation since manually tracking of initial submittal to approval
dates does not accurately account for the time awaiting on applicant's response to plan check comments or
submittal revisions or District holidays
2. Commercial, Mixed-Use and larger Multi-Family Residential often require review by additional Sections
(Environmental Compliance for pretreatment requirements, Financial Planning for fee assessments, and
Inspection for constructability or phasing)
Page 2 of 4
February 22, 2023 REEP Committee Meeting Agenda Packet- Page 9 of 21
Page 4 of 5
Department: Engineering&Technical Services ATTACHMENT 1
Division: Planning&Development Services
Section: Development Services
Mainline Plan Review (new sewer mains)
• Meeting turnaround times on submittals (6-4-2 weeks)
• Pre-Plan Review (PPR) meetings are mandatory to demonstrate compliance with
Standard Specifications before 1St Plan Submittal is accepted. Use of these virtual
meetings has been instrumental in reducing overall design approval for mainline
extensions since most engineers are not familiar with Central San requirements and an
iterative discussion provides quicker feedback
Mainline Submittal Report Highlights
■ #PPR Mtgs ■ #Plans Approved
■ #Permits Issued ■ #Submittals Returned
25 ■#Inspection Complete,Begin 1-Yr Warranty ■#Closeout,End 1-Yr Warranty
20
15
10
5
titi titi titi titi titi titi titi titi titi titi titi titi titi titi titi titi titi titi ti�
10111 �e� �.ac' PQM' �aJ �J� � P��O 411 pow �o, pew 4111
Recent and Upcoming Development Highlights
• County placing an advisory stamp on permitted building plans; instead of requiring plan
approvals by outside agencies prior to submitting the application
• Continuing trend of in-fill/densification, mixed-use, multi-family residential (MFR), senior
living, accessory dwelling units (ADUs) and SB9 lot-splits; very few developments with
single-family residential (SFR)
Walnut Creek
• Plan Review: Oak Road/Circle by Summerhill Homes, SFRs
Danville
• Plan Review: EI Pintado, MFR for 52 units, 3 story
• Plan Review: Hartz Ave, mixed-use
Page 3 of 4
February 22, 2023 REEP Committee Meeting Agenda Packet- Page 10 of 21
Page 5 of 5
Department: Engineering&Technical Services ATTACHMENT 1
Division: Planning&Development Services
Section: Development Services
San Ramon
• Seeing lots of development in the "City Village" area, entitlements, pre-application
meetings, determination of mainline extensions, and hydraulic capacity reviews
• Plan Review: City Village, Master Plans and Plot Plans for 268 SFR & 136 MFR units
• Pre-Application: 6131 Bollinger Canyon, MFR, 383 units (luxury apartments)
• Plan Review: 6132 Bollinger Canyon, MFR, 169 units (Senior Living)
• Plan Review: Deer Creek, MFR, 280 units (senior apartments)
Misc
• De-silting Walnut Creek and Grayson creek channels
• 1-680/SR-4 interchange improvements — planning started for final phase by CCTA
consultant
Page 4 of 4