HomeMy WebLinkAbout04.a. Review draft Position Paper to award a construction contract in the amount of $444,000 to Power Engineering Construction Company, the lowest responsive and responsible bidder for the Outfall Monitoring Improvements, District Project 100018 Page 1 of 7
Item 4.a.
CENTRAL SAN BOARD OF DIRECTORS
. , , .
POSITION PAPER
. ,
DRAFT
MEETING DATE: MAY 4, 2022
SUBJECT: REVI EW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $444,000 TO POWER ENGINEERING
CONSTRUCTION COMPANY, THE LOWEST RESPONSIVE AND
RESPONSIBLE BIDDER FOR THE OUTFALL MONITORING
IMPROVEMENTS, DISTRICT PROJECT 100018
SUBMITTED BY: INITIATING DEPARTMENT:
MARK WENSLAWSKI, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: NATHAN HODGES, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
Authorization is also required for the General Manager to execute the Contract Documents subject to
submittal requirements.
BACKGROUND
The Central Contra Costa Sanitary District (Central San) operates a 3.5 mile, 72-inch reinforced concrete
outfall pipeline (outfall). The outfall, constructed in 1958, runs primarily underground for nearly 19,000 feet
and a submarine section of about 1,700 feet in length. Above the shoreline portion of the outfall, an
unvegetated, tidal mudflat extends approximately 1,000 feet from the shore and into Suisun Bay. Central
San also maintains a variety of infrastructure associated with the outfall, such as manholes, access risers,
air relief valves, cathodic protection systems, inclinometers, and leveling monuments.
In 2020, the Outfall Improvements, Phase 7 Project (Outfall Phase 7) completed a full internal inspection
and survey of the pipeline as well as necessary repairs and improvements. Staff hired a specialty
consultant to evaluate the condition of the existing inclinometers and leveling monuments on the outfall.
The consultant's report recommended maintenance and repairs, as well as identified more than the
anticipated scope of work than previous Outfall Projects. The additional or unanticipated work included
May 4, 2022 EOPS Regular Committee Meeting Agenda Packet- Page 4 of 34
Page 2 of 7
replacement of several inclinometers and leveling monuments. Some of the repairs were completed;
however, other repairs or new inclinometers could not be performed during the timeline of the Outfall
Phase 7 construction period.
The Outfall Monitoring Improvements, District Project 100018 (Project), will replace and construct new
inclinometers and leveling monuments and perform non-routine maintenance on the systems. Staff has
coordinated with various agencies to obtain necessary approval and/or permits from the San Francisco
Bay Regional Water Quality Control Board, United States Army Corps of Engineers, United States Fish
and Wildlife Service, and California Department of Fish and Wildlife.
The Engineer's estimate for the Project is $390,000. This Project was advertised on March 21 and 28,
2022. One bid was received and publicly opened on April 14, 2022. The Capital Projects Division
conducted a technical and commercial review of the bid and determined that Power Engineering
Construction Company is a responsive and responsible bidder, with a bid amount of$444,000 as shown in
Attachment 2.Although the bid received is roughly$50,000 or 14 percent over the Engineer's estimate,
staff is recommending to award based on the following analysis of the bid and process:
• The scope of work under the Project is specialized and there was very limited interest by prospective
bidders. Staff contacted several contractors during the bid period and does not believe that
rebidding would bring additional interest.
• The costs for the new inclinometers were higher than anticipated and represent the difference
between the bid and Engineer's estimate.
• Rebidding will likely not save costs considering staff would have to spend significant time in bidding
again and extending the permits for the Project.
• Power Engineering Construction Company is uniquely familiar with the outfall infrastructure and has
successfully completed two of the Outfall Project Phases, thus has the expertise and knowledge to
perform the required work.
California Environmental Quality Act(CEQA)
At the October 21, 2021 meeting, the Board independently found this project to be exempt from the California
Environment Quality Act under CEQA Guidelines Section 15301. A Notice of Exemption was filed with the
Contra Costa County Clerk on October 21, 2021, as this was required before award of the construction contract
due to permitting.
ALTERNATIVES/CONSIDERATIONS
Proper maintenance of the outfall is required by the National Pollutant Discharge Elimination System
permit, which includes the inclinometers. Staff has reviewed whether to continue use of the inclinometers
as a tool for monitoring settlement and recommends continuing based on the historic settling of clay soils
or bay mud in and around the outfall alignment.
FINANCIAL IMPACTS
The total estimated cost for the Project is $789,000, which includes planning, design, construction contract,
contingency, and construction management costs as shown in Attachment 3. The Outfall Monitoring
Improvements Project is included in the FY 2021-22 District Budget on page 257 with a total budget of
$610,000.Atransfer of$179,000 from the FY 2021-22 Capital Improvement Budget contingency account is
needed to fund the Project. The transfer amount is within the General Manager's delegated authority and will be
done if the Board awards the contract.
May 4, 2022 EOPS Regular Committee Meeting Agenda Packet- Page 5 of 34
Page 3 of 7
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee has reviewed this subject at its meeting on May 4, 2022 and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the Board award a construction contract in the amount of$444,000 to Power Engineering
Construction Company, the lowest responsive and responsible bidder for the Outfall Monitoring Improvements,
District Project 100018.
Strategic Plan re-In
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL FIVE: Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 3—Protect personnel and assets from
threats and emergencies
GOAL SIX: Innovation and Optimization
Strategy 1—Implement the Central San Smart Initiative
GOAL SEVEN:Agility andAdaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
ATTACHMENTS:
1. Project Location Maps
2. Summary of Bid
3. Post-Bid/P reconstruction Estimate
May 4, 2022 EOPS Regular Committee Meeting Agenda Packet- Page 6 of 34
Page 4 of 7
N
o zoo aoo
FEET `
`ttect
s A
b y f-D
1 ppNE 111 �/
1 'MNpFF
r � o
D I li /i
k
•:
.� Guth 9 O
f�
o HHWC o I Gi t SoC�J�`�g
4 `
o
�C
Warehou e m O
HOB
Annex
o
2 CENTRALSAN
OUTFALL MONITORING Attachment
IMPROVEMENTS PROJECT
la
District Project 100018
ro'e t oc do
Page 5 of 7
SUBMARINE WEIR STRUCTURE
N
PORTION OF
OUTFALL
0 1000 2000
Moog
` FEET
rrr
rrrPp _
rrrr _ O
r r ANT
WATERER � R
s8 �
o
MANHOLE RISER (TYP)
s-
l
ti
o �
0
o f
11
0
a �
E -
TREATMENT PLANT iMNO
= PROPERTY '
0
LEGEND O
• MANHOLE OR ACCESS HATCH
2 CENTRAL SAN OUTFALL MONITORING Attachment
IMPROVEMENTS PROJECT lb
' District Project 100018
ro'e t l2c2tloq
Page 6 of 7
ATTACHMENT 2
OUTFALL MONITORING IMPROVEMENTS
DISTRICT PROJECT 100018
SUMMARY OF BID
PROJECT NO.: 100018 NO. OF ADDENDA: 0 DATE/TIME: APRIL 14, 2022/2:00 PM
PROJECT NAME: OUFALL MONITORING IMPROVEMENTS
PROJECT MANAGER: MARK WENSLAWSKI
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $390,000
NO. BIDDER BID
PRICE
1 Power Engineering Construction Company $444,000
Alameda, CA 94501
BIDS OPENED BY /s/ Katie Young DATE: April 14, 2022
May 4, 2022 EOPS Regular Committee Meeting Agenda Packet- Page 9 of 34
Page 7 of 7
ATTACHMENT 3
OUTFALL MONITORING IMPROVEMENTS
DISTRICT PROJECT 100018
POST-BID/PRECONSTRUCTION ESTIMATE
%Of
Construction
No. Item Description Amounts Cost
1 CONSTRUCTION
a. Construction Contract $444,000
b. Contingency at 15% $60,000
c. Permits $20,000
SUBTOTAL-CONSTRUCTION COST $524,000 100%
2 CONSTRUCTION MANAGEMENT
a. District Forces
-Construction Management/Regulatory $53,000
b. Consultants
-AECOM Support Services $30,000
-Zentner $40,000
SUBTOTAL-CONSTRUCTION MANAGEMENT $123,000 23%
3 PREBID EXPENDITURES
a. Staff Engineering and Operations $102,000
b. Consultants $40,000
SUBTOTAL- PREBID EXPENDITURES $142,000 27%
4 TOTAL PROJECT ESTIMATED COST $789,000
May 4, 2022 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 34