HomeMy WebLinkAbout23. Emergency situation update re: urgent repairs to Aeration Blower No.2 Page 1 of 2 Item 23. CENTRAL SAN BOARD OF DIRECTORS POSITION PAPER MEETING DATE: OCTOBER 6, 2022 SUBJECT: RECEIVE UPDATE TO DETERMINE WHETHER TO CONTINUE OR TERMINATE THE EMERGENCY SITUATION DECLARED ON AUGUST 4, 2022, AUTHORIZING URGENT REPAIRS TO STEAM DRIVEN AERATION BLOWER NO. 2, IN ACCORDANCE WITH PUBLIC CONTRACT CODE SECTION 22050 SUBMITTED BY: INITIATING DEPARTMENT: STEVE MCDONALD, DIRECTOR OF OPERATIONS-MAINTENANCE OPERATIONS Roger S. Bailey General Manager ISSUE On August 4, 2022, the Board of Directors (Board) authorized to declare an emergency and ratify the General Manager's actions under Public Contract Code Section 22050 to perform emergency repairs to the Steam Driven Aeration Blower No. 2; and authorized an increase to an existing contract in an amount not to exceed $412,600 with Conhagen Rotating Equipment Specialists (Conhagen), increasing the contract cost ceiling up to $550,000, to perform the required repairs. BACKGROUND The contractor, Conhagen, completed the necessary repairs which included custom fabrication of a number of turbine components that are no longer commercially available. Fabrication was followed by installation and then start-up testing services. Installation started on September 7, 2002 and repairs were completed on September 14, 2022. Staff is awaiting final billing. If the final invoice is received prior to the Board meeting on October 6, 2022, then the continuation of this item will not be needed. October 6, 2022 Regular Board Meeting Agenda Packet- Page 316 of 317 Page 2 of 2 ALTERNATIVES/CONSIDERATIONS No feasible alternatives. FINANCIAL IMPACTS The total estimated cost for this repair is $550,000, which includes all engineering, fabrication, installation, and start-up and testing. COMMITTEE RECOMMENDATION This matter was not reviewed by a Board Committee. RECOMMENDED BOARD ACTION Staff recommends the Board receive the update and confirm by motion that the action proclaimed on August 4, 2022 either: 1. Continues to exist, and that the expenditures to address the emergency repairs to the Steam Driven Aeration Blower No. 2 are continuing as planned; or 2. Terminate the emergency situation in accordance with Public Contract Code Section 22050. Strategic Plan Tie-In GOAL TWO: Environmental Stewardship Strategy 1 -Achieve compliance in all regulations GOAL FIVE: Safety and Security Strategy 2- Protect personnel and assets from threats and emergencies GOAL SIX., Infrastructure Reliability Strategy 1 - Manage assets optimally October 6, 2022 Regular Board Meeting Agenda Packet- Page 317 of 317