HomeMy WebLinkAbout12.a.Att.3-Capital Program Presentation Page 352 of 358 Attachment 3 I�u PROPOSED FISCAL YEAR 2022-23 CAPITAL IMPROVEMENT BUDGET AND TEN-YEAR CAPITAL IMPROVEMENT PLAN Board Meeting May 26, 2022 Jean Marc Petit, P.E. Director of Engineering and Technical Services Edgar J. Lopez, P.E. Capital Projects Division Manager FISCAL YEAR (FY) 2021-22 MAJOR ACCOMPLISHMENTS • Regulatory and Safety • Reduced the Solids Handling Facility Improvements (Solids Project);currently in design for Phase(Ph.) 1A with new air pollution control equipment and other needed improvements. °pL • Completed the Treatment Plant Safety Enhancements, Ph.5 that added an emergency exit to the Solids Conditioning Building for employee safety. • Sewer Infrastructure Replacement • Replaced or rehabilitated up to approximately 7 miles(mi.) of public sewers in the service area. • Treatment Plant Infrastructure Replacement • Nearing completion of the Pump Station Upgrades, Ph. 1 in Orinda and Moraga. • Continuing construction of the Filter Plant and Clearwell Improvements, Ph. 1Afor reliable recycled water storage and electrical improvements. • Continuing construction of the Influent Pump Electrical Improvements and Electric Blower Improvements. ` z CENTRAL SAN May 26, 2022 Special Board Meeting Agenda Packet- Page 459 of 532 1 Page 353 of 358 PROPOSED FY 2022-23 CAPITAL IMPROVEMENT BUDGET (CIB) Budget-to-Date2022 Program (2) (3) Project Budgets Ten Year CIP Collection System $74,864,181 $36,850,000 $130,941,000 $242,655,181 $324,141,000 Treatment Plant 96,569,332 39,981,000 414,000,000 550,550,332 724,290,000 General Improvements 19,896,459 3,795,000 5,175,000 28,866,459 23,480,000 Recycled Water 32,854,000 8,715,000 34,884,000 76,453,000 44,777,000 CIB Contingency - 1,635,000 17,350,000 18,985,000 18,985,000 Totals: $224,183,972 $90,976,000 $602,350,000 $917,509,972 $1,135,673,000 The Budget-to-Date(1)column includes budget already spent for on-going projects. Any remaining budget,except for closed projects,will carry-forward to FY 2022-23. 3 MAJOR PROJECTS SUMMARY RECOMMENDED FOR NEXT FISCAL YEAR TREATMENT PLANT IN • Solids Project,Ph.1A(Construction) COLLECTION SYSTEM • Electric Blower Improvements(Construction) Sewer Renovation Projects: • Steam Renovations,Ph.1(Design/Construction) Design: • UV Disinfection Replacement&Hydraulic Improvements Sewer Renovation,Ph.2 (Design) Large Diameter Renovation • Aeration Basins Diffuser Replacement and Seismic Upgrades —Danville (Construction) Construction: • Walnut Creek,Ph.15-16 GENERAL IMPROVEMENTS North Orinda,Ph.8 • Technology Strategic Plan South Orinda,Ph.9 • New Permit Counter Software and Information Technology(IT) Lafayette,Ph.15 Development(Construction) Danville,Ph.4 • Vehicle Replacement and Equipment Acquisition(Purchase) Martinez,Ph.7 Pump Stations(Construction): RECYCLED WATER • San Ramon Electrical Filter Plant and Clearwell Improvements,Ph.1A(Construction) Upgrades • Filter Plant and Clearwell Improvements,Ph.1B(Electrical Ph.2:Martinez/ Design) Fairview/Maltby • Distribution System Renovations Program(Planning) 4 CENTRAL SAN May 26, 2022 Special Board Meeting Agenda Packet- Page 460 of 532 2 Page 354 of 358 NEW MAJOR PROJECTS IN FY 2022-23 BY PROGRAM Collection System: • Collection System Sewer Renovation, Ph. 2 ($90 M Total), 5-year project Treatment Plant: • Secondary Clarifier Improvements ($10.0 M), renovation of all clarifiers in next 5 years • Electrical Infrastructure Sub 90 ($23.6 M), first major step in electrical replacement at the treatment plant M=million ��5 CIENTRALSAN FY 2022-23 COLLECTION SYSTEM PROGRAM MAJOR Focus Collection System Sewer Renovation, Ph. 2: • Main sewers, less than 12" diameter, represent 87% or 1,337 of the 1,540 mi. collection system. Of which, approx. 228 mi. are 6" diameter sewers or less. • Ph. 1, completed in 5 years, renovated 32.2 mi. of small diameter sewers (mostly 6" clay pipes) or 6.5 mi. per year. • Ph. 2 plans to increase the yearly replacement to reach up to 7.5 mi. per year and continue focusing on small diameter sewers in easements, near creeks, and to be coordinated with local jurisdictions and other projects in the service area. Pump Station Renovation: • Construction of San Ramon Electrical Upgrades and Pump Station Upgrades, Ph. 2 for Martinez, Fairview, and Maltby. 6 CENTRAL SAN May 26, 2022 Special Board Meeting Agenda Packet- Page 461 of 532 3 Page 355 of 358 FY 2022-23 TREATMENT PLANT PROGRAM MAJOR Focus Regulatory and Safety: • Wet scrubber replacement for the Solids Project, Ph. 1A • Safety Enhancement Program �= - Rehabilitation and Replacement: • Finish construction of Electric Blower Improvements and Piping Renovation, Ph. 10 • Solids Project, Ph. 1A-award and start construction • Steam Renovations, Ph. 1 -award and start construction • UV Disinfection Replacement-complete design and review funding options • Aeration Basins Diffuser Replacement and Seismic Upgrades- award and start construction FY 2022-23 GENERAL IMPROVEMENTS PROGRAM MAJOR PROJECTS FOCUS IT Development: • Community Development System Replacement • IT Infrastructure Improvements • Technology Strategic Plan AL 101b; 4 Building Improvements: 01,ERP • Security Improvements � ` Vehicle Replacement Program 8 CENTRAL SANMay 26, 2022 Special Board Meeting Agenda Packet- Page 462 of 532 4 Page 356 of 358 FY 2022-23 RECYCLED WATER PROGRAM MAJOR Focus Rehabilitation and Replacement: • Filter Plant and Clearwell Improvements, Ph. 1A(Construction) • Filter Plant and Clearwell Improvements, Ph. 1 B (Electrical Rehab) Planning: • Zone 1 Recycled Water System • Recycled Water Distribution System Renovations Program • Water Exchange I l do— CENTRALSAN CIB MODIFICATIONS CHANGED PROJECT ESTIMATES The following total estimated project budgets were modified: Projects FY 2021-22 FY 2022-23 Pump Station Upgrades, Ph.2, District Project DP 8457 $38,950,000 $47,950,000 UV Disinfection Replacement and Hydraulic 35,280,000 68,480,000 Improvements, DP 100012 Aeration Basins Diffuser Replacement and 25,800,000 61,300,000 Seismic Upgrades, DP 100019 Steam Renovations,Ph. 1, DP 100032 0 17,500,000 Steam and Aeration Blower Systems 35,350,000 5,850,000 Renovations, DP 7349 Solids Handling Facility Improvements, 183,984,000 135,018,687 Phase 1A, DP 7348' Totals $319,364,000 $336,098,687 `DP 7348 has been revised and renamed as Phase 1A 10 CENTRAL SAN May 26, 2022 Special Board Meeting Agenda Packet- Page 463 of 532 5 Page 357 of 358 PROPOSED TEN-YEAR CAPITAL IMPROVEMENT PLAN (CIP) FY 2022-31 : $17135 M Program Collection System $ 324,141,000 Treatment Plant 724,290,000 General Improvements 23,480,000 Recycled Water 44,777,000 Subtotal $ 1,116,688,000 Contingency 18,985,000 Total with Contingency $ 1,135,673,000 Chanqes included in CIP: • Solids Project, Ph. 2 has been fully included at$156.2 M • Nutrient Removal has been partially included at$55 M • Solids Project, Ph. 2B(seismic only)separated, $33 M • Future projects total costs increased 3% 1 11 CENTRALSAN CHANGES SINCE DRAFT BUDGET ISSUED TO THE BOARD ON MAY 5 Project Budgets based on Regulatory Drivers: • POB Electric Vehicles Charging Station total estimated budget on page 270 revised to $1,290,000. Scope has increased to include CSO and pool vehicles at the Martinez Campus. Schedule to match the State order and proposed California Air Regulatory Board regulations for fleets starting 2024. Funding the Changes: • Program budgets shall be revised based on recent project awards and for charging stations. Funding will come from contingency budget; therefore, no overall changes to the total CIB/CIP overall budgets. POB=Plant Operations Building;CSO=Collection System Operations J 12 CENTRAL SAN May 26, 2022 Special Board Meeting Agenda Packet- Page 464 of 532 6 Page 358 of 358 QUESTIONS 13 CENTRALSAN May 26, 2022 Special Board Meeting Agenda Packet- Page 465 of 532