HomeMy WebLinkAbout04.a. Review draft to authorize a Purchase Agreement with Trojan Technologies Group, ULC for DP 100012 and amend existing agreement with Carrollo Engineers for final design servicesPage 1 of 15
Item 4.a.
DCENTRALSAN
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: JANUARY23, 2023
SUBJECT: REVIEW DRAFT POSITION PAPER AUTHORIZING THE GENERAL
MANAGER TO:
1. EXECUTE A PURCHASE AGREEMENT I N AN AMOUNT NOT TO
EXCEED $5.5 MILLION WITH TROJAN TECHNOLOGIES GROUP ULC
FOR ULTRAVIOLET (UV) DISINFECTION EQUIPMENTAND SPECIAL
SERVICES FOR THE UV DISINFECTION REPLACEMENT, DISTRICT
PROJECT 100012; AND
2. AMEND AN EXISTING PROFESSIONAL ENGINEERING SERVICES
AGREEMENT WITH CAROLLO ENGINEERS, INC. IN AN AMOUNT
NOTTO EXCEED $4.4 MILLION, INCREASING THE COST CEILING
TO $5.3 MILLION FOR FINAL DESIGN SERVICES
SUBMITTED BY: INITIATING DEPARTMENT:
AMANDA CAUBLE, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
ISSUE
The Board of Directors (Board) authorization is required for contracts or professional engineering services
agreement above $200,000 in the Capital Program.
BACKGROUND
Central San built the existing UV Facilities in 1994 to replace gaseous chlorination disinfection for
wastewater effluent. Fischer -Porter was the original manufacturer, patent holder, and is no longer in
business. The patent rights were sold several times, first to Elsag Bailey, then ABB and now belongs to
I ronbrook UV of Canada (I ronbrook).
Most of the current UV system has been in service for roughly 29 years and requires substantial
maintenance, lamp replacement, and frequent chemical cleaning of UV banks. Operations and
Maintenance (O&M) staff is able to maintain the system and, to date, has been able to obtain spare parts
and lamps from I ronbrook. For wet weather operation, the UV system has a capacity of 100 million gallons
per day (MGD) and it has been established through hydraulic modeling that a capacity of 127 MGD is
achievable through improvements and with the existing secondary and aeration process. Thus, the existing
UV system at its current location and downstream infrastructure creates a bottleneck effect, limiting the
discharge of disinfected final effluent during peak wet weather events.
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 4 of 32
Page 2 of 15
On January 11, 2021, Central San initiated a formal public solicitation for engineering services for the UV
Disinfection Replacement, District Project 100012 (UV Project), and seven consulting engineering firms
responded with qualified and responsive proposals. Carollo Engineers, Inc. (Carollo) ranked as the top
firm and was recommended to be the designer, or engineer of record, for the UV Project. On April 15,
2021, the Board authorized the General Manager to execute a professional engineering services
agreement with Carollo in an amount not to exceed $900,000 for planning and pre -design services.
A condition assessment of the UV system was performed under the UV Project that evaluated alternative
state-of-the-art disinfection technologies, such as LED UV, ozone, peracetic acid, and sodium
hypochlorite disinfection to determine the optimal disinfection system for Central San. Based on a
comprehensive evaluation, continuing with UV disinfection technology was determined as the best path
forward. The new UV disinfection system is planned to be constructed adjacent to the south clarifiers and
provides multiple benefits, as shown in Attachment 1. First, it frees the existing UV areas for future
secondary capacity needs that may arise due to changes in regulations. Second, it alleviates the existing
hydraulic bottleneck in the secondary process, which may impact operations during peak wet weather
events and helps improve wet weather management. With completion of the UV Project, Central San will
have state-of-the-art UV disinfection technology. Modern UV lamps are higher intensity and more efficient
than the existing lamps and have the ability to modulate and reduce intensity down to 30 percent based on
flow and water quality while still meeting disinfection requirements. Electricity use of the new UV facility is
expected to be about 50 percent lower than the existing electricity use to treat average flows. Lamp banks
are oriented at 45 degrees which reduces the hydraulic headloss across each channel. Modern UV
equipment includes self-cleaning lamps using an automated wiping system that can be completed without
removing the lamps from the channel. Wipers are activated based on lamp fouling monitored by a UV
intensity meter on each bank or based on time. These improvements will reduce O&M costs and
significantly improve worker safety.
As part of the pre -design, Carollo developed the equipment selection documents, consisting of technical
drawings and specifications for UV equipment. The UV equipment manufacturers were determined by
performing a business case evaluation and included O&M staff input. Staff recommended to pre -select
the UV equipment manufacturer under a competitive and qualified bid process. The UV manufacturer will
provide shop drawings and participate in workshops with staff during the final design. The UV equipment
agreement is intended to be assigned to an installation contractor, therefore the purchase of the equipment
will not be done by Central San. Equipment pre -selection and involving a UV manufacturer in the final
design includes the following advantages:
• Construction drawings and specifications will be based on the vendor's actual equipment;
• Results in a very complete overall design for the installation contractor, particularly process and
instrumentation diagrams and electrical drawings, as the manufacturer's submittals will be approved
during design;
• Improves overall cost estimate during design; and
• Reduces change orders or potential delays in the project timeline.
On September 13, 2022, staff advertised a formal Request for Qualifications and Bids on PlanetBids for
UV disinfection equipment and design support services. On October 14, 2022, Central San received
responses from Trojan Technologies Group ULC (Trojan) and Wedeco (owned by Xylem). Each bid
submittal package contained two parts: Part 1 - Qualifications and Part 2 - Bid. Qualifications included
technical requirements, ability to meet dose and disinfection requirements, successful installations
designed for municipal wastewater in North America sized similarly to Central San. Central San staff and
Carollo conducted an extensive evaluation of the qualifications and determined both vendors met the
qualifications.
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 5 of 32
Page 3 of 15
Bids included the cost for UV lamps, banks, sensors, cables, and electrical components, such as power
distribution centers and electrical control panels, including programmable logic controllers; design services
to coordinate the shop drawings with the installation design, workshops with staff and support; and optional
services, such as an extended warranty, equipment storage, cost for an optional additional bank per
channel, price escalation, and additional as -needed design services.
The low bidder is determined based on a low-cost present worth analysis of capital and select operational
costs (annual electrical use, annual replacement costs for lamps, ballasts, sleeves, sensors and wipers)
over 25 years. Staff opened the bids or present worth costs on November 1, 2022, and received a cost of
$9,395,917.54 from Trojan and $11,384,862 from Wedeco. Trojan was the responsive and responsible
low bidder. The UV equipment cost for Trojan was $4,341,760 and close to the Engineer's estimate of
$4,000,000. Wedeco was slightly lower in capital costs but more costly to operate and maintain at a cost of
$2,000,000 more than Trojan. Central San will pay the manufacturer for approved submittals and the
installation contractor will pay the total equipment cost during construction of the new UV facilities.
The Bid also required pricing to be provided for additional scope and services. After a detailed evaluation
of the optional services, staff is recommending the following be added to the contract:
• Storage of UV disinfection system for up to six months.
• Three-year warranty extension.
• Allowance for additional as -needed design assistance.
• One additional UV bank per channel, if needed.
An additive item for storage of the UV disinfection system was included due to the possible shift in
schedule due to securing electrical equipment to power the UV system under installation contract.
Electrical gear is currently the longest lead item for the UV Project and has been difficult to procure within
the last two years. Staff will work with the vendor to ensure the latest instrumentation and controls
technology is included in the design and included prior to releasing the final shop drawings for fabrication.
Operations staff modified the dissolved oxygen (DO) setpoints in the aeration tanks since June of 2022.
This modification improved effluent quality and increased ultraviolet transmittance (UVT), one of the UV
design parameters. Staff wanted to include the extra UV bank per channel as a conservative measure to
meet permit requirements in the event the DO setpoints did not consistently improve water quality. Staff
will monitor UVT and remove the extra bank from design if staff and the design team believe that Central
San will be able to meet disinfection requirements without the extra bank.
With the UV vendor selected, the final design of the UV Project is recommended to move forward. Central
San has negotiated a scope and fee with Carollo. The current schedule for design and construction of the
UV project is detailed below:
• Submitted a California State Water Resources Control Board (SWRCB) State Revolving Fund
(SRF) application in December 2022. Anticipated status of funding availability in mid-2023;
• Complete Final Design by 2025;
• Bidding will be based on funding and constructability timeline with other ongoing capital projects.
Bidding can occur between 2025-2026;
• Construction duration is estimated between three -to -four years and should be completed and
operational by 2030.
Staff is recommending to proceed with the final design as stated above, but also because larger and more
complex electrical projects take time to complete as staff experienced with the recent Solids Handling
Facility Improvements project. Additionally, the schedule provides flexibility to align with SRF funding
availability.
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 6 of 32
Page 4 of 15
Having the project ready to bid and properly coordinated within the Ten -Year Capital Improvement Plan will
allow Central San to obtain the remaining useful life from existing facilities and create a reliable and safe
replacement timeline of this critical facility at Central San.
California Environmental Quality Act (CEQA)
At its December 15, 2022 meeting the Board of Directors independently found the project was exempt
from the California Environmental Quality Act (CEQA) under Central San's CEQA Guidelines Section
15302 (Replacement or Reconstruction) and Section 15061(b)(3) (Common Sense Exemption). A Notice
of Exemption was filed with the Contra Costa County Clerk on December 16, 2022.
ALTERNATIVES/CONSIDERATIONS
The Board may elect to not authorize the purchase agreement and include the equipment for procurement
under a general contractor and a Central San construction contract. Central San received a low net present
value from a qualified UV equipment vendor and due to the complexity and specialized nature of the
installation design, it is recommended to enter into a contract with the vendor to complete shop drawings
and finalize design. Therefore, this alternative is not recommended.
The SRF application process and scoring is significantly better when the final design is complete as the
project would be viewed as shovel ready. Typically, Central San does not shelve or delay projects for
bidding. However, due to the costs and potential impacts with other capital projects, such as the Solids
Handling Facility Improvements, Phase 1 A and the Aeration Basins Diffuser Replacement projects, staff
recommends completing the final design and then make sure that other projects do not obstruct or
negatively impact operations or the UV Project schedule.
Central San invested significant costs, over a million dollars, replacing critical components several years
ago to allow for this project to proceed in the timeline proposed by staff. The Capital Projects and
Operations Divisions agree and will continue monitoring and maintaining the existing UV facilities until its
replacement by 2030.
FINANCIAL IMPACTS
The total anticipated cost for the purchase agreement is $5,500,000, which includes the following:
• Item 1: $4,341,761 for UV equipment, spare parts, special tools, design assistance, supervision of
installation, testing, training, commissioning, warranty, and support services;
• Item 2: $18,600 for storage of UV disinfection equipment for up to six months;
• Item 3: $190,117 for a three-year extended warranty;
• Item 4: $100,000 for additional as -needed design assistance;
• Item 5: $595,000 for an extra bank of UV lamps per channel; and
• The remaining amount of $254,522 of contract contingency.
Carollo's final design services for the project is estimated at $4,400,000. The UV Project is listed in the
Fiscal Year (FY) 2022-23 Budget on page 251 at a total estimated project budget of nearly $68,500,000.
There are adequate funds within the current budget and future budget for the final design of this project.
Staff submitted a SW RCB SRF application in December 2022 for a $65,000,000 low interest loan for FY
2023-24. If the project is not selected for a SRF loan or if funding is not available in 2023, staff can amend
and resubmit the application by December 2023 for FY 2024-25. Construction would start after the
SWRCB project review is completed and a loan agreement is executed.
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 32
Page 5 of 15
At this time, the Financial Impact consists of the final design at $4,400,000, Trojan's design assistance at
roughly $250,000, and staff time. The UV equipment and installation costs are intended to be covered by
the SRF agreement and will be presented to the Board at a future date.
COMMITTEE RECOMMENDATION
The Engineering & Operations Committee reviewed this matter at its January 23, 2023 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following Board action to authorize the General Manager to:
1. Execute a purchase agreement in an amount not to exceed $5.5 million with Trojan Technologies
Group ULC for UV disinfection equipment and special services for the UV Disinfection
Replacement, District Project 100012; and
2. Amend an existing professional engineering services agreement with Carollo Engineers, Inc. in an
amount not to exceed $4.4 million, increasing the cost ceiling to $5.3 million, for final design
services.
Strategic Plan Tie -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations, Strategy 4 - Identify and advance sustainability initiatives, including
reducing energy usage and emissions
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3 - Maintain financial stability and sustainability
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX. Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Presentation
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 32
Page 6 of 15
Ultraviolet (UV) Disinfection Replacement Project
District Project 100012 Location
Map Date: 10/11/2022
Martinezetail Area
Concord
X \ Pleasant H
d
n
W�
I
n
1 c
J.
Y oc
Project jam
Location
m AA
Q District -Owned Property
Q Project Location and Number
Note: 0 400 800 Map Displayed in North American Datum of 1983 Attachment
Central San data as of October 2022. H Feet California State Plane, Zone III FIPS O403, US Feet 1
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 32
Page 7 of 15
Attachment 2
Central Contra Costa Sanitary District
REQUEST FOR QUALIFICATIONS AND BID
ULTRAVIOLET DISINFECTION EQUIPMENT FOR
THE ULTRAVIOLET DISINFECTION REPLACEMENT
District Project No. 100012
Draft Summary of Bids
Bid Opening: November 1, 2022, 11:00 AM
Engineer's Estimate: $4,000,000
No.
Bidder
Total Bid
1
Trojan Technologies Group ULC
$9,395,917.54
2
Xylem Water Solutions USA, Inc./Wedeco
$11,384,862.00
Subcontractor Lists
Subcontractor
Work Description
Contractor 1
None
Contractor 2
None
Bids Opened By: /s/Katie Young
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 32
Page 1 of 1
Page 8 of 15
Attachment 3
UV System Background
In 1994, Central San installed 18 banks of
UV lamps under the UV Facilities (District
Project 7100) in 6 channels
In 2006, another 6 banks were added
under the UV Expansion Project (DP 7240)
in 2 additional channels
Fischer -Porter was the original
manufacturer and patent holder. The
rights sold several times and now belong
to Ironbrook UV in Canada
FIX
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 11 of 32
Page 9 of 15
3
Drivers for UV Disinfection Replacement Project
Aging Infrastructure
• Majority of UV system planned to
be in service for nearly 40 years
• Staff has excelled at keeping
system reliable and operational
Sustainability/Optimization
• Energy -efficient improvements
• Smarter controls (i.e., dosage based
on UV transmittance and flows)
• Easier maintenance - built-in cleaninf
systems
MGD = Million gallons per day
Capacity
• Review process improvements or
optimizations to gain capacity
• Addressing hydraulic bottleneck to
increase capacity to 127 mgd
Regulation_
• Comply with regulations as
disinfection is critical for
discharge permit
• Use existing basins if -and -when
regulations become more
restrictive
ry��
rosuslu ear
INEW NV 5111UCTU„E
I
e'�l
��i rm �— FF CNaNNEL
I
5
@@ f
81a11LTUPEX � er
P� ie� �L„i
oa
9 44 DI0
Proposed UV System
'° iE ��
i�
'� 1
�¢ 4
Location and Flow
R
;
Path Removes��.1
Hydraulic
Bottlenecks
41�®
vEnslo„c,Lie aE'
r
EXISTING
. GE41aB
--+ OUT OF SFWIGE
siacni
`7 WET WELLL�No
FUMP e_
` aid
ggp
2
3
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 32 2
Page 10 of 15
New UV Facilities
Location Near the
South Clarifiers
yj.
5
New UV Facilities
Coordinated with
Future Site Planning
I
a
ME 1"
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 32 3
Page 11 of 15
UV Equipment Supplier Scope of Work
UV Disinfection Equipment
UV modules, lamps, sensors, power distribution center, lamp and control
cables, cleaning and lift mechanisms, controls, instrumentation and controls
Spare Parts and Tools
Lamps, ballasts, cables, sensors, etc.
Design Assistance
Shop drawings, design workshops, design support including instrumentation
and controls
Installation Support
Factory testing, field services, including coordinating with the Installation
Contractor during Construction for the installation of the equipment, assisting
during startup and testing, training, and programming
Bid Process Timeline
UV Disinfection Replacement Project presented to
Engineering and Operations (E&O) Committee on March 30,
2021, and announced at the Board meeting on April 15, 2021
Staff posted Request for Qualifications and Bid for UV
Disinfection equipment and services on September 13, 2022
Received two submittal packages on October 14, 2022; staff
reviewed the qualifications part of each bid package and
determined both met all qualifications
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 14 of 32 4
Page 12 of 15
Bid Results
The basis of selection for the vendor was lowest present
worth costs consisting of capital and select operational costs
(annual electrical use, annual replacement costs for lamps,
ballasts, sleeves, sensors and wipers) over 25-years'
Opened bid packages on November 1, 2022; and received
costs of $9,395,917 from Trojan Technologies and
I
$11,384,862 from Wedeco
The UV equipment cost for Trojan Technologies is
$4,341,760; the Engineer's estimate was $4,000,000
0
Total Estimated Equipment Contract Value
The total anticipated cost for the vendor contract is up to $5,500,000, which includes the
following
Item 1: $4,341,761 for UV equipment, spare parts, special tools, design assistance,
supervision of installation, testing, training, commissioning, warranty, and support
services
Item 2: $18,600 for storage of UV disinfection equipment for up to 6 months
Item 3: $190,117 for an extended warranty
Item 4: $100,000 for additional as -needed design assistance
Item 5: $595,000 for an extra bank of UV lamps per channel
Remaining amount at around 5% as contingency
10
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 15 of 32 5
Page 13 of 15
Amend Engineering Agreement
Carollo Engineers, Inc. selected after a competitive formal public
solicitation and proposal process
Scope of Services include all engineering services from planning
to engineering services during construction
Final design services negotiated up to $4.4 Million (M)
Staff intends to limit scope to 90-percent final design for SRF Loan
Application process
Staff will not proceed to 100-percent until construction timeline
and funding is more accurate
SRF = State Revolving Fund
11
12
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 16 of 32 6
Page 14 of 15
Total Project Budget
The total estimate project budget is
nearly $68.5 M
Equipment purchase contract
anticipated in construction budget
Design includes consultant and staff
costs
13
$1,800,000 $0 $1,800,000
$4,680,000 $1,300,000 $5,980,000
$0 $60,7000,000 $60,700,000
Authorize the General Manager to:
Execute a purchase agreement in an
amount not to exceed $5.5 million with
Recommended Trojan Technologies Group ULC for
ultraviolet (UV) disinfection equipment
Board Action and special services for the UV
Disinfection Replacement, District Project
100012; a n d
Amend an existing professional
engineering services agreement with
Carollo Engineers, Inc. in an amount not
to exceed $4.4 million, increasing the
cost ceiling to $5.3 million, for final
design services
14
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 17 of 32 7
Page 15 of 15
Questions?
15
January 23, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 18 of 32 $