HomeMy WebLinkAbout04.a. Review draft Position Paper to approve a new District Project in the amount of $3.6 million for solids handling facility improvements, phase 2; and authorize the general manager to transfer $3.6 million from the Solids Handling Facility ImprovementPage 1 of 18
Item 4.a.
DCENTRALSAN
MEETING DATE: DECEMBER 14, 2021
BOARD OF DIRECTORS
POSITION PAPER
DRAFT
SUBJECT: REVIEW DRAFT POSITION PAPER TO APPROVE A NEW DISTRICT
PROJECT IN THE AMOUNT OF $3.6 MILLION FOR SOLIDS HANDLING
FACILITY IMPROVEMENTS, PHASE 2; AND AUTHORIZE THE GENERAL
MANAGER TO:
TRANSFER $3.6 MILLION FROM THE SOLIDS HANDLING FACILITY
IMPROVEMENTS, PHASE 1 TO THE NEW PROJECT; AND
EXECUTE TWO PROFESSIONAL ENGINEERING SERVICES
AGREEMENTS TO EVALUATE AND PLAN FOR LONG-TERM SOLIDS
HANDLING AND DISPOSAL WITH: 1) BROWN AND CALDWELL, I N AN
AMOUNT NOT TO EXCEED $1.8 MILLION, AND 2) CAROLLO
ENGINEERS, IN AN AMOUNT NOT TO EXCEED $250,000
SUBMITTED BY: INITIATING DEPARTMENT:
NITIN GOEL, SENIOR ENGINEER
ENGINEERING AND TECHNICAL SERVICES-
PDS-ASSET MANAGEMENT
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
DANEA GEMMELL, PLANNING AND DEVELOPMENT SERVICES DIVISION
MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
The Board of Directors' (Board) authorization is required for the General Manager to execute a
professional engineering services agreement in an amount greater than $200,000. Board authorization is
also required to initiate a new capital project greater than $200,000 and to transfer funds between projects
greater than $500,000.
BACKGROUND
On September 2, 2021, the Board rejected all bids for the construction of the Solids Handling Facility
I mprovements, District Project 7348 (Phase 1) due to the excessive costs of the bids received and
overall project costs. Thereafter, staff proposed moving forward with a reduced scope for Phase 1
and also to re-evaluate the long-term Solids Handling and Disposal plan as developed in 2017 under
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 4 of 23
Page 2 of 18
the Comprehensive Waster Master Plan (CWMP). A copy of the presentation used at the June 16,
2016, Board workshop on Solids Process Alternative Analysis CW MP has been provided as
reference in Attachment 2.
On November 18, 2021, the Board authorized the General Manager to execute engineering agreements to
repackage and bid the urgent and critical elements of the Phase 1 project, which will include replacement
of the wet air scrubbers for the incinerators, four centrifuges and cake pumps, improvements to incinerator
burners, and other miscellaneous equipment associated with the systems. This reduced scope project will
be named the Solids Handling Facility Improvements, Phase 1 A.
At the September 2, 2021 Board meeting, staff made a recommendation to proceed with re-evaluating the
long-term solids handling facility plan i.e., Solids Handling Facility Improvements Phase 2 (Phase 2).
Phase 2 will evaluate and plan the optimal alternative(s) for long-term solids handling and disposal which
may include, but not limited to, new solids processing and energy recovery facilities, anaerobic digesters,
new biogas cogeneration system, fluidized bed incinerators, or other thermal treatment technologies. Staff
issued a Request for Proposal (RFP) for professional engineering services to evaluate these potential
alternatives and find the best long-term biosolids facilities plan for Central San. On September 21, 2021,
two (2) proposals were received: 1.) Brown and Caldwell (B&C) and 2.) a team of Carollo Engineers, Inc.
(Carollo), HDR, Inc.(HDR), and GHD, Inc. (GHD).
After conducting interviews, B&C was selected as the lead consultant to assist Central San in the planning
of the Phase 2 project. In addition, Carollo will also be participating, leading the Peer review with HDR to
assist in the task associated with integration with the Steam System Evaluation, and GHD to aid with
existing Furnace or thermal process evaluation.
Being that the evaluation and resulting decisions of the long-term Solids Handling Facilities at Central San
is critical, it will require the views, perspectives, and options of many experts in the fields associated with
these types of facilities. This will also require an in depth evaluation of integration of new facilities with the
existing incinerators, co -generation, and steam systems. Therefore, included in the RFP was hiring
additional experts or firms to assist in Peer Review or assess alternative project delivery methods. Four
proposals were received on November 3, 2021 from AECOM, Greeley and Hansen, Jacobs (formally
C H2M Hill), and Stantec, Inc (Stantec). All firms were selected to participate on expert panels for the
overall peer review. Jacobs was selected to perform alternate delivery evaluation and will also be assisting
with the Peer Review.
All viable and proven technologies for treatment and disposal of the solids, energy, biogas production, and
side stream treatment will be considered as a part of evaluation process. Staff will work with B&C, Carollo,
and the other experts identified above to determine the best long-term solution for Central San and
address the many questions or possibilities for future solids handling and disposal at Central San.
California Environmental Quality Act
Staff has concluded that this action is exempt from the California Environmental Quality Act (CEQA)
under Central San's CEQA Guidelines Section 15262 since it allows for further planning and feasibility
studies for possible future actions which Central San has not approved, adopted, or funded, and the
outcome of these tasks will not have a legally binding effect on later activities. Approval of this action will
establish the Board of Directors' independent finding that these agreements are exempt from CEQA.
Central San will conduct an environmental evaluation of any environmental -altering, physical project that is
proposed in the future as a result of these studies to determine the need for any additional CEQA
documentation.
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 5 of 23
Page 3 of 18
ALTERNATIVES/CONSIDERATIONS
Alternative 1 - Do not perform the Phase 2 project now. This alternative is not recommended. Continuing
with the current solids process is a significant capital expense, as represented in the bids received under
the Phase 1 Project. Staff is recommending to re -confirm or possibly determine another path moving
forward to better use capital funding or transition into other future long-term solid processes. The
evaluation and planning methods will provide an optimal road map for Central San for decades to come,
and update the ten-year Capital Improvement Plan.
Alternative 2 - Another alternative would be to select only a single firm to provide the services. This option
was considered by staff but ultimately determined to not be an optimal approach for this project. It is
recommended that the road map for the Central San should be vetted out by many industry experts. The
selected firms are bringing specific specialization and experience to the various scope or technology
items. This alternative is not recommended.
Alternative 3 - Continue with the remaining work that has been postponed under the Phase 1. Staff is
monitoring items and will address any future work on an as -needed basis. B&C could also consider the
alternative or timing of a Phase 1 B Project, which includes other components that should be considered
moving forward in the long-term plan. This alternative will be considered as part of the business case
evaluations under the Phase 2 project.
FINANCIAL IMPACTS
The total estimated cost for the planning of the Solids Handling Facility Improvements, Phase 2 is
estimated at $3.6 million, which includes consultant services for $2.8 million and staff time of $800,000.
The Phase 1 Project (District Project 7348) is listed on page 236 of the Fiscal Year 2021-22 Central San
Budget and has sufficient funds to initiate the Phase 2 project. A transfer of $3.6 million from Phase 1 to
Phase 2 will be completed upon Board approval of the new project and transfer amount.
Several agreements are within the General Managers authority (less than $200,000) and range from
$50,000 - $195,000 and include the following engineering firms:
• AECOM
• GHD, Inc.
• Greeley and Hansen
• HDR, Inc.
• Jacobs
• Stantec
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its December 14, 2021 meeting and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following Board actions:
1. Approve a new District project in the amount of $3.6 million for the Solids Handling Facility
Improvements, Phase 2;
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 6 of 23
Page 4 of 18
2. Authorize the General Manager to transfer $3.6 million from the Solids Handling Facility Phase 1,
District Project 7348 to new Phase 2 Project;
3. Authorize the General Manager to execute professional engineering services agreements to evaluate
and plan for long-term solids handling and disposal with:
• Brown and Caldwell, in an amount not to exceed $1.8 million; and
• Carollo Engineers, Inc., in an amount not to exceed $250,000.
Strategic Plan re -In
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations, Strategy 2—Anticipate and prepare for potential regulatory
changes, Strategy 4 - Reduce reliance on non-renewable energy
GOAL FIVE: Infrastructure Reliability
Strategy 1— Manage assets optimally to prolong their useful life, Strategy 2 — Execute long-term capital renewal and
replacement program
ATTACHMENTS:
1. Presentation
2. CWMP Board Workshop Presentation 06-16-16
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 7 of 23
Page 5 of 18
ATTACHMENT 1
LONG-TERM SOLIDS FACILITIES PLAN PROJECT
.LEAN-MARC PETIT, DIRECTOR OF ENGINEERING & TECHNICAL SERVICES
NITIN GOEL, SENIOR ENGINEER, SPECIAL PROJECTS & ASSET MANAGEMENT GROUP
ENGINEERING & OPERATIONS COMMITTEE MEETING
DECEMBER 14, 2021
1
2
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 8 of 23 1
Page 6 of 18
PROJECT DESCRIPTION
• This project will evaluate, plan, and update the Long-term Solids
Handling, Treatment and Disposal Facilities as outlined in the
Comprehensive Wastewater Master Plan (CWMP) and update the
Ten -Year Capital Improvement Plan (CIP).
• It will review and evaluate, the optimal alternative(s) for long-term
solids handling and disposal which may include new solids
processing and energy recovery facilities such as anaerobic
digesters and a new biogas cogeneration (Co-gen), or other
thermal treatment processes.
• It will also evaluate this plan in concert with the Solids Handling
Improvement Project, Phase 1A currently being redesigned.
3
PROJECT GOALS
• Review the various technologies for treatment and disposal of solids.
• With this project, Central San needs to determine the following:
• How to best transition from current solids handling and disposal methods to any
proposed approach?
• What are the viable long-term options for disposal of solids: Class B or Class A,
or other such as ash or char?
• Diversified disposal of solids, and address issues associated with per- and
polyfluoroalkyl substances (PFAS) on land disposal?
• Evaluate viable regional option for treatment and disposal that would benefit all
parties?
• Many other questions.
4
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 9 of 23 2
Page 7 of 18
ROADMAP FOR LONG-TERM SOLIDS FACILITIES PLAN UPDATE
8. Prepare Updated
Technical Memorandum 19. Evaluate Transitionin Solids and EnergyPlans
Related CWMP for the
Selected Alternative(s)
5
CURRENT SOLIDS FINANCIAL BACKGROUND
NEEDS TO UPDATED
• CWMP 2017
• Current Fiscal Year 2021-22 CIB and Ten -Year CIP:
• Solids Phase 1: Improvements to the Solids Handling Facilities, District
Project (DP) 7348: (Not Awarded). Phase 1A under
redesign.
• Steam System Improvements, DP 7349: $35.4 M
• MHF Replacement, DP 100009: $1 M
• Replace Co -Gen System: $25.4 M
• Other Solids Facilities Improvement Projects: e.g.; Dissolved Air Flotation
Thickener (DAFT): $2.4 M
• Future Solids Related Projects beyond Ten -Year:
• Solids Phase 2: Add two Anaerobic Digesters with Digester Gas Co -Gen:
$126.8 M
• Solids Phase 3: Add two additional Anaerobic Digesters and a Fluidized
bed incinerator (and abandon existing MHFs): $175.4 M
1XV
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 10 of 23 3
Page 8 of 18
RE-EVALUATE LONG-TERM PATH FOR
SOLIDS HANDLING AT CENTRAL SAN
Path 1: Proceed with Path 2: Re -Evaluate Long -
Reduced Scope for Phase 1A Term Solids Handling and
Disposal - Solids Phase 2
Refurbish MHFs,
Replace Re -Evaluate Long -
Centrifuges, Cake + Term Solids Handling
Pumps and Wet and Disposal
Scrubbers Alternatives Facilities
Plan Update
"` 4_ . Proceeding
with both
paths
i%
STAFF HAS SELECTED THE FOLLOWING TEAM TO CONDUCT
THE LONG-TERM SOLIDS FACILITIES PLAN
The following engineering consulting firms have been selected to evaluate and
plan for the long-term the elements of the Solids Phase 2 Project:
• Brown and Caldwell
• Carollo Engineers
Staff is planning to issue the following contracts under staff authority:
• AECOM
• GHD
• Greeley and Hansen
• HDR
• Jacobs
• Stantec
I
8I
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 11 of 23 4
Page 9 of 18
RECOMMENDED BOARD ACTION
Staff recommends the following Board actions:
1. Approve a new District project in the amount of $3.6 million for the Solids Handling
Facility Improvements, Phase 2;
2. Authorize the General Manager to transfer $3.6 million from the Solids Handling Facility
Phase 1, District Project 7348 to new Phase 2 Project;
3. Authorize the General Manager to execute professional engineering services agreements
to evaluate and plan for long-term solids handling and disposal with:
• Brown and Caldwell, in an amount not to exceed $1.8 million; and
• Carollo Engineers, Inc., in an amount not to exceed $250,000.
QUESTIONS?
10
10
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 12 of 23 5
Page 10 of 18
Attachment 2
-qr
LONG-TERM BIOSOLIDS FACILITIES PLAN PROJECT
CWMP PRESENTATION JUNE 16, 2016
ENGINEERING & OPERATIONS COMMITTEE MEETING
DECEMBER 14, 2021
COMPREHENSIVE WASTEWATER MASTER PLAN
-"° Board Workshop
swo+
Part A
Treatment Plant Master Plan Update
June 16, 2016
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 13 of 23 1
Page 11 of 18
Attachment 2
PHASED APPROACH TO ADDRESS FURNACE
CAPACITY LIMITATIONS
Capacity/Regulatory Testing
Pilot New Wet Scrubber
Lime Reduction Testing
Storage and Mixing
Improvements
Replace Centrifuges
Pilot Innovative Technologies
Increase Permitted Capacity
Long -Term Split Stream
Demonstration Facility
Implement Nutrient Removal
Early Implementation of
Digesters with Incineration
Assess Feasibility of Permit Increase 0-5
Improved Regulatory Reliablility 0-5
Reduce Load to MHF 0-5
(delays trigger by >3 years)
Improve Reliable Solids Storage 0-5
Capacity/Addresses Peak Day Capacity
Improve Reliable MHF Capacity 0-5
Assess Feasibility of Split Solids Handling 0-5
Depends on Testing
(delays trigger by -5 years) 5 10
Use Innovative Split Stream Technology
10 20
to Reduce MHF Load
Reduces Solids Load 10-20
(delays trigger by -5 years)
New System Sized for Projected Loads 10-20
SOLIDS PROCESS ALTERNATIVE
ANALYSIS PRESENTATION
FROM JUNE 169 2016
BOARD WORKSHOP
3
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 14 of 23 2
Page 12 of 18
Attachment 2
SOLIDS HANDLING GOALS
• Identify Ideal Alternative for Replacing Multiple Hearth
Furnaces when Replacement is Required
• Timing Based on Condition: >20 Years
• Timing Based on Regulatory & Capacity Drivers: Likely > 10 Years
• Identify Costs & Footprint Required
• Improve Energy Efficiency
• Reduce Greenhouse Gas Emissions
• Triple Bottom Line Plus
POTENTIAL SOLIDS HANDLING ALTERNATIVES
1. Keep Existing MHFs & Replace Ash System & Air
Pollution Control Devices
2. Replace MHFs with Fluidized Bed Incinerators
3. Add Digesters Upstream of Incineration
4. Replace MHFs w/ Digestion & Biosolids Disposal Program
5. Consider Alternative Thermal Processes
➢ Gasification
➢ Pyrolysis
➢ Others
5
61
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 15 of 23 3
Page 13 of 18
Attachment 2
SOLIDS STREAM NARROWED TO BASELINE PLUS
THREE ALTERNATIVES
:ernative 'Solids Processing nergy production
ORC (After Conversion To Electric Blowers)
Baseline KeepMHFs +Gas Turbine
51 Transition from MHF to FBI ORC (After Conversion To Electric Blowers)
+ Gas Turbine
52 AD + Transition from MHF to ORC (after conversion to electric blowers) +
FBI Gas Turbine + FOG Addition to AD's
53 Transition to all AD + Gas Turbine + FOG Addition to AD's
Thermal Hydrolysis
7
ALTERNATIVE S1 LAYOUT
CONVERT
TO FLUIDIZED BED INCINERATION
Qemonstration
Project
Gas Conditioning System
+'S Emergency Sludge
ea Load Out Facility
• �' Ash Thickeners
�& A
FBIs, ORC, Gas Turbine,
A and Vacuum Filter in
' A existing solids building
Blend Tank
Wet Weather
Solids Storage
• Tank.'
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 16 of 23 4
Page 14 of 18
Attachment 2
ALTERNATIVE S2 LAYOUT DIGESTION WITH
FLUIDIZED BED INCINERATION
oil
M
~� Sidestream
Treatment
Solids
Demonstration
I Project
Gas r,
Conditioning
�. System •
Blend Tank
Ash
JThickeners w
FOG Receiving
Station
Gas Storage
Gas Treatmer
a
Anaerobic Digestion Process
Emergency Sludge
Load Out Facility
DAFT Tank (t)
MEN
Dryer, FBIs, ORC, Gas
Turbine, and Vacuum Filter
in exsiting solids building
3r// . I
ALTERNATIVE S3 LAYOUT — ALL DIGESTION
1
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 17 of 23 5
Page 15 of 18
Attachment 2
CHALLENGES
OF BIOSOLIDS DISPOSAL
pRF.f�pN
[
tlF,
oa.w
9Eefu� Of CeuMy �Mlrun[aa
I
i.w•• wue.A Nam, � � 9frt o�Af LMQ+�YWKkq�
R�dld 9en
� � uenm Cw.6
f� Elan AP�b^ Abner
F�pi�vrCldriry farhd
�
fw ^.
wr.iwmw.n�o
fro REVM,4
r.vli°r
ate' n1p{ iuxa
MbyCO
Figuru
11.4 SEulus ul Biosufds Land AppFral'un Didirwnas 6y CuurM1y
REGULATIONS ARE EXPECTED TO BAN SOLIDS DISPOSAL
AND USE OF BIOSOLIDS FOR ALTERNATE DAILY COVER
(ADC) AT LANDFILLS BY 2025
• By 2020, AB 341 will require 75%
reduction of organic solid waste:
either reduced at the source,
recycled, or composted
• By 2020, AB 1594 will disallow green
waste to qualify for diversion credit
when used as ADC at a landfill
• By 2025, Short Lived Climate
Pollutant Reduction Strategy will
likely lead to elimination of organic
waste (biosolids) from landfills
12
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 18 of 23 6
Page 16 of 18
Attachment 2
CONSIDERATIONS FOR BIOSOLIDS DISPOSAL IN
THE FUTURE
• Landfill disposal should not be
considered a viable solution
• Beneficial use/land disposal will
require treatment of biosolids to
Class A standards
• There is be more competition from
other agencies for disposing
biosolids in available sites, leading
to higher costs and risks
13
COMPARING SOLIDS HANDLING ALTERNATIVES
Reduces Energy Required &
Cannot Use Co -Digestion
Greenhouse Gas Emissions
to Reduce Plant Energy
Alternative S1
Compared to Existing MHF
Needs
Fluidized Bed
Furnaces
Highest Energy &
$350
Does Not Require Biosolids
Greenhouse Gas
Incineration
Disposal
Emissions Compared To
Familiarity with Operation
Other Alternatives
Smallest Footprint
Lowest Capital Cost
Requires More Footprint
Alternative S2
Significantly Reduces Energy
than Incineration Only
Required & Greenhouse Gas
Multiple Processes Adds
Fluidized Bed
Emissions
Some Complicatio n as
$340
Incineration/ Anaerobic
Does Not Require Biosolids
compared to existing
Digestion
Disposal
operation
Cogeneration Opportunity
Multiple Solids Disposal Options
Highest Capital Cost
More New Unit Processes
Least Energy Required
Requires Biosolids
Alternative S3
Lowest Greenhouse Gas
Disposal Program
$380
Anaerobic Digestion
Emissions
Increased Odor Control
Cogeneration Opportunity
Significant Truck Traffic
Produces Class A Product
Most Chemicals Required
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 19 of 23
Page 17 of 18
Attachment 2
PRELIMINARY SOLIDS
STREAM
TBL+
RESULTS
■T-1: Provide Reliability and Performance
E2
■ T-2: Process Efficiency
El
■ Fl: Minimize Capital Costs
E
■ F2: Minimize Life -cycle Costs.
52
El
El
■ S-1: Protect Public Health and Safety
S1
52
52
E2
E1
■ S2: Maintain Good Public Relations
Sl
S1
S2
F2
■ E-1 Minimize Impact on Local Environment
F2
F2
S1
F1
IIIE-2: Minimize impact on Global Environment
NF,F2FT
T1
Ideal Alternative Alt 1- FBIs
Alt 2 - Digestion + Alt 3 - Digestion
Dryer + FBI
Only
' 15
MINIMIZING
GREENHOUSE GAS EMISSIONS
30000
California Cap and Trade Threshold is>_25,000 MT of COze
Anthropogenic Stationary Combustion Emissions
25000
20000
0
U
`o
0
15000
7
10000
5000
0
Current
Projected (MHF) Alternative 1 Alternative 2 Alternative 3
a Natural Gas Combustion ■ Digester Biogas Combustion (CH4 & N20)
❑Landfill Biogas Combustion
(CH4 & N20) ❑Incineration (CH4 & N20)
' 16
December 14, 2021 EOPS Regular Committee Meeting Agenda Packet - Page 20 of 23 8
Page 18 of 18
Attachment 2
MASTER PLAN RECOMMENDATIONS - 6
• Implement All 0-5 year Studies and Projects:
• Implement Recommended Mixing & Storage Tank
Improvements to Handle Peak Day Loads
• Replace Centrifuges and Cake Pumps
• Initiate Lime Reduction & Capacity Testing As Soon As
Possible to Confirm Capacity Trigger Timing &
Feasibility
• Pilot Innovative Solids Technologies
• Seismic Improvements to Solids Handling Building
• Wet scrubber pilot and replacement
17
MASTER PLAN RECOMMENDATIONS - 6
(CONTINUED)
• Use Alternative S2: Digestion Followed By Fluidized Bed
Incineration As The Long-term Replacement Of The
Multiple Hearth Furnaces
• Continue With Ash Disposal
• Re -Evaluating These Recommendations in —5 Years
After Further Piloting is Complete & Regulatory Timing is
More Clear
• Include Placeholder in CIP for Early Implementation of
two Anaerobic Digesters (-10 years) & Related Support
Equipment
• Include Placeholder in CIP for Ultimate Implementation of
Remaining 2 Digesters & One Fluidized Bed Incinerator