HomeMy WebLinkAbout07. Authorize an amendment to an existing professional services agreement with Degenkolb Engineers, Inc. for DP 7348, increasing cost ceiling to $334,000 Page 1 of 3
Item 7.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: AUGUST 18, 2022
SUBJECT: AUTHORIZE THE GENERAL MANAGER TO AMEND AN EXISTING
PROFESSIONAL ENGINEERING SERVICES AGREEMENT IN AN AMOUNT
NOT TO EXCEED $284,000 WITH DEGENKOLB ENGINEERS, INC.,
INCREASING THE AGREEMENT FROM $50,000 TO $334,000 TO PROVIDE
SEISMIC DESIGN SERVICES FOR THE SOLIDS HANDLING FACILITY
IMPROVEMENTS, PHASE 1A, DISTRICT PROJECT 7348
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
L
Roger S. Bailey
General Manager
ISSUE
The Board of Directors'authorization is required for the General Manager to execute an amendment to an
existing professional engineering services agreement above $200,000.
BACKGROUND
The Solids Handling Facility Improvements, Phase 1 A, (Project) is under design and includes critical
infrastructure replacement and upgrade of the incinerator air pollution control equipment within the
treatment plant's Solids Conditioning Building (SCB)to meet regulatory standards. The original Solids
Handling Facility Improvements (Solids Project) included several project elements that were deferred or
under re-evaluation, such as a new ash handling facility, improved sludge blending tanks, major electrical
replacement, and seismic upgrades to bring the SCB and the existing incinerators in line with current
seismic performance standards. Staff has continued to evaluate seismic alternatives with Degenkolb
Engineers, Inc. (Degenkolb) in parallel with the Project.
Degenkolb was tasked to evaluate the SCB seismic improvements with the approach to minimize
disruption to process operations, increase safety for staff (especially at the existing stairwells), reduce
August 18, 2022 Regular Board Meeting Agenda Packet- Page 49 of 76
Page 2 of 3
impact to existing SCB systems, and move most of the construction work to the building exterior.As
seismic upgrades or safety levels are determined by Central San, another objective was to maximize
seismic performance without taking the SCB or incinerators and solids processes fully offline. Seismic
improvements for the incinerators, such as the base isolators, have been removed from the Project.
However, the new proposed design will significantly lower the amount of displacement from 24 inches to 6-
inches (depending on incinerator elevation, can also range from 3 to 9-inches) during a major earthquake.
Staff evaluated several ideas with Degenkolb since the work within the SCB has been minimized. I n the
end, Degenkolb presented a concept that meets Central San's stated objectives and substantially
improves the expected seismic performance of the SCB, which includes:
• Exterior buttresses at North-East and South-West corners;
• Strengthen beams and beam-column connections at buttresses;
• New brace at the North-West corner of SCB;
• Strengthen existing braces; and
• A design that can be used with future modifications to meet the current design criteria for critical
facilities.
Degenkolb has extensive experience with seismic engineering in general and specifically with the SCB.
Degenkolb designed the first seismic improvements for the SCB in the 1980s. The current Degenkolb
team conducted the assessment of the SCB seismic performance in 2009 and was selected in
December 2016 as part of the design team for the Solids Project.At the November 18, 2021 Board
Meeting, the Board was informed that Degenkolb would continue to provide seismic engineering services
as part of the Project and an agreement within the General Manager's authority was executed at a cost
ceiling of$50,000.
Staff has negotiated a scope and fee with Degenkolb to complete bid documents for the buttresses and
other seismic upgrades, including bid services. The bid documents for the seismic work will be included
with the Project as an alternate bid item. The cost for the additional services is estimated at$284,000.
ALTERNATIVES/CONSIDERATIONS
An alternative would be to not make any seismic improvements to the SCB. Staff considered this
alternative as part of the Solids Project rescoping effort; however, making the proposed seismic
improvements to the SCB resolves many of the seismic performance deficiencies at a reasonable cost.
These improvements will protect staff working in the SCB and the critical process equipment.
A consideration known and evident to staff is that the SCB contains more than solids process equipment, it
also includes the main components of the steam system or heat recovery systems and power generation
for the treatment plant. These systems and the incinerators have significant remaining life (20 plus years)
when properly maintained. Therefore, the building is needed for the near term and likely in the future. The
proposed design allows for a staged or phase improvement plan that in time when other systems are in
place, the SCB may be improved to obtain the highest level of seismic performance.
FINANCIAL IMPACTS
Degenkolb's services as described above is $284,000. The original agreement amount to evaluate
alternatives was $50,000; thus, the new cost ceiling for the agreement will be $334,000. There is adequate
remaining budget in the Project to fund the new seismic design.
The preliminary construction estimate for the seismic upgrades is between $15 million and $20 million. I n
comparison, the Solids Project bids received last year included seismic upgrades at a cost from $40
August 18, 2022 Regular Board Meeting Agenda Packet- Page 50 of 76
Page 3 of 3
million to $60 million and roughly$20 million or more in solids hauling and disposal due to the seismic
work. The proposed Project does not include solids hauling or disposal as the seismic work will be mainly
completed from outside the SCB.
Budget for seismic upgrades to the SCB are included in the Ten-Year Capital I mprovement Plan— Solids
Handling Facility Improvements, Phase 1 B Seismic. $32,950,000 has been budgeted starting in Fiscal
Year 2023-24.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the August 3, 2022 meeting and
recommended approval.
RECOMMENDED BOARD ACTION
Authorize the General Manager to amend an existing professional engineering services agreement in an
amount not to exceed $284,000 with Degenkolb Engineers, I nc., increasing the agreement from $50,000
to $334,000 to provide seismic design services for the Solids Handling Facility I mprovements, Phase 1 A,
District Project 7348.
Strategic Plan re-In
GOAL TWO: Environmental Stewardship
Strategy 1 -Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 2- Protect personnel and assets from threats and emergencies
GOAL SIX: Infrastructure Reliability
Strategy 2- Execute long-term capital renewal and replacement program
August 18, 2022 Regular Board Meeting Agenda Packet- Page 51 of 76