CENTRAL CONTRA COSTA SANITARY DISTRICT
November 17, 2022
TO: HONORABLE BOARD OF DIRECTORS
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: PHILIPLEIBER, DIRECTOR OF FINANCE AND ADMINISTRATION
SUBJECT: RECEIVE PRE-AUDIT FISCAL YEAR 2021-22 CAPITAL IMPROVEMENT
BUDGET YEAR-END STATUS REPORT
The Board of Directors (Board) approves the Capital Improvement Budget (CIB) and Ten-Year Plan on a
yearly basis. At fiscal year (FY) end, staff reviews and compares the final revenues and expenditures,
based on the pre-audit financial reports to update the Board on the progress of the Capital Improvement
Program.
A public hearing was held on June 3, 2021, after which the Board adopted the FY 2021-22 Cl B. The
proposed revenue and estimated expenditures for FY 2021-22 Cl B were approximately$32,243,421 and
$105,455,000, respectively. Based on the pre-audit June 2022 financial statements, the actual revenues
and expenditures including carry-forward and budget transfers are $32,343,693 and $73,636,093, as
detailed in Attachment 1 - Pre-Audit FY2021-22 CIB Year-End Status Report. A revenue of$34,120,000
was anticipated from the State Revolving Fund loan under the Solids Handling Facility Improvements,
District Project 7348. However, the project schedule and scope of work have been changed.
Attachment 2 is the presentation staff will review with the Board.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1 -Achieve compliance in all regulations, Strategy 3- Be a partner in regional development of local water
supply
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3- Maintain financial stability and sustainability
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness, Strategy 2- Protect personnel and assets from threats and
emergencies
November 17, 2022 Regular Board Meeting Agenda Packet- Page 32 of 101
Page 2 of 10
GOAL SIX.Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2- Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Pre-Audit FY2021-22 C I B Year-End Status Report
2. Presentation
November 17, 2022 Regular Board Meeting Agenda Packet- Page 33 of 101
Page 3 of 10
Attachment 1
Pre-Audit Fiscal Year (FY) 2021-22 Capital Improvement Budget (CIB)
Year-End Status Report
Sewer Construction Fund (Fund 20):
"(Variance)
Revenue
Sewer Service Charge $10,035,739 $10,267,767 2.3%
Ad Valorem Taxes $6,940,168 $8,856,057 27.6%
Capacity Fees $5,799,000 $4,418,244 -23.8%
Pumped Zone Fees $151,000 $133,938 -11.3%
Developer Fees $296,000 $293,099 -1.0%
Interest Income $319,000 $342,006 7.2%
City of Concord $8,700,914 $7,799,702 -10.4%
Other Revenue Sources $1,600 $232,881 >100%
Sub-total Revenue $32,243,421 $32,343,693 0.31%
State Revolving Fund
$34,120,000 $0 -
Loan Proceeds
Total Revenue Projected $66,363,421 $32,343,693 -51.4%
Program t1iims Carry
11 Budget** to-Actua to-Actual
. . -
Budget* Actual Forward
Expenditures
Collection System $39,795,000 $49,507,745 $31,375,554 -21.1% -36.6%
Treatment Plant $45,230,000 $65,878,267 $24,360,324 -46.1% -63.0%
General
Improvements $3,830,000 $5,432,436 $2,191,232 -42.8% -59.7%
Recycled Water $16,600,000 $19,825,679 $15,708,983 -5.4% -20.8%
Total $105,455,000 $140,644,127 $73,636,093 -30.2% -47.6%
Expenditures
November 17, 2022 Regular Board Meeting Agenda Packet- Page 34 of 101
Page 4 of 10
Attachment 1
Pre-Audit Fiscal Year (FY) 2021-22 Capital Improvement Budget (CIB)
Year-End Status Report
NOTES:
Contingency budget at beginning of year was $2,500,000 and not included at year end, any
remaining balance will be a positive variance to the sewer construction fund. The balance was
$2,346,000. The budgeted figures below also exclude project close-out savings of$2,846,519.
The total FY 2021-22 CIB authorized spend gross of contingency and close-out savings known at
year end is $145,836,673.
Includes carry-forward from past fiscal years and transfers
November 17, 2022 Regular Board Meeting Agenda Packet- Page 35 of 101
Page 5 of 10
Attachment 2
November 17,2022
PRE-AUDIT FISCAL y ,
YEAR 2021-22 •-
CAPITAL
IMPROVEMENT
BUDGET YEAR-END q y
STATUS REPORT
Board Meeting
Edgar J.Lopez,P.E.
Capital Projects Division Manager
1
PRE-AUDIT FY 2021-22
REVENUE
Budget Actual Budget-t
Actual
Revenue
Sewer Service Charge $10,035,739 $10,267,767 2.3%
Ad Valorem Taxes $6,940,168 $8,856,057 27.6%
Capacity Fees $5,799,000 $4,418,244 -23.8%
Pumped Zone Fees $151,000 $133,938 -11.3%
Developer Fees $296,000 $293,099 -1.0%
Interest Income $319,000 $342,006 7.2%
City of Concord $8,700,914 $7,799,702 -10.4%
Other Revenue Sources $1,600 $232,881 >1001/.
Sub-total Revenue $32,243,421 $32,343,693 0.31%
State Revolving Fund $34,120,000 $0
Loan Proceeds
Total Revenue Projected $66,363,421 $32,343,693 -61.4%
November 17, 2022 Regular Board Meeting Agenda Packet- Page 36 of 101 1
Page 6 of 10
PRE-AUDIT FY 2021-22
EXPENDITURES
1
f f Carry
Programiance) (Variance)
Actual Budget-
to-Actual to-Actual
Expenditures
Collection System $39,795,000 $49,507,745 $31,375,554 -21.1% -36.6%
Treatment Plant $45,230,000 $65,878,267 $24,360,324 -46.1% -63.0%
General $3,830,000 $5,432,436 $2,191,232 -42.8% -59.7%
Improvements
Recycled Water $16,600,000 $19,825,679 $15,708,983 -5.4% -20.8%
Total $105,455,000 $140,6449127 $73,636,093 -30.2% -47.6%
Expenditures
NOTES Contingency budget at beginning of year was$2,500,000 and not included at year end,any
remaining balance will be a positive variance to the sewer construction fund.The balance was
$2,346,000. The budgeted figures below also exclude project close-out savings of$2,846,519.
hb The total FY 2021-22 CIB authorized spend gross of contingency and close-out savings known at
Year
end is$145,836,673.
Includes carry-forward from past fiscal years and transfers
s,
CAPITAL PROGRAM - MAJOR REASONS FOR
PROJECT VARIANCES IN FY 2021
• Construction projects timelines are not going as projected.
• Timelines are being driven by vendor delivery and material
shortages including metals,electrical,resins,and equipment
manufacturing.
• Approximately up to $25 million of construction
commitments (contractor and consultant) have been
rescheduled into FY 2022.
• Treatment Plant and Recycled Water Programs are the
most impacted due to seasonal and operational constraints.
• Assumptions in project delivery are being revisited for next
budget cycle and will include changes moving forward.
A
November 17, 2022 Regular Board Meeting Agenda Packet- Page 37 of 101 2
Page 7 of 10
MAJOR PROJECT VARIANCES (41 MILLION)
- COLLECTION SYSTEM PLANNING
Large Diameter Pipeline Funds are available in FY
Inspection Program, $1,626,791 $85,730 2022-23.
District Project(DP)8443
Large Diameter Piping
Renovation Program,DP $2,000,000 $302 Awaiting inspection results
100007 from DP 8443.
Force Main Inspection $1,109,475 $2,607 Funds are available in FY
Program,DP 8444 2022-23.
1
MAJOR PROJECT VARIANCES (0$1 MILLION)
- COLLECTION SYSTEM PROJECT COORDINATION
Pleasant Hill Sewer Coordinating with CC Water,
Renovations,Phase(Ph.) $1,177,238 $42,586 PG&E,and City.Project in
2,DP 5991 design.
Land acquisition longer than
Pump Station Upgrades, $3,613,636 $1,022,867 anticipated due to utility ROW.
Ph.2,DP 8457 2A Contract awarded and
awaiting Notice to Proceed.
Martinez Sewer Coordinated with City Paving
Renovations,Ph.7,DP $2,203,174 $259,863 project.Contract award
8464 scheduled this October.
1
November 17, 2022 Regular Board Meeting Agenda Packet- Page 38 of 101 3
Page 8 of 10
MAJOR PROJECT VARIANCES (41 MILLION)
- COLLECTION SYSTEM SCHEDULES MODIFIED
Pump Station Upgrades, $15,051,580 $13,820,107 Construction completed in FY
Ph.1,DP 8436 2022-23.
Walnut Creek Sewer Funds are available in FY
Renovations,Ph.15,DP $4,872,965 $3,594,771 2022-23.
8465
1
MAJOR PROJECT VARIANCES ($1 MILLION)
- TREATMENT PLANT PROJECT CHANGES
Solids Handling Facility Project being repackaged,
Improvements,DP 7348 $18,830,205 $2,747,846 reduced scope and coordinated
with Phase 2.
Plant Wide Instrumentation $1,310,515 $0 Optimization group leading and
Upgrades,DP 7357 awaiting IT Master Plan
Solids Handling Facility
17'G 600,000 $191,043 Planning in progress,funds
b W'%aYu4'ProgralT' available for FY 2022.
UV Disinfection $2,306,768 $1,045,869 Pre-purchase changed to pre-
Replacement,DP 100012 selection,design in progress.
Aeration Basins Diffuser Pre-purchase changed to pre-
Replacement&Seismic $2,284,903 $817,601 selection,project phased and
Upgrades,DP 100019 design in progress.
1
November 17, 2022 Regular Board Meeting Agenda Packet- Page 39 of 101 4
Page 9 of 10
MAJOR PROJECT VARIANCES ($1 MILLION
- TREATMENT PLANT SCHEDULES MODIFIED
Treatment Plant Piping Construction ongoing and funds
Renovations,Ph.10,DP $4,782,587 $1,223,992 available for FY 2022.
7369
Annual Infrastructure Equipment and long lead items
Replacement,DP 7370 $2,418,966 $805,407 impacting spending.Funds
available for FY 2022
R91VO,%F(Rl(P�j ra Several contracts in place,
DP1 0001 g ,042,498 $19,493 awaiting materials and start of
construction.
Air Conditioning and Funds available for FY 2022,
Lighting Renovations,DP $1,249,734 $380 seeking energy rebates and
100010 program incentives.
Electric Blower $8,233,172 $4,979,230 Construction ongoing and funds
Improvements,DP 100015 available for FY 2022.
1
MAJOR PROJECT VARIANCES ($1 MILLION)
RECYCLED WATER SCHEDULE MODIFIED
Filer Plant and Clearwell Construction ongoing and funds
Improvements,Ph.1A, $18,165,424 $15,563,494 will carry over and be available
DP 7361 in FY 2022.
1
November 17, 2022 Regular Board Meeting Agenda Packet- Page 40 of 101 5
Page 10 of 10