CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: JULY 21, 2022
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $1,140,000
TO ALEX KUSHNER GENERAL, INC., THE LOWEST RESPONSIVE AND
RESPONSIBLE BIDDER, FOR THE LABORATORY ROOF AND SEISMIC
UPGRADES, DISTRICT PROJECT 100008; AND FIND THE PROJECT IS
EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL QUALITYACT
SUBMITTED BY: INITIATING DEPARTMENT:
MICHAEL CUNNINGHAM, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: NATHAN HODGES, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is also required for the General Manager to execute the Contract Documents subject to
submittal requirements.
BACKGROUND
The Environmental Laboratory Building (Lab) is located within the Martinez campus and is a critical and
specialty facility used daily by staff for permitting and regulatory compliance, and process control. I n recent
years the roof condition has steadily degraded with several leaks, the most significant of which were in the
testing areas of the Lab.
July 21, 2022 Regular Board Meeting Agenda Packet- Page 49 of 113 Amended Agenda
Page 2 of 6
The Laboratory Roof and Seismic Upgrades, District Project 100008 (Project), will replace the roofing
and perform minor structural modifications to upgrade the seismic criteria from the 1994 building code to
current design standards. See Attachment 1 for the project location. To accomplish the seismic work in a
cost efficient and safe manner, the modifications are designed to be constructed to minimize disruption to
sensitive and specialized testing areas and equipment. The majority of structural work will be performed
above the ceiling, or from the exterior, and from the roof. The Lab is not expected to be closed during the
retrofit and restoration work. In addition, the building HVAC will be modified to allowfor better maintenance
access and less disruption to the office area.
Central San, Complete Project Solutions (CPS), and Calpo Hom and Dong Architects, Inc. (CH&D)
prepared the plans and specifications for the Project. The Engineer's estimate for construction is
$900,000. This Project was advertised on June 2 and 9, 2022. Two bids were received and publicly
opened on June 27, 2022, which were $1,140,000 and $1,475,000. The Capital Projects Division
conducted a technical and commercial review of the bids and determined that Alex Kushner General,
I nc. (AK General) is the lowest responsive and responsible bidder. A summary of bids received is shown
in Attachment 2.
AK General is a contractor based out of San Francisco and meets the qualifications and experience
requirements for the Project. The bid price provided byAK General is $240,000 (27%) above the
Engineer's estimate. Staff met with AK General and confirmed that the cost difference from the estimate is
due to the roofing scope of work. The cost was nearly doubled than anticipated due to the difficult roof
access, multiple equipment penetrations, large roof equipment on platforms, and an increased cost of the
membrane materials.
Central San will administer the construction contract and provide construction management, administration,
and submittal review. CPS and CH&D will provide as-needed technical assistance. The general inspection
and specialty inspection will be provided under as-needed services agreements in the Capital Program.
California Environmental Quality Act (CEQA)
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15302 because it involves replacement of existing facilities at substantially the same locations and with the
same purpose and level of activity as the facilities being replaced. Approval of this Project will establish the
Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
One alternative is to delay or postpone the Project. This is not recommended as the Lab roof is beyond its
useful life and in need of replacement before next winter.
Another alternative would be to reject all bids or revise the Project scope and rebid. This is not
recommended as seismic upgrades have been designed to be completed in parallel to roof replacement;
completing seismic upgrades at a later time would require removing and repairing a section of the new
roof.
FINANCIAL IMPACTS
The total estimated project budget is $1,577,000, which includes planning, design, bid price, contingency,
construction management, and consultant costs as detailed in Attachment 3.
This Project is included in the Fiscal Year 2022-23 District Budget, shown on page 247, with a total budget
of$1,450,000. An additional $127,000 is needed to fund the Project. Staff will transfer the needed amount
after Board award, which is under the General Manager's delegation of authority for the Capital
Improvement Program.
July 21, 2022 Regular Board Meeting Agenda Packet- Page 50 of 113 Amended Agenda
Page 3 of 6
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at its meeting on July 6, 2022 and
recommended approval.
RECOMMENDED BOARD ACTION
Staff recommends the following Board action:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of$1,140,000 to Alex Kushner General, I nc., the lowest
responsive and responsible bidder, for the construction of the Laboratory Roof and Seismic
Upgrades, District Project 100008; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements.
Strategic Plan Tie-In
GOAL TWO:Environmental Stewardship
Strategy 1 -Achieve compliance in all regulations
GOAL FIVE: Safety and Security
Strategy 2- Protect personnel and assets from threats and emergencies
GOAL SIX.Infrastructure Reliability
Strategy 2- Execute long-term capital renewal and replacement program
ATTACHMENTS:
1. Project Location Maps
2. Summary of Bids
3. Post Bid/P reconstruction Estimate
July 21, 2022 Regular Board Meeting Agenda Packet- Page 51 of 113 Amended Agenda
Page 4 of 6
UJ zoo 400 Basin A South \`�\
\ FEET MONOMER \
ry
r) \•
LL \
LL
O
_ —
i SOLIDS
NDITIONI
i
BUILDING
i CONSTRUCTION
i STAGING AREA
i I
8 0=
i I Aeration CLA IERS
i Tanks (SOUT UAD)
0]"� �, ❑ _PUMP AND BLOWER
0
PROJECT AREA BUILDING
LABORATORY BUILDING --
% POD HOB
MAIN GATE O
// IMHOFF PLACE
o �
of /�_� •�
Central Contra Costa Attachment
Y
Sanitary District Laboratory Roof and Seismic Upgrades
N District Project 100008 1
N
0
oard MeetinLocation Ma
g Agenda Packet- Page 52 of 11? Amended Agenda
Page 5 of 6
ATTACHMENT 2
LABORATORY ROOF AND SEISMIC UPGRADES
DISTRICT PROJECT 100008
SUMMARY OF BIDS
PROJECT NO.: 100008 NO. OF ADDENDA: 1 DATE/TIME: JUNE 27, 2022/3:00 PM
PROJECT NAME: LABORATORY ROOF AND SEISMIC UPGRADES
PROJECT MANAGER: MICHAEL CUNNINGHAM
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CA
ENGINEER'S ESTIMATE: $900,000
NO. BIDDER BID PRICE
1 Alex Kushner General, Inc. $1,140,000
San Francisco, California
2 CWS Construction Group, Inc. $1,475,000
Novato, California
BIDS OPENED BY: /s/Amelia Berumen DATE: June 27, 2022
July 21, 2022 Regular Board Meeting Agenda Packet- Page 53 of 113 Amended Agenda
Page 6 of 6
ATTACHMENT 3
LABORATORY ROOF AND SEISMIC UPGRADES
DISTRICT PROJECT 100008
POST-BID/PRECONSTRUCTION ESTIMATE
% of
No. Item Description Amounts Construction
Cost
1. CONSTRUCTION
a. Construction Contract $1,140,000
b. Contingency at 10% $114,000
c. Permits(Fire District), includes any modifications $30,000
SUBTOTAL-CONSTRUCTION COST $1,284,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
-Construction Management $70,000
b. Consultants
-Consultants $40,000
- Inspection (General and Specialty) $90,000
SUBTOTAL-CONSTRUCTION MANAGEMENT $200,000 16%
3. PREBID EXPENDITURES
a. District Engineering $10,000
b. Consultant Fees $83,000
SUBTOTAL- PREBID EXPENDITURES $93,000 7%
4. TOTAL PROJECT ESTIMATED COST $1,577,000