HomeMy WebLinkAbout07. Approve a new capital project to support the Solar Array Project on the Lagiss Property and authorize associated budgetary components Page 1 of 7
Item 7.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: FEBRUARY3, 2022
SUBJECT: APPROVE A NEW DISTRICT CAPITAL PROJECT TO SUPPORT CENTRAL
SAN'S SOLAR PROJECT ON THE LAGISS PROPERTYAND AUTHORIZE
THE GENERAL MANAGER TO:
1. TRANSFER $600,000 FROM THE FISCAL YEAR 2021-22 CAPITAL
IMPROVEMENT BUDGET CONTINGENCY FUND TO THE NEW
PROJECT;
2. PAYAN APPROXI MATE $533,000 PG&E I NTERCONNECTI ON FEE;
AND
3. INCORPORATE THE NEW RESULTING SOLAR ENERGY PRICE OF
$0.0857 PER KI LOWATT-HOUR I NTO AMENDMENT 1 OF CENTRAL
SAN'S POWER PURCHASE AGREEMENT WITH REC SOLAR
SUBMITTED BY: INITIATING DEPARTMENT:
MELODY LABELLA, RESOURCE RECOVERY ENGINEERING AND TECHNICAL SERVICES-
PROGRAM MANAGER RESOURCE RECOVERY
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey Kenton L. Alm
General Manager District Counsel
ISSUE
Board of Directors (Board) authorization is required to create and fund new capital projects that exceed the
General Manager's signature authority and to amend an existing Power Purchase Agreement (PPA).
February 3, 2022 Regular Board Meeting Agenda Packet- Page 37 of 72
Page 2 of 7
BACKGROUND
At its January 13, 2022, special meeting, the Board continued and closed a public hearing, adopted a
mitigated negative declaration under the California Environmental Quality Act (CEQA), and approved
Central San's Solar Project on the Lagiss property. As indicated during the presentation, staff is returning
to seek the Board's approval to create a new project for the payment of certain elements of the project to
achieve the highest financial benefit for Central San over the 25-year term of the PPA with REC Solar.
I n particular, staff is recommending direct payment of approximately$533,000 for the project's PG&E
interconnection, which is an asset Central San will own, since the interconnection will be made to a
property owned by Central San. Staff is also requesting $50,000 to cover near-term CEQA mitigation
costs associated with the project, which are Central San's responsibility per the terms of the PPA.
Depending on the outcome of four biological surveys to be conducted over the burrowing owl nesting
season in 2022 (February 1 -August 31), funding for additional CEQA mitigation costs may be needed.
Staff will return to the Board later this year to provide an update on the results of the surveys and request
additional funds, if necessary.
Central San's PPA currently requires that REC Solar fund the PG&E interconnection cost as part of the
overall project and that cost was reflected in the solar power price offered. If Central San pays for that
element, the solar power price will drop from $0.10 per kilowatt hour(kWh)to $0.0857 per kWh. Staff is
requesting the Board's approval to incorporate this new pricing and the appropriate language updates
related to the payment of PG&E's interconnection fee into Amendment 1, which was approved at the
January 13, 2022 Board meeting and is currently being drafted.
ALTERNATIVES/CONSIDERATIONS
The Board could choose not to directly fund PG&E's interconnection fee and allow it to be paid by REC
Solar, as originally planned. This is not recommended, because, by paying directly, Central San would
realize the highest net present value (NPV)of savings over the 25-year PPA term.
FINANCIAL IMPACTS
If the Board moves forward with staff's recommendation to pay PG&E's interconnection fee, rather than
financing it through the PPA with REC Solar, Central San will save an additional $437,000 to $870,00 in
NPV over the 25-year term of the PPA. The savings will depend on PG&E's actual utility escalation rate,
which has been modeled by our solar consultant at both 3% and 4.5% per year. To accomplish the
payment of the interconnection fee, PG&E would be paid approximately$503,000 and REC Solar would
be reimbursed the $30,000 initial deposit it has already paid to PG&E.
The new District project is estimated to cost$600,000, which includes approximately$533,000 to cover
PG&E's fee, $50,000 to cover initial CEQA mitigation costs, and approximately$17,000 in contingency. A
transfer of$600,000 from the Fiscal Year(FY)2021-22 Capital Improvement Budget (CI B) contingency
fund will be completed upon the Board's approval of the new project, leaving a contingency fund balance
of$1.75 million.
COMMITTEE RECOMMENDATION
The Real Estate, Environmental and Planning Committee reviewed this matter at its January 26, 2022
meeting and recommended approved.
February 3, 2022 Regular Board Meeting Agenda Packet- Page 38 of 72
Page 3 of 7
RECOMMENDED BOARD ACTION
Approve a new District project in the amount of$600,000 to support Central San's Solar Project on the
Lagiss Property and authorize the General Manager to:
1. Transfer$600,000 from the FY 2021-22 Cl B contingency fund to the new project;
2. Pay a PG&E interconnection fee of approximately$533,000; and
3. Incorporate the new resulting solar energy price of $0.0857 per kWh into Amendment 1 of Central
San's PPA with REC Solar.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 2—Maintain a positive reputation
GOAL TWO: Environmental Stewardship
Strategy 4- Reduce reliance on non-renewable energy
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
ATTACHMENTS:
1. Presentation
February 3, 2022 Regular Board Meeting Agenda Packet- Page 39 of 72
Item 7.
(Updated Presentation)
'{4 q
APPROVE A NEW DISTRICT PROJECT TO
l SUPPORT CENTRAL SAN'S SOLAR PROJECT
ON THE LAGISS PROPERTY
Melody LaBella, P.E.
Resource Recovery Program Manager
Board Meeting
February 3, 2022
SOLAR PROJECT BACKGROUND
June 2020: Request for Proposals issued ProposedS*WrProjed _
for a Power Purchase Agreement (PPA)
November 5, 2020: Board awarded a PPA `
to REC Solar for a 1 .75 megawatt (MW)
solar photovoltaic system on Central San's
Lagiss property
July 2021 : Project design sufficient to w '
complete environmental evaluation = r.
January 2022: Board adopted mitigated
negative declaration, approved project, -
and approved PPAAmendment 1 with a
new solar price of $0.10 per kilowatt-hour o� �
(kWh) R � z
1
RECOMMENDING PAYMENT OF PG&E'S
INTERCONNECTION FEE
• The interconnection with PG&E is a facility Central San will own,
regardless of who pays for it.
• Central San's PPA currently makes REC Solar responsible for
paying PG&E's interconnection fee of approximately $533,000.
• If Central San pays the interconnection fee, the solar power price
will drop from $0.10 to $0.0857 per kWh and Central San will realize
the highest savings on a net present value basis.
• Staff is recommending that Central San pay the interconnection fee
directly and the new solar rate and related language be incorporated
into PPAAmendment 1 , which is currently being drafted.
' 3
CENTRAL SAN
FINANCIAL ANALYSIS
Summary of Financial Scenarios with an Annual Utility Escalation Rate of 3.0%
1. • $0.08660 $6,469,426 $4,424,185 1
2.PPA • • $0.10244 $5,165,364 $3,372,654 1
• $0.11558 $4,083,605 $2,589,890 2
Capital-PPA4.
• $0.08573 $5,968,576 $3,809,682 5
Capital-PPA5. • $0.08573 $5,518,576 $3,370,657 8 _
Summary of Financial Scenarios with an Annual Utility Escalation Rate of 4.5%
IM-01M�offl Cash .
02MUM (Year)
1. • $0.08660 $9,918,476 $6,666,530 1
2.PPA Covers All Costs: CEQA Low $0.10244 $8,614,414 $5,560,308 1
• = $0.11558 $7,532,655 $4,777,544 1
Capital-PPA4. • $0.08573 $9,417,626 $5,997,336 5
Hybrid:5.Capital-PPA • $0.08573 $8,967,626 $5,558,311 7
California Environmental Quality Act(CEQA) 40m ' q
CFNTPAI SAN
2
NEW DISTRICT PROJECT REQUES-
In order to fund elements of Central San's Solar Project,
staff is requesting approval of a new District project in the
amount of $600,000.
Approximately $533,000 to pay PG&E's interconnection fee
$50,000 to cover initial CEQA mitigation costs
Approximately $17,000 contingency
Staff is requesting approval to fund the new project from
the Fiscal Year (FY) 2021 -22 Capital Improvement Budget
(CIB) contingency fund, which currently has $2.35 million.
CENTRAL SAN
IS
COMMITTEE REVIEW ww
041
iish;
The Real Estate, Environmental ander
g
Plannin Committee reviewed this matter at -111
�
its January 26, 2022, meeting and supported
staffs recommended Board actions.
16
3
RECOMMENDED BOARD ACTIONS
Approve a new District project in the amount of $600,000 to
support Central San's Solar Project on the Lagiss Property;
Authorize the General Manager to transfer $600,000 from the
FY 2021-22 CIB contingency fund to the new project;
Authorize the General Manager to pay a PG&E interconnection
fee of up to $533,000; and
Authorize the General Manager to incorporate the new resulting
solar energy price of approximately $0.0857 per kWh into
Amendment 1 of Central San's PPA with REC Solar.
I
QUESTIONS?
CFNTPAISAN
4