Item 6.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: SEPTEMBER 15, 2022
SUBJECT: AUTHORIZE THE GENERAL MANAGER TOAMEND FOUR EXISTING
PROFESSIONAL ENGINEERING SERVICES AGREEMENTS UNDER THE
SOLIDS HANDLING FACILITY IMPROVEMENTS, PHASE 1A PROJECT
FOR ADDITIONALDESIGNAND BIDDI NGSERVICES WITH THE
FOLLOWING CONSULTANTS IN AMOUNTS NOT TO EXCEED:
• CDM SMITH, INC. FOR $550,000, INCREASING THE AGREEMENT TO
$1,400,000;
• GHD, INC. FOR $200,000, INCREASING THE AGREEMENT TO
$700,000;
• ARCSINE ENGINEERING, INC. FOR $200,000, INCREASING THE
AGREEMENT TO $800,000; AND
• HDR, INC. FOR $200,000, INCREASING THE AGREEMENT TO
$350,000
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
Roger S. Bailey
General Manager
ISSUE
Board of Directors (Board) authorization is required for the General Manager to execute an amendment to
an existing professional engineering services agreement above $200,000.
BACKGROUND
The Solids Handling Facility Improvements, Phase 1A, District Project 7348 (Phase 1A) is under design
and includes critical infrastructure replacement and the upgrade of the incinerator air pollution control
equipment to meet regulatory standards within the treatment plant's Solids Conditioning Building (SCB).
September 15, 2022 Regular Board Meeting Agenda Packet- Page 31 of 104
Page 2 of 4
In November 2021, the Board authorized professional engineering agreements for the selected consultant
team to verify and confirm the scope of work and to ultimately produce new bid documents, including
technical specifications and contract drawings for the Phase 1 A work.
The consultant team is overseen by District staff and consists of:
• CDM Smith, I nc. (CDM) is the lead consultant with overall responsibility for packaging the project for
bid. CDM is also responsible for mechanical, dewatering system, and project model.
• GHD, Inc. (GHD) is responsible for incinerators and air pollution control equipment.
• ArcSine Engineering, Inc. (ArcSine) is responsible for electrical improvements and overall control
system architecture.
• HDR, I nc. (HDR) is responsible for structural engineering (including seismic engineering for new
equipment) and architectural scope.
• Degenkolb Engineers, Inc. (Degenkolb)was also selected as part of the original design team and is
responsible for seismic strengthening of the SCB. The Board recently approved a revision to
Degenkolb's agreement to proceed with producing bid documents for seismic improvements to the
SCB.
• Ewing Construction Services (Ewing) is assisting staff with bid documents, equipment procurement
documents, cost estimating and construction schedule.
• Stan Chilson, an incinerator and air pollution control specialist, is assisting staff with review of GHD's
design and technical aspects of revisions to the wet scrubber procurement contract.
The consultant team was first tasked with confirming the scope of the Phase 1 A project and identifying
elements that require a redesign either to better clarify the work for bidders, produce more cost-effective
construction, or meet future District needs for the SCB facilities. The Phase 1 A scope includes the
following major items:
• Replace the sludge blend tank cover.
• Replace centrifuges and cake pumps.
• New cake piping to the incinerators.
• Incinerator improvements, including center shaft drive, blowers, burners, gas piping, and control
system from field devices and cabinets to the furnace control console.
• Replace and upgrade the incinerator air pollution control equipment (wet scrubbers).
• Electrical and control improvements to facilitate replacement of the new systems.
During scope confirmation, modifications to the original design were identified that address deficiencies
found in the original design or address constructability issues. The following are scope items that are new
from the previous design:
• A new electrical design.As Phase 1 A began, it was understood that the electrical design would be
starting from near beginning. This was primarily due to the decision to not build a new electrical room
and keep as much of the existing electrical infrastructure as possible.A new electrical design
provides the opportunity to provide more detail as this was identified by bidders as a major driver for
construction pricing exceeding expectations.
• Centrifuge polymer system is not being replaced resulting in additional controls work to integrate with
the new dewatering systems.
• GHD identified issues with the original wet scrubber design that, when addressed, will better meet
current objectives and prepare for potential future air pollution control equipment, such as:
• Raising the wet scrubber to eliminate pumping of scrubber drain water
• Access platform to be redesigned to better accommodate seismic loads from the scrubber,
accommodate the elevated scrubber, and take into account future air pollution control
equipment.
• Redesign the emergency bypass stack that will be utilized to route bypass exhaust to the new
September 15, 2022 Regular Board Meeting Agenda Packet- Page 32 of 104
Page 3 of 4
wet scrubber and improve the piping lining to handle anticipated high temperatures.
• A new concrete infill slab is needed on the 1 st floor of the SCB for the cake pump hydraulic power
units (HPU). There is insufficient space on the 2nd floor to accommodate the cake pumps, control
panels, and HPUs.
• Cake pump design pressures were reanalyzed for new operating parameters to eliminate the need to
replace all the cake piping in and outside the SCB.
• Lube pumps were removed from the scope.
• Reduced amount of overall piping to be replaced. New design will include replacing valves required
for dewatering system control.
• Incinerator console. Revised construction sequence to eliminate the temporary console and the new
console will be modified to eliminate hard wired physical devices.
• SCB seismic is under design with Degenkolb; however, CDM is coordinating and designing the yard
utility conflicts and work required to facilitate the new design within the building.
• HDR scope has increased due to the need for equipment anchoring and seismic, and to allow more
details for the bidders.
Bid Schedule
The new electrical renovation design has been the main driver for the project schedule. Significant effort
has been expended to investigate, document the existing electrical system, and coordinate with the new
discipline experts. Below are key milestones to bid Phase 1 A:
• Final Design by November 2022
• Bid Period of December 2022 - March 2023
• Bid Opening by April 2023 - May 2023
ALTERNATIVES/CONSIDERATIONS
An alternative would be to not approve revisions to the consultant agreements. This decision would stop
progress on the design to allow time to rescope the project to determine which items, if any, could proceed
to construction. This alternative is not recommended as the project scope has already been reduced to
address critical equipment replacement needs and meet regulatory requirements.
FINANCIAL IMPACTS
The current total expected consultant cost for CDM, GHD, ArcSine, and HDR is $3,250,000, of which up
to $350,000 is related to bidding services. The reasons for the increase in design costs ($800,000) are
cited above in the list of scope items that are being redesigned to satisfy deficiencies and improve
constructability of the project.
Electrical redesign accounts for much of the additional costs as the electrical scope essentially started
from the beginning. The consultants are making use of as much of the original design drawings as
possible, but most of the design and drawings have to be redone to account for reutilizing much of the
existing electrical infrastructure. This effort not only is being carried by ArcSine, but also CDM and GHD.
Agreements requiring Board authorization include those in the table below:
Consultant Original Amount Proposed New Amount
Amendments
CDM $850,000 $550,000 $1,400,000
GHD $500,000 $200,000 $700,000
ArcSine $600,000 $200,000 $800,000
HDR $150,000 $200,000 $350,000.
Total $2,100,000 $1,150,000 $3,250,000
September 15, 2022 Regular Board Meeting Agenda Packet- Page 33 of 104
Page 4 of 4
The current Engineers estimate for Phase 1A is $90 million. However, this estimate does not include the
recently authorized SCB seismic design that staff, along with Ewing, continues to refine this estimate as
the design progresses. A 95-percent estimate is scheduled to be completed by this October.
The total estimated budget for this project is $169,000,000, as detailed below:
Design - $21,000,000
Construction - $90,000,000 (Phase 1 A)
$20,000,000 (Phase 1 B)
Contingency- $16,000,000
Construction Management- $22,000,000
The combined total listed in the FY 2022-23 Budget and Capital Improvement Plan is approximately
$168,000,000. The project work has qualified for a State Revolving Fund (SRF) loan projected at
$173,100,000.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the August 31, 2022 meeting and
recommended approval.
RECOMMENDED BOARD ACTION
Authorize the General Manager to amend four existing professional engineering services agreements
under the Solids Handling Facility Improvements, Phase 1A project for additional design and bidding
services with the following consultants in amounts not to exceed:
• CDM Smith, Inc. for$550,000, increasing the agreement to $1,400,000;
• GHD, Inc. for$200,000, increasing the agreement to $700,000;
• ArcSine Engineering, Inc. for$200,000, increasing the agreement to $800,000; and
• HDR, Inc. for$200,000, increasing the agreement to $350,000.
Strategic Plan Tie-In
GOAL TWO: Environmental Stewardship
Strategy 1 -Achieve compliance in all regulations
GOAL SIX., Infrastructure Reliability
Strategy 1 - Manage assets optimally, Strategy 2- Execute long-term capital renewal and replacement program