HomeMy WebLinkAbout06. Award a construction contract to Velluntini Corporation, dba Royal Electric Company, for the San Ramon Electrial Upgrades, DP 100017 Page 1 of 7
Item 6.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: MAY 26, 2022
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF
$1,333,333 TO VELLUTINI CORPORATION, DBA ROYAL ELECTRIC
COMPANY, THE LOWEST RESPONSIVE AND RESPONSIBLE BIDDER
FOR THE SAN RAMON ELECTRICAL UPGRADES, DISTRICT PROJECT
100017; AND FIND THAT THE PROJECT IS EXEMPT FROM THE
CALIFORNIA ENVIRONMENTAL QUALITYACT
SUBMITTED BY: INITIATING DEPARTMENT:
KEITH GELLERMAN, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is also required for the General Manager to execute the Contract Documents subject to
submittal requirements.
BACKGROUND
Staff identified several electrical deficiencies at the San Ramon Pumping Station. These deficiencies are
with critical electrical equipment used for the daily operation of powering wastewater pumps or to power
the entire pumping station during PG&E power shut-off conditions. The electrical equipment scheduled for
replacement under the San Ramon Electrical Upgrades, District Project 100017 (Project) includes several
variable frequency drives (VFDs), the automatic transfer switch for standby emergency generator power,
May 26, 2022 Special Board Meeting Agenda Packet- Page 38 of 532
Page 2 of 7
and the main electric service entrance (service entrance)for the pumping station. The VF Ds and automatic
transfer switch have been in constant need of repair in recent years and have shown signs of being
unreliable during routine maintenance testing. In addition, due to the existing electrical configuration of the
pumping station, the ability to fully test or perform maintenance on the automatic transfer switch is limited
and difficult. Improving the service entrance during the replacement of the automatic transfer switch is
highly recommended and provides for the optimal opportunity to upgrade the system. The improvements
will allow for additional electrical and arc-flash safety. Both the service entrance and automatic transfer
switch are the most important pieces of electrical equipment at the pumping station and will require support
from PG&E during the Project. The new service entrance will be installed in a small outdoor enclosure
adjacent to the building.
Central San staff and ArcSine Engineering (ArcSine) prepared the plans and specifications for the
Project. The Engineer's estimate for construction was $1.2 million. This Project was advertised on March
31 and April 7, 2022. Six sealed bids ranging from $1,333,333 to $1,790,300 were received and publicly
opened on April 27, 2022. The Capital Projects Division conducted a technical and commercial review of
the bids and determined that Vellutini Corporation, dba Royal Electric Company(Royal Electric) is the
lowest responsive and responsible bidder. This determination came after staff reviewed the bids for
completeness and verified all references. Royal Electric is a new contractor to Central San; however, they
do have similar experience in wastewater and projects with similar equipment.A summary of bids received
is shown in Attachment 2.
All bids were over the Engineer's estimate. After evaluating the bid costs received and information
provided by some of the bidders, the increase is due to equipment costs. The type of equipment specified
in this Project has increased more than anticipated in the last several months due to the limited supply and
product availability. Based on this information, the Engineer's estimate would have increased to a total of
$1.5 million.
Central San will administer the construction contract and provide construction management, resident
engineering, administration, and submittal review with support from ArcSine. Construction inspection will be
performed by staff and specialty inspectors.
Staff plans on using Carollo Engineers, I nc. (Carollo)for construction management services for the
Project; however, the agreement will be presented at a future Board meeting. Carollo was selected as the
top scoring firm to support Central San for the construction at several pumping stations, including this
Project and the Pump Station Upgrades, Phase 2. The selection was based on a formal solicitation,
Request for Proposal process, in which several qualified and experienced firms participated. Staff will
provide all construction management services on this Project until the Pump Station Upgrades, Phase 2
starts construction.
California Environmental Quality Act(CEQA)
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15301 because it involves minor alterations to existing public facilities involving no expansion of use and
Section 15302, because it involves replacement of existing facilities at substantially the same locations
and with the same purpose and level of activity as the facilities being replaced. Approval of this Project will
establish the Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Delaying or postponing this work is not recommended since the equipment is essential for the pumping
station to operate and respond during emergencies or power outages.Another alternative would be to
reject all bids, which is also not recommended.
May 26, 2022 Special Board Meeting Agenda Packet- Page 39 of 532
Page 3 of 7
FINANCIAL IMPACTS
The total estimated project cost is $1,913,000, including design, bid price, contingency, construction
management, and consultant costs as detailed in Attachment 3. The Project is listed on page 224 of the
Fiscal Year(FY) 2021-22 District Budget at a total cost of$1.2 million. The cost increase to the Project
was anticipated and is reflected in the upcoming FY 2022-23 District Budget. No additional budget is
required this fiscal year.
COMMUNITY OUTREACH
Although the project elements are critical, the construction impacts to the nearby community or
neighborhood is very minor as a majority of the construction work is within the pumping station building and
on Central San property. However, staff is aware of past community outreach and concerns from nearby
residents during larger renovation efforts; thus plans to hold an outreach meeting to educate nearby
residents of the importance of the Project and to present the timeline and what to expect during
construction. Also, staff is coordinating with the City of San Ramon and will notify all nearby residents in the
neighborhood as previously done for smaller maintenance type projects that have been performed since
the last major renovation completed in 2004.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at its meeting on May 4, 2022 and
recommended approval.
RECOMMENDED BOARD ACTION
Staff recommends the following Board action:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of $1,333,333 to Vellutini Corporation, dba Royal
Electric Company, the lowest responsive and responsible bidder for the construction of the San
Ramon Electrical Upgrades, District Project 100017; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements.
Strategic Plan re-In
GOAL ONE: Customer and Community
Strategy 2—Maintain a positive reputation
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE: Infrastructure Reliability
Strategy 2—Execute long-term capital renewal and replacement program, Strategy 3—Protect personnel and assets
from threats and emergencies
GOAL SEVEN:Agility andAdaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
May 26, 2022 Special Board Meeting Agenda Packet- Page 40 of 532
Page 4 of 7
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post Bid/P reconstruction Estimate
May 26, 2022 Special Board Meeting Agenda Packet- Page 41 of 532
Page 5 of 7
San Ramon Electrical Upgrades
• District Project 100017 Map Date:4/20/2022
C<Ov�d
Ga y��R
Martinez
Concord
Pleasant Hill
IE: Walnut Creek
Lafayette
Moraga �--�
Danville
Detail Area
N° rid tsMam n
Gar`1°
O
Oe-
09
Lc°m
X
Mopt(9t,
eo,0
i
O
5
t
�nse�ada0
\ `Oc
�sme'
P�
Q Project Area
Note: 0 2,000 Map Displayed in North American Datum of 1983 Attachment
Central San data as of April,2020. Feet California State Plane,Zone III RIPS 0403,US Feet 1
May 26, 2022 Special Board Meeting Agenda Packet- Page 42 of 532
Page 6 of 7
ATTACHMENT 2
SAN RAMON ELECTRICAL UPGRADES
DISTRICT PROJECT 100017
SUMMARY OF BIDS
PROJECT NO.: 100017 NO. OF ADDENDA: 1 DATE/TIME: APRIL 27, 2022/2:00 PM
PROJECT NAME: SAN RAMON ELECTRICAL UPGRADES
PROJECT MANAGER: KEITH GELLERMAN
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ CA
ENGINEER'S ESTIMATE: $1,200,000
NO. BIDDER BID PRICE
1 Vellutini Corporation dba Royal Electric Company $1,333,333
Sacramento, CA 95828
2 Telstar Instruments $1,493,559
Concord, CA 94520
3 D.W. Nicholson Corporation $1,563,754
Hayward, CA 94540
4 Blocka Construction, Inc. $1,646,500
Pleasanton, CA 94566
5 Contra Costa Electric $1,668,545
Martinez, CA 94553
6 Auburn Constructors LLC $1,790,300
Sacramento, CA 95834
BIDS OPENED BY: /s/ Amelia Berumen DATE: April 27, 2022
May 26, 2022 Special Board Meeting Agenda Packet- Page 43 of 532
Page 7 of 7
ATTACHMENT 3
SAN RAMON ELECTRICAL UPGRADES
DISTRICT PROJECT 100017
POST-BID/PRECONSTRUCTION ESTIMATE
% of
Construction
No. Item Description Amounts Cost
1. CONSTRUCTION
a. Construction Contract $1,333,333
b. 15% Contingency $199,667
SUBTOTAL - CONSTRUCTION COST $1,533,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management (Engineering) $60,000
- Operations $10,000
b. Consultants
ArcSine (ESDC) $70,000
Carollo (CM Services) $130,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $270,000 18%
3. PREBID EXPENDITURES
a. Engineering (Design, Drafting) $110,000
SUBTOTAL - PREBID EXPENDITURES $110,000 7%
4. TOTAL ESTIMATED PROJECT COST 1 $1,913,000
May 26, 2022 Special Board Meeting Agenda Packet- Page 44 of 532