HomeMy WebLinkAbout05.c. Receive Pre-Audit Fiscal Year 2021-22 Capital Improvement Budget Year-End Status ReportPage 1 of 10
Item 5.c.
F__1_448�411C_S0
October 25, 2022
TO: FINANCE COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: PHILIPLEIBER, DIRECTOR OF FINANCE AND ADMINISTRATION
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE PRE -AUDIT FISCAL YEAR 2021-22 CAPITAL IMPROVEMENT
BUDGET YEAR-END STATUS REPORT
The Board of Directors (Board) approves the Capital Improvement Budget (CIB) and Ten -Year Plan on a
yearly basis. At fiscal year (FY) end, staff reviews and compares the final revenues and expenditures,
based on the pre -audit financial reports, to update the Board on the progress of the Capital Improvement
Program.
A public hearing was held on June 3, 2021, after which the Board adopted the FY 2021-22 Cl B. The
proposed revenue and estimated expenditures for FY 2021-22 Cl B were approximately $66,363,421 and
$105,455,000, respectively. Based on the pre -audit June 2022 financial statements, the actual revenues
and expenditures including carry -forward and budget transfers are $32,343,693 and $73,636,093, as
detailed in Attachment 1 - Pre -Audit FY 2021-22 Cl B Year -End Status Report.
Attachment 2 is the presentation staff will review with the Committee prior to the Board meeting.
Strateaic Plan re -In
GOAL ONE: Customer and Community
Strategy 1 - Deliver high -quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1 - Achieve compliance in all regulations, Strategy 3 - Be a partner in regional development of local water
supply
GOAL FOUR: Governance and Fiscal Responsibility
Strategy 3 - Maintain financial stability and sustainability
GOAL FIVE: Safety and Security
Strategy 1 - Reduce and eliminate risks of injury or illness, Strategy 2 - Protect personnel and assets from threats and
emergencies
GOAL SIX: Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2 - Execute long-term capital renewal and replacement program
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 64 of 105
Page 2 of 10
GOAL SEVEN: Innovation and Agility
Strategy 1 - Leverage data analytics to become a more efficient utility
ATTACHMENTS:
1. Pre -Audit FY2021-22 C I B Year -End Status Report
2. Presentation
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 65 of 105
Page 3 of 10
Attachment 1
Pre -Audit Fiscal Year (FY) 2021-22 Capital Improvement Budget (CIB)
Year -End Status Report
Sewer Construction Fund (Fund 20):
"(Variance)
Revenue
Sewer Service Charge
$10,035,739
$10,267,767
2.3%
Ad Valorem Taxes
$6,940,168
$8,856,057
27.6%
Capacity Fees
$5,799,000
$4,418,244
-23.8%
Pumped Zone Fees
$151,000
$133,938
-11.3%
Developer Fees
$296,000
$293,099
-1.0%
Interest Income
$319,000
$342,006
7.2%
City of Concord
$8,700,914
$7,799,702
-10.4%
Other Revenue Sources
$1,600
$232,881
>100%
Sub -total Revenue
$32,243,421
$32,343,693
0.31 %
State Revolving Fund
Loan Proceeds
$34,120,000
$0
-
Total Revenue Projected
$66,363,421
$32,343,693
-51.4%
Program Approved Budget -
Budget** to-Actua to -Actual
Expenditures
Collection System
$39,795,000
$49,507,745
$31,375,554
-21.1 %
-36.6%
Treatment Plant
$45,230,000
$65,878,267
$24,360,324
-46.1 %
-63.0%
General
$3,830,000
$5,432,436
$2,191,232
-42.8%
-59.7%
Improvements
Recycled Water
$16,600,000
$19,825,679
$15,708,983
-5.4%
-20.8%
Total
$105,455,000
$140,644,127
$73,636,093
-30.2%
-47.6%
Expenditures
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 66 of 105
Page 4 of 10
Attachment 1
Pre -Audit Fiscal Year (FY) 2021-22 Capital Improvement Budget (CIB)
Year -End Status Report
NOTES:
Contingency budget at beginning of year was $2,500,000 and not included at year end, any
remaining balance will be a positive variance to the sewer construction fund. The balance was
$2,346,000. The budgeted figures below also exclude project close-out savings of $2,846,519.
The total FY 2021-22 CIB authorized spend gross of contingency and close-out savings known at
year end is $145,836,673.
*` Includes carry -forward from past fiscal years and transfers
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 67 of 105
Page 5 of 10
Attachment 2
October 25, 2022
PRE -AUDIT FISCAL
CAPITAL W-7LW4W
IMPROVEMENT
BUDGET YEAR-END q
STATUS REPORTLmwa��AILAM
Finance Committee
Edgar J. Lopez, P.E.
Capital Projects Division Manager
PRE -AUDIT FY 2021-22
REVENUE
IBudget Actual Budget-t
Revenue
Sewer Service Charge
$10,035,739
$10,267,767
2.3%
Ad Valorem Taxes
$6,940,168
$8,856,057
27.6 %
Capacity Fees
$5,799,000
$4,418,244
-23.8%
Pumped Zone Fees
$151,000
$133,938
-11.3%
Developer Fees
$296,000
$293,099
-1.0%
Interest Income
$319,000
$342,006
7.2 %
City of Concord
$8,700,914
$7,799,702
-10.4 %
Other Revenue Sources
$1,600
$232,881
>1001/.
Sub -total Revenue
$32,243,421
$32,343,693
0.31%
State Revolving Fund
Loan Proceeds
$34,120,000
$0
-
Total Revenue Projected
$66,363,421
$32,343,693
-51.49/6
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 68 of 105
Page 6 of 10
PRE -AUDIT FY 2021-22
EXPENDITURES
1
(Variance)
f
Programiance)
f
..12 Actual Budget-
Carry
.,.to -Actual
to -Actual
Expenditures
Collection System
$39,795,000
$49,507,745
$31 ,375,554
-21.1 °%
-36.6°%
Treatment Plant
$45,230,000
$65,878,267
$24,360,324
-46.1 °%
-63.0°%
General
$3,830,000
$5,432,436
$2,191,232
-42.8°%
-59.7°%
Improvements
Recycled Water
$16,600,000
$19,825,679
$15,708,983
-5.4%
-20.8°%
Total
$105,455,000
$140,644,127
$73,636,093
-30.2%
-47.6°%
Expenditures
NOTES Contingency budget at beginning of year was $2,500,000 and not included at year end, any
remaining balance will be a positive variance to the sewer construction fund. The balance was
$2,346,000. The budgeted figures
below also exclude project close-out savings of $2,846,519.
The total FY 2021-22 CIB authorized spend gross of contingency and close-out savings known
at
Yearend is $145,836,673.
" Includes carry -forward from past fiscal years and transfers
hb
s,
3
CAPITAL PROGRAM - MAJOR REASONS FOR
PROJECT VARIANCES IN FY 2021
• Construction projects timelines are not going as projected.
• Timelines are being driven by vendor delivery and material
shortages including metals, electrical, resins, and equipment
manufacturing.
• Approximately up to $25 million of construction
commitments (contractor and consultant) have been
rescheduled into 2022.
• Treatment Plant and Recycled Water Programs are the
most impacted due to seasonal and operational constraints.
• Assumptions in project delivery are being revisited for next
budget cycle and will include changes moving forward.
4
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 69 of 105 2
Page 7 of 10
MAJOR PROJECT VARIANCES (41 MILLION)
- COLLECTION SYSTEM
PLANNING
Large Diameter Pipeline
Inspection Program, $1,626,791
Funds are available in FY
$85,730
District Project (DP) 8443
2022-23.
Large Diameter Piping
Renovation Program, DP $2,000,000
$302 Awaiting inspection results
100007
from DP 8443.
Force Main Inspection $1,109,475 $2,607 Funds are available in FY
Program, DP 8444 2022-23.
5
MAJOR PROJECT VARIANCES (>$1 MILLION)
- COLLECTION SYSTEM PROJECT COORDINATION
Pleasant Hill Sewer
Coordinating with CC Water,
Renovations, Phase (Ph.)
$1,177,238 $42,586 PG&E, and City. Project in
2, DP 5991
design.
Land acquisition longer than
Pump Station Upgrades,
$3,613,636 $1,022,867 anticipated due to utility ROW.
Ph. 2, DP 8457
2A Contract awarded and
awaiting Notice to Proceed.
Martinez Sewer
Coordinated with City Paving
Renovations, Ph. 7, DP
$2,203,174 $259,863 project. Contract award
8464
scheduled this October.
.1
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 70 of 105 3
Page 8 of 10
MAJOR PROJECT VARIANCES (41 MILLION)
— COLLECTION SYSTEM SCHEDULES MODIFIED
Pump Station Upgrades, $15,051,580 $13,820,107 Construction completed in FY
Ph. 1, DP 8436 2022-23.
Walnut Creek Sewer Funds are available in FY
Renovations, Ph. 15, DP $4,872,965 $3,594,771 2022-23.
8465
7
MAJOR PROJECT VARIANCES ($1 MILLION)
— TREATMENT PLANT PROJECT CHANGES
Solids Handling Facility $18,830,205
Improvements, DP 7348
Plant Wide Instrumentation $1,310,515
Upgrades, DP 7357
Solids Handling Facility
%7PW'%aYu4' PrograR,600,000
UV Disinfection $2,306,768
Replacement, DP 100012
Aeration Basins Diffuser
Replacement & Seismic $2,284,903
Upgrades, DP 100019
A
Project being repackaged,
$2,747,846 reduced scope and coordinated
with Phase 2.
$0 Optimization group leading and
awaiting IT Master Plan
$191,043 Planning in progress, funds
available for FY 2022.
$1,045,869 Pre -purchase changed to pre-
selection, design in progress.
Pre -purchase changed to pre-
$817,601 selection, project phased and
design in progress.
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 71 of 105 4
Page 9 of 10
MAJOR PROJECT VARIANCES ($1 MILLION
- TREATMENT PLANT SCHEDULES MODIFIED
Treatment Plant Piping
Renovations, Ph. 10, DP $4,782,587
7369
Annual Infrastructure $2,418,966
Replacement, DP 7370
a VOg%F((Wi(Prigra�,042,498
DP1 0001
Air Conditioning and
Lighting Renovations, DP $1,249,734
100010
Electric Blower $8,233,172
Improvements, DP 100015
I
$1,223,992
Construction ongoing and funds
available for FY 2022.
Equipment and long lead items
$805,407
impacting spending. Funds
available for FY 2022
Several contracts in place,
$19,493
awaiting materials and start of
construction.
Funds available for FY 2022,
$380
seeking energy rebates and
program incentives.
$4,979,230
Construction ongoing and funds
available for FY 2022.
MAJOR PROJECT VARIANCES ($1 MILLION)
RECYCLED WATER SCHEDULE MODIFIED
Filer Plant and Clearwell
Improvements, Ph. 1A, $18,165,424
DP 7361
10
Construction ongoing and funds
$15,563,494 will carry over and be available
in FY 2022.
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 72 of 105 5
Page 10 of 10
Questions?
11
October 25, 2022 Regular FINANCE Committee Meeting Agenda Packet - Page 73 of 105