HomeMy WebLinkAbout05.b. Execute a purchase agreement with Trojan Technologies, Group ULC for ultraviolet (UV) disinfection equipment and special services for the UV Disinfection Replacement, District Project 100012; and amend existing agreement with Carollo EngineersPage 1 of 14
Item 5.b.
DCENTRALSAN
MEETING DATE: JANUARY5, 2023
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
SUBJECT: REVIEW DRAFT POSITION PAPER AUTHORIZING THE GENERAL
MANAGER TO:
1. EXECUTE A PURCHASE AGREEMENT I N AN AMOUNT NOT TO
EXCEED $5.5 MILLION WITH TROJAN TECHNOLOGIES, GROUP
ULC FOR ULTRAVIOLET (UV) DISINFECTION EQUIPMENTAND
SPECIAL SERVICES FOR THE UV DISINFECTION REPLACEMENT,
DISTRICT PROJECT 100012; AND
2. AMEND AN EXISTING PROFESSIONAL ENGINEERING SERVICES
AGREEMENT WITH CAROLLO ENGINEERS IN AN AMOUNT NOT TO
EXCEED $4.4 MILLION, INCREASING THE COST CEILING TO $5.3
MILLION, FOR FINAL DESIGN SERVICES
SUBMITTED BY: INITIATING DEPARTMENT:
AMANDA CAUBLE, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES -
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
ISSUE
The Board of Directors (Board) authorization is required for contracts or professional engineering services
agreement above $200,000 in the Capital Program.
BACKGROUND
Central San built the existing UV Facilities to replace gaseous chlorination disinfection for the treatment
plant (plant) effluent in 1994. Fischer -Porter was the original manufacturer, patent holder, and is no longer
in business. The patent rights were sold several times, first to Elsag Bailey, then ABB, and now belongs to
I ronbrook UV of Canada.
Most of the current UV system has been in service for roughly 29 years and requires substantial
maintenance, lamp replacement, and frequent chemical cleaning of UV banks. For wet weather operation,
the UV system has a capacity of between 90 to 100 million gallons per day (MGD). The treatment plant is
designed to handle up to 127 MGD. Thus, the existing UV system at its current location and downstream
infrastructure creates a bottleneck effect in the secondary treatment process, limiting the discharge of
disinfected final effluent during peak wet weather events.
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 34 DRAFT
Page 2 of 14
On January 11, 2021, Central San initiated a formal public solicitation for engineering services for the UV
Disinfection Replacement Project, District Project 100012 (UV Project), and seven consulting engineering
firms responded with qualified and responsive proposals. Carollo Engineers Inc. (Carollo) ranked as the
top firm and was recommended to be the designer, or engineer of record, for the UV Project. On April 15,
2021, the Board authorized the General Manager to execute a professional engineering services
agreement with Carollo in an amount not to exceed $900,000 for planning and pre -design services.
To date, a condition assessment of the existing UV system was performed under the UV Project that
evaluated alternative state-of-the-art disinfection technologies, such as LED UV, ozone, peracetic acid,
and sodium hypochlorite disinfection to determine the optimal disinfection system for Central San. Based
on a comprehensive evaluation, continuing with UV disinfection technology was determined as the best
path forward. The new UV disinfection system is planned to be constructed adjacent to the south clarifiers
and provides multiple benefits. First, it frees the existing UV areas for future secondary capacity needs
that may arise due to potential nutrient regulations. Second, it alleviates the existing hydraulic bottleneck in
the secondary treatment plant, limiting the discharge of disinfected final effluent during the peak wet
weather events as the new UV system will be sized to 127 MGD.
As part of the pre -design, Carollo developed the equipment selection package that consists of technical
drawings and specifications for UV equipment manufactures. The UV equipment manufactures were
determined by performing Business Case Evaluations and included the input of Operations and
Maintenance staff. Staff recommended to pre -select the UV equipment manufacturer under a competitive
and qualified bid process to complete the UV Project final design with Carollo. The UV manufacturer will
also assist in the final design and the pre -purchase contract is intended to be assigned to an installation
contractor. Equipment pre -selection and including a UV manufacturer to the final design brings the
following advantages:
• Construction drawings and specifications will be based on the vendor's actual equipment;
• Results in a very complete overall design for the installation contractor, particularly Process and
Instrumentation Diagrams (P&I Ds) and Electrical drawings, as the manufacturer's submittals will be
approved during design;
• Improves overall cost estimate during design; and
• Reduces change orders or potential delays in the project timeline.
On September 13, 2022, staff advertised a formal Request for Qualifications and Bids on PlanetBids for
UV disinfection equipment and design support services. On October 14, 2022, Central San received
qualification and bid packages from Trojan Technologies (Trojan) and Wedeco (owned by Xylem). Each
bid submittal package contained two parts: Part 1 - Qualifications and Part 2 - Bid. Qualifications included
technical requirements, ability to meet dose and disinfection requirements, successful installations
designed for municipal wastewater in North America sized similarly to Central San. Central San staff and
Carollo conducted an extensive evaluation of the qualifications and determined both suppliers met the
qualifications.
Bids included costs for UV lamps, banks, sensors, cables, electrical components such as power
distribution centers, electrical control panels including programmable logic controllers (PLCs); design
services to coordinate the shop drawings with the installation design, workshops with staff and support;
optional services such as an extended warranty, equipment storage, cost for an optional additional bank
per channel, price escalation or de-escalation, and additional as -needed design services.
The equipment basis of selection is a low-cost selection based on a present worth analysis of capital and
select operational costs (annual electrical use, annual replacement costs for lamps, ballasts, sleeves,
sensors and wipers) over 25-years. Staff opened the bids of both qualified suppliers on November 1,
2022, and received a cost of $9,395,917.54 from Trojan and $11,384,862 from Wedeco. Trojan is the
responsive and responsible low bidder. The UV equipment cost for Trojan is $4,341,760 and close to the
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 14 of 34 DRAFT
Page 3 of 14
Engineer's estimate of $4,000,000. Wedeco was slightly lower in capital costs but more costly to operate
and maintain at a future cost of $2,000,000 more than Trojan. Central San will pay the manufacturer for
approved submittals and the installation contractor will pay the balance of the total equipment cost when the
purchase agreement is assigned to them.
The Bid also required pricing to be provided for additional scope and services. After a detailed evaluation
of the optional services, staff is recommending the following be added to the contract:
• Storage of UV Disinfection system for up to six months for $18,300.
• Three-year warranty extension for $190,117.
• Allowance for additional as -needed design assistance for $100,000.
• One additional UV bank per channel for $595,000, if needed.
An additive item for storage of the UV disinfection system was included due to the possible shift in
schedule due to securing electrical equipment to power the UV system under installation contract.
Electrical gear is currently the longest lead item for the UV Project and has been difficult to procure within
the last two years. Operations staff modified the dissolved oxygen (DO) setpoints in the aeration tanks
since June 2022. This modification improved effluent quality and increased ultraviolet transmittance (UVT),
one of the UV design parameters. Staff wanted to include the extra UV bank per channel as a conservative
measure to meet permit requirements in the event the DO setpoints did not consistently improve water
quality. During design, staff will monitor UVT and remove the extra bank from the design if staff and the
design team feel Central San will be able to meet disinfection requirements without the extra bank.
With procurement complete and the vendor selected, the final design of the UV Project is recommended
to move forward. Central San has negotiated a scope and fee with Carollo Engineers for the final design
services. Staff is planning to use Carollo to produce up to the 90-percent final design in order to acquire
financing from the California State Revolving Fund (SRF). The time required for the design and potential
construction of the UV project is noted below:
• Complete 90-percent set of project documents by mid-2024
• Final Design and bidding will be based on funding, constructability timeline with other ongoing capital
projects, and status of the existing UV system reliability. Bidding is currently estimated in 2025; and
• Construction completed by 2029 and in operation by 2030. The existing equipment will have been in
service for nearly 37 years and beyond its useful life around this time.
Staff is recommending to proceed with the design as stated above, but also because larger and more
complex electrical projects take time to complete as experienced with the recent Solids Handling Facility
Improvements project. Having the project ready to bid and properly coordinated within the ten-year Capital
Improvement Plan will allow Central San to obtain all the useful life from the existing facilities and create a
reliable and safe operation replacement timeline of this critical facility at Central San.
California Environmental Quality Act (CEQA)
Staff has concluded that this project is exempt from the California Environmental Quality Act (CEQA)
under Central San's CEQA Guidelines Section 15302 since it involves replacement of existing public
facilities at substantially the same location and with the same purpose as the public facilities being
replaced. The projects are also exempt under Central San's CEQA Guidelines Section 15061(b)(3), since
it can be seen with certainty that there is no possibility that the activity in question may have a significant
effect on the environment. This certainty is based on the Central San's past experience with construction
of numerous treatment plant improvement projects of this nature, its long familiarity with the project site,
Central San's impact -limiting construction specifications, and the impact -limiting components of the project
description. Central San's specifications are standardized general and special conditions that are made
part of the project to address environmental considerations, as well as compliance with applicable federal,
state, county, district, municipal and local laws, ordinances, orders, and regulations.
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 15 of 34 DRAFT
Page 4 of 14
ALTERNATIVES/CONSIDERATIONS
The Board may elect to not authorize the purchase agreement and include the equipment for procurement
under a general contractor and a Central San construction contract. Central San received a low net present
value from a qualified UV equipment vendor and due to the complexity and specialized nature of the
installation design, it is recommended to enter into a contract with the vendor to complete shop drawings
and finalize the design. The SRF application process and scoring is significantly better when the final
design is complete as the project would be viewed as shovel ready. Typically, Central San does not shelve
or delay projects for bidding. However, due to the costs and potential impacts with other capital projects
such as the Solids Handling Facility Improvements -Phase 1A and the Aeration Diffuser Replacement
projects, staff recommends completing the final design and then make sure that other projects do not
obstruct or negatively impact operations. Therefore, this alternative is not recommended.
FINANCIAL IMPACTS
The total anticipated cost for the purchase agreement is $5,500,000, which includes the following:
• Item 1: $4,341,761 for UV equipment, spare parts, special tools, design assistance, supervision of
installation, testing, training, commissioning, warranty, and support services;
• Item 2: $18,600 for storage of UV disinfection equipment for up to six months;
• Item 3: $190,117 for a three-year extended warranty;
• Item 4: $100,000 for additional as -needed design assistance;
• Item 5: $595,000 for an extra bank of UV lamps per channel; and
• The remaining amount of $254,522 of contract contingency.
Carollo's final design services for the project is estimated at $4,400,000. The UV Project is listed in the
Fiscal Year (FY) 2022-23 Budget on page 231 at a total estimated project budget of nearly $68,500,000. There
are adequate funds within the current budget and future budget for the final design of this project.
COMMITTEE RECOMMENDATION
The Engineering & Operations Committee reviewed this matter at its January 5, 2023 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following Board action to authorize the General Manager to:
1. Execute a purchase agreement in an amount not to exceed $5.5 million with Trojan Technologies,
Group ULC for ultraviolet (UV) disinfection equipment and special services for the UV Disinfection
Replacement, District Project 100012; and
2. Amend an existing professional engineering services agreement with Carollo Engineers in an
amount not to exceed $4.4 million, increasing the cost ceiling to $5.3 million, for final design
services.
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 16 of 34 DRAFT
Page 5 of 14
Strategic Plan Tie -In
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations, Strategy 4 - Identify and advance sustainability initiatives, including
reducing energy usage and emissions
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3 - Maintain financial stability and sustainability
GOAL FIVE: Safety and Security
Strategy 2 - Protect Personnel and assets from threats and emergencies
GOAL SIX. Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Presentation
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 17 of 34 DRAFT
Page 6 of 14
Ultraviolet (UV) Disinfection Replacement Project
District Project 100012 Location
Map Date: 10/11/2022
Martinezetail Area
Concord
X \ Pleasant H
d
n
W�
I
n
1 c
J.
Y oc
Project jam
Location
m AA
Q District -Owned Property
Q Project Location and Number
Note: 0 400 800 Map Displayed in North American Datum of 1983 Attachment
Central San data as of October 2022. H Feet California State Plane, Zone III FIPS O403, US Feet 1
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 18 of 34 DRAFT
Page 7 of 14
Attachment 2
Central Contra Costa Sanitary District
REQUEST FOR QUALIFICATIONS AND BID
ULTRAVIOLET DISINFECTION EQUIPMENT FOR
THE ULTRAVIOLET DISINFECTION REPLACEMENT
District Project No. 100012
Draft Summary of Bids
Bid Opening: November 1, 2022, 11:00 AM
Engineer's Estimate: $4,000,000
No.
Bidder
Total Bid
1
Trojan Technologies Group ULC
$9,395,917.54
2
Xylem Water Solutions USA, Inc./Wedeco
$11,384,862.00
Subcontractor Lists
Subcontractor
Work Description
Contractor 1
None
Contractor 2
None
Bids Opened By: /s/Katie Young
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 19 of 34 DRAFT
Page 1 of 1
Page 8 of 14
Attachment 3
1
UV System Background
In 1994, Central San installed 18 banks of
i
UV lamps under the UV Facilities (District
Project 7100) in 6 channels
In 2006, another 6 banks were added
under the UV Expansion Project (DP 7240)�%'
in 2 additional channels
Fischer -Porter was the original
manufacturer and patent holder. The
i
rights sold several times and now belong
to Ironbrook UV in Canada
2
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 20 of 34 DRAFT 1
Page 9 of 14
Drivers for UV Disinfection Replacement Project
Aging Infrastructure
• Majority of UV system planned to
be in service for nearly 40 years
• Staff has excelled at keeping
system reliable and operational
Sustainability/Optimization
• Energy -efficient improvements
• Smarter controls (i.e., dosage based
on UV transmittance and flows)
• Easier maintenance - built-in cleaning
systems
3
Proposed UV System
Location and Flow
Path Removes
Hydraulic
Bottlenecks
4
MGD = Million gallons per day
EXSTI aG
� NEW
• • O
OUT
M5ERJIGE
Capacity
• Review process improvements or
optimizations to gain capacity
• Addressing hydraulic bottleneck to
increase capacity to 127 mgd
Regulations
• Comply with regulations as
disinfection is critical for
discharge permit
• Use existing basins if -and -when
regulations become more
restrictive
1.
I
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 21 of 34 DRAFT 2
Page 10 of 14
New UV Facilities
Location Near the
South Clarifiers
UV Equipment Supplier Scope of Work
UV Disinfection Equipment
UV modules, lamps, sensors, power distribution center, lamp and control
cables, cleaning and lift mechanisms, controls, instrumentation and controls
Spare Parts and Tools
Lamps, ballasts, cables, sensors, etc.
Design Assistance
Shop drawings, design workshops, design support including instrumentation
and controls
Installation Support
Factory testing, field services, including coordinating with the Installation
Contractor during Construction for the installation of the equipment, assisting
during startup and testing, training, and programming
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 22 of 34 DRAFT 3
Page 11 of 14
Bid Process Timeline
UV Disinfection Replacement Project presented to
Engineering and Operations (E&O) Committee on March 30,
2021, and announced at the Board meeting on April 15, 2021
Staff posted Request for Qualifications and Bid for UV
Disinfection equipment and services on September 13, 2022
Received two submittal packages on October 14, 2022; staff
reviewed the qualifications part of each bid package and
determined both met all qualifications
7
Bid Results
The basis of selection for the vendor was lowest present
worth costs consisting of capital and select operational costs
(annual electrical use, annual replacement costs for lamps,
ballasts, sleeves, sensors and wipers) over 25-years
Opened bid packages on November 1, 2022; and received
costs of $9,395,917 from Trojan Technologies and
$11,384,862 from Wedeco
The UV equipment cost for Trojan Technologies is
$4,341,760; the Engineer's estimate was $4,000,000
8
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 23 of 34 DRAFT 4
Page 12 of 14
Total Estimated Equipment Contract Value
The total anticipated cost for the vendor contract is up to $5,500,000, which includes the
following
Item 1: $4,341,761 for UV equipment, spare parts, special tools, design assistance,
supervision of installation, testing, training, commissioning, warranty, and support
services
Item 2: $18,600 for storage of UV disinfection equipment for up to 6 months
Item 3: $190,117 for an extended warranty
Item 4: $100,000 for additional as -needed design assistance
Item 5: $595,000 for an extra bank of UV lamps per channel
Remaining amount at around 5% as contingency
Amend Engineering Agreement
Carollo Engineers, Inc. selected after a competitive formal public
solicitation and proposal process
Scope of Services include all engineering services from planning
to engineering services during construction
Final design services negotiated up to $4.4 Million (M)
Staff intends to limit scope to 90-percent final design for SRF Loan
Application process
Staff will not proceed to 100-percent until construction timeline
and funding is more accurate
SRF = State Revolving Fund
10
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 24 of 34 DRAFT 5
Page 13 of 14
Project Schedule r
90-percent Design completion by mid-2024 AL
100-percent Design and bidding in 2025, \
at the earliest
New UV facilities operational and 4
permitted by 2030; existing UV Facilities
turned off and are potential back-up facility -
until basins are needed for other uses _ .. .
11
Total Project Budget
The total estimate project budget is
nearly $68.5 M Mdate®
Equipment purchase contract $1,800,000 $0 $1,800,000
anticipated in construction budget $4,680,000 $1,300,000 $5,980,000
Design includes consultant and staff Construction $0 $60,7000,000 $60,700,000
costs
12
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet -Page 25 of 34 DRAFT 6
Page 14 of 14
Authorize the General Manager to:
Execute a purchase contract with Trojan
Technologies Group ULC for Ultraviolet
Recommended Disinfection Equipment and special
Board Action services in an amount not to exceed
$5,500,000
Amend an existing professional
engineering services agreement with
Carollo Engineers, Inc. in an amount not
to exceed $4.4 million, increasing the
cost ceiling to $5.3 million, for final
design services for the UV Project
13
14
January 5, 2023 EOPS Regular Committee Meeting Agenda Packet - Page 26 of 34 DRAFT 7