HomeMy WebLinkAbout11. Authorize a construction change order with K.J. Woods, Inc. to include urgent replacement of sewers under District Project 8451 Page 1 of 4
Item 11.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: APRIL 7, 2022
SUBJECT: AUTHORIZE THE GENERAL MANAGER TO EXECUTE A CONSTRUCTION
CHANGE ORDER IN AN AMOUNT NOT TO EXCEED $328,000 WITH K.J.
WOODS CONSTRUCTION, INC., TO INCLUDE THE ECCLESTON
AVENUE/OAK PARK BOULEVARD SEWER REPLACEMENT ADJACENT TO
THE NEW PLEASANT HILL LIBRARY UNDER THE COLLECTION SYSTEM
SEWER RENOVATION, PHASE 1, DISTRICT PROJECT 8451; AND FIND
THE PROJECT IS EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL
QUALITYACT
SUBMITTED BY: INITIATING DEPARTMENT:
DAMASI0 ZEPEDA ARAGON, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey Kenton L. Alm
General Manager District Counsel
ISSUE
Authorization from the Board of Directors (Board) is required to execute a construction contract change
order in an amount greater than $200,000.
April 7, 2022 Regular Board Meeting Agenda Packet- Page 132 of 194
Page 2 of 4
BACKGROUND
Capital Projects staff has been meeting with the City of Pleasant Hill (City) and other utilities, such as the
Contra Costa Water District, on a staff level to coordinate future construction activities and street paving
plans. The efforts are aimed to coordinate utility work along with the City's plans for street rehabilitation and
reduce the construction impacts to the public, neighborhoods, and residents. During a recent meeting, it
was observed that one of Central San's sewers on Eccleston Avenue in Walnut Creek includes
replacement that spans into Oak Park Blvd. and the easement located at the Pleasant Hill Library project
site, as shown in the attached map. These sewers were yet to be determined for replacement at the time
Central San reviewed the City plans several years ago. Staff has deemed the sewers to be near the end of
their useful life, and full replacement by open-trench method is required to properly install new sewers to
current design standards.
In total, approximately 700 feet of existing sewers are scheduled to be replaced due to the deficiencies on
the Eccleston Avenue sewer. The scope of work also includes constructing sewer manholes, reconnecting
side sewers, new sewer alignments, abandonment work, traffic control, permits, restoration of public right-
of-way and private easements.
The City plans to complete the library project by the middle of this year and has requested that Central San
minimize the construction impacts of the sewer work to its residents and patrons of the newly constructed
library. Staff concurs and is recommending completing the work prior to the City's final acceptance and
grand opening. To accomplish such an aggressive timeline, traditional bidding methods cannot be used,
but the work can be accomplished if contracted through one of Central San's current sewer construction
contractors.
Staff contacted three contractors and is obtaining quotes from two of them. The first is Andes
Construction, I nc. (Andes)who recently completed the rehabilitation of 12,700 feet of sewer mains on the
Lafayette Sewer Renovations, Phase 14 project. The second being K.J. Woods Construction, Inc. (K.J.)
who is currently working on the North Orinda Sewer Renovations, Phase 8 project.A third contractor was
contacted but due to scheduling, a quote will not be obtained. Central San does not have a contractor
focused in Pleasant Hill at this time.Andes and K.J. are experienced with District projects and are familiar
with project area and jurisdiction requirements. The engineer's estimate was $360,000. The respective
quotes received were $372,408 and $328,000, respectively.
The construction contracts issued for sewer renovation projects has provisions to allow Central San to
include additional sites within the scope of the contract work for public sewers that may need to be
replaced on an urgent timeline or in case of an emergency.Avoiding construction impacts to the
community has always been a Central San priority and, due to sewer replacement timing and coordinating
with the City's project and requirements, the replacement of the sewer is considered urgent and can be
added to an active construction contract.
California Environmental Quality Act(CEQA)
Staff has concluded that this project is exempt from CEQA under Central San CEQA Guidelines Section
15302 because it involves replacement of existing facilities at the same locations and with the same
purpose.Any capacity increases are for non-growth inducing, wet weather purposes.Approval of this
project will establish the Board's independent finding that this project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Consider or request working with the City's contractor to perform the work. The City and Central San
entered into a Joint Powers Agreement early in the library project construction to relocate a Central San
sewer on the City property; however, the underground contractor has since demobilized and the sewer
work is beyond the jurisdiction of Pleasant Hill.
April 7, 2022 Regular Board Meeting Agenda Packet- Page 133 of 194
Page 3 of 4
The sewers require replacement; therefore, the Board has very limited alternatives, but could consider
bidding the work as a stand-alone project or as part of an upcoming sewer renovation project. This would
delay the work and yield a negative impact to the local neighborhood residents and library. Staff does not
recommend any approach that adds time beyond the new library grand opening.
FINANCIAL IMPACTS
The total estimated budget for the work is approximately$440,000, which includes the change order costs
with the contractor, permits, staff and consultant time, and contingency. To fund the work, staff will charge
all costs to the Collection System Sewer Renovation, Phase 1, District Project 8451. This program project
has adequate funding and has a budget of$5.6 million as shown on page 211 in the Fiscal Year 2021-22
Budget.
COMMUNITY OUTREACH
Staff has been in close coordination with the City of Pleasant Hill regarding this work throughout the
design process. Both Central San and the City of Pleasant Hill agree that the impact to the community
should be minimized by completing this work prior to the new library's grand opening. Staff has been in
contact with the local and impacted residents and continue to do so. Construction notification will be
issued and additional outreach will be conducted prior to any construction work.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee considered this matter at its March 16, 2022 meeting and
recommended approval.
RECOMMENDED BOARD ACTION
Staff recommends the following Board action:
1. Find the project is exempt from CEQA; and
2. Authorize the General Manager to execute a construction change order in an amount not to exceed
$328,000 with K.J. Woods Construction, Inc., to include the Eccleston Avenue/Oak Park Blvd.
Sewer Replacement adjacent to the new Pleasant Hill Library under the Collection System Sewer
Renovation, Phase 1, District Project 8451.
Strategic Plan re-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service, Strategy 2—Maintain a positive reputation
GOAL FIVE: Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 2—Execute long-term capital renewal and
replacement program
ATTACHMENTS:
1. Location Map
April 7, 2022 Regular Board Meeting Agenda Packet- Page 134 of 194
Page 4 of 4
Eccleston Ave / Oak Park Sewer Renovations
Pleasant Hill / Walnut Creek Boundary
Map Date:3/10/2022
Martinez
•�� Concord
Boyd-Rd
Pleasant Hill
Detail
Q Area
Beatrice-Rd
Walnut Creek
Roberta-Ave •��
�` Qa
m`
Pleasant Hill Library
a Ifo
L
� Es Z
Oak-Park-Blvd
Rogers-Ave
Hudson-Ave
SSun-Valley-Dr
un-Sun
Eccleston-Ave
En
m Sunny vale- ve
l
I I I
Geary-Rd Treat:Blvd
Pioneer Ave
- Project Location
Q Pleasant Hill
Q Walnut Creek
Q Unincorporated Area
Note: 0 1,000 Map Displayed in North American Datum of 1983 Attachment