Item 8.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: APRIL 21, 2022
SUBJECT: AUTHORIZE THE GENERAL MANAGER TO AMEND AN EXISTING
PROFESSIONAL ENGINEERING SERVICES AGREEMENT I N AN AMOUNT
NOTTO EXCEED $1.2 MILLION WITH STANTEC CONSULTING SERVICES,
INC., INCREASING THE AGREEMENT COST CEILING FROM $4,562,000
TO $5,762,000 FOR ENGINEERING SUPPORT SERVICES FOR THE
FILTER PLANT AND CLEARWELL IMPROVEMENTS AND THE WET
WEATHER BASIN IMPROVEMENTS PROJECTS; AND FIND THE
PROJECT IS EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL
QUALITYACT
SUBMITTED BY: INITIATING DEPARTMENT:
CHATHURAABEYRATHNA, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: CRAIG MIZUTANI, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board of Directors'authorization is required for the General Manager to execute an amendment to an
existing professional engineering services agreement above $200,000.
BACKGROUND
On May 3, 2018, the Board authorized an agreement with Stantec Consulting Services, Inc. (Stantec)to
provide design services for the Filter Plant and Clearwell Improvements, Phase 1, District Project 7361
April 21, 2022 Regular Board Meeting Agenda Packet- Page 39 of 135
Page 2 of 4
(Project). In addition, Stantec provided other services such as condition assessments of the facilities,
proved disinfection alternatives, hydraulics, seismic assessment, process and automation solutions, and
alternative filtration technology information.
Staff and Stantec took a long-term approach to the Filter Plant and Clearwell Improvements Project and
evaluated the possible impacts of future projects, including the Concord Community Reuse Project and a
potential Water Exchange Project. While looking at possible solutions, the team also evaluated Central
San's immediate existing facility needs to provide adequate system reliability. This evaluation prioritized
the most critical items that require replacement and that would not conflict with or potentially leave stranded
assets when other projects are implemented.
All the needed improvements to meet current recycled water demands were scoped and planned under
the Project. However, the design and construction of Phase 1 was split into two sub-phases: Phases 1A
and 1 B. Phase 1 A is currently in construction and includes improvements to the Applied Water Pump
Station, Recycled Water Pump Station, Filter Plant, a new electrical building, and two new recycled water
storage tanks located at the Clearwell. The improvements to the Filter Plant include an improved polymer
feed system, sodium hypochlorite disinfection system, instrumentation and piping, and one filter
refurbishment.
Phase 1 B will include seismic upgrades, rehabilitation of electrical equipment at the Filter Plant,
replacement of the three remaining existing filters, hydraulic upgrades to bypass the Forebays, chlorine
contact tanks, and other improvements. However, Phase 1 B has been deferred in an attempt to coordinate
with the Concord Community Reuse Project.
There are several aging electrical items that were not included in the Phase 1 A project but now need to be
addressed in an urgent manner, and before the Phase 1 B project is fully constructed. The Filter Plant
Electrical Rehabilitation Project will include the replacement of 480 volt feeders, motor control centers,
transformers and transformer disconnect switches, battery systems, low voltage conduit, and wire. Other
anticipated work includes the addition of HVAC units and exhaust fans to portions of the filter building.
Staff is recommending continuing with Stantec to design the electrical replacements and rehabilitation
based on their knowledge of these systems to ensure overall system reliability.
In addition, there are other needs relating to the Phase 1 A project construction that require the engineering
services of Stantec. These include:
• Engineering for a new emergency access road to the recycled water storage tanks for use by Central
San and the Contra Costa County Fire District.
• Additional services are anticipated as the Operations staff has requested that Stantec look at existing
permit compliance measures and design improvements to ensure continuous compliance with Title
22 regulations. The Regional Board has required a new engineering study and report since the new
storage tanks will be used for chlorine contact time, and staff will need to update compliance
procedures.
• Stantec designed the raising of the wet weather Basin C roadways under the Phase 1 A project using
the soils generated from the Clearwell levee. Portions of the roads for Basins B and D require the
same design to protect from potential flooding of Pacheco Slough. Staff is recommending that
Stantec continue the engineering effort to complete the work.
• Staff is requesting additional contingency for engineering services due to supply-chain issues, as
more effort has been needed to review submittals and respond to request for information.
Stantec was selected through a competitive solicitation, Request for Proposal process, to provide the type
April 21, 2022 Regular Board Meeting Agenda Packet- Page 40 of 135
Page 3 of 4
of services stated above and for the Phase 1A project, including the Filter Plant Electrical Rehabilitation.
California Environmental Quality Act(CEQA)
Staff has concluded that this project is exempt from CEQA under Central San's CEQA Guidelines
Section 15301, since it involves minor alterations to existing public facilities involving no expansion of use,
and CEQA Guidelines Section 15302, since it involves replacement of existing public facilities at the
same location and with the same purpose. Approval of this project will establish the Board of Directors'
independent finding that this project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Other alternatives are set forth below; however, they are not recommended by staff.
Alternative 1: Postpone the recommended project elements longer or minimize the scope and wait to
integrate solutions to the current problems with a future project phase. Under this alternative, staff would
amend Stantec's agreement for a lower value in the future as well as proceed with a smaller scope project
and postpone some of the needed work to the future, if possible.All elements suggested in the Filter Plant
Electrical Rehabilitation project are critical for the reliable operation of the recycled water system. These
electrical items were specifically selected to be replaced before the beginning of Phase 1 B because of
their importance.
Alternative 2: Do nothing to address the electrical equipment. Under this alternative, staff would lower the
amendment costs for Stantec's agreement, and the existing electrical items would continue operating in
their current condition. Repairs would be done as failures occur. This alternative could be more costly in
the future and likely impact the delivery and service to the recycled water users, the Central San treatment
plant, and Zone 1 customers.
Alternative 3: Seek other consultants to assist with the work. Stantec has performed satisfactorily under
the Phase 1A project and already has the knowledge of the existing system and related design issues.
Staff does not recommend a change in design consultants since the schedule would be delayed and the
design costs would likely increase.
FINANCIAL IMPACTS
The current Stantec agreement value is $4,562,000. This amendment has been negotiated to not exceed
$1,200,000, which will increase the agreement cost ceiling to $5,762,000.Approximately$650,000 of the
amendment will be allocated for the Filter Plant Electrical Rehabilitation. The preliminary construction cost
for the electrical rehabilitation is $6,000,000.
Approximately$200,000 will be allocated for the Wet Weather Basin I mprovements for the
embankment/levee design services. There is adequate budget within the Wet Weather Basin
Improvements project for these services.
The remainder of the design budget for this amendment may be used to cover any additional expenses
relating to the Phase 1 A or 1 B project. Both projects have sufficient funds to proceed, and the budgets are
shown on pages 277 and 280 of the fiscal year 2021-22 District Budget.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this subject at the April 6, 2022 meeting and
recommended approval.
April 21, 2022 Regular Board Meeting Agenda Packet- Page 41 of 135
Page 4 of 4
RECOMMENDED BOARD ACTION
Staff recommends the following Board action:
1. Find the project is exempt from CEQA; and
2. Authorize the General Manager to amend an existing professional engineering services agreement in
an amount not to exceed $1.2 million with Stantec Consulting Services, I nc., increasing the
agreement ceiling from $4,562,000 to $5,762,000 for engineering support services for the Filter
Plant and Clearwell Improvements and the Wet Weather Basin Improvements, District Projects
7361 and 100022, respectively.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL THREE:Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life
GOAL SIX:Innovation and Optimization
Strategy 2—Improve and modernize operations through technology and efficiency measures
April 21, 2022 Regular Board Meeting Agenda Packet- Page 42 of 135