November 18, 2021
TO: HONORABLE BOARD OF DIRECTORS
FROM: ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: ANNOUNCEMENTS - NOVEMBER 18, 2021
Attached are the announcements for the above meeting.
ATTACHMENTS:
1. General Manager Written Announcements
November 18, 2021 Regular Board Meeting Agenda Packet- Page 65 of 112
Page 2 of 2
Attachment 1
Board Meeting of November 18, 2021
General Manager Written Announcements
PROJECT UPDATES
1) Public Bidding of Fire Protection System, Phase 3, District Project 7373
The existing fire protection systems at the treatment plant have been installed over a
45-year period and have been added or modified on a project-to-project basis. The older
systems are becoming unreliable and difficult to maintain. This is the third phase of the
Fire Protection System Project at the wastewater treatment plant. Phase 3 includes
replacing two older standalone fire alarm systems and connecting them via fiber cabling
to the main fire alarm notification panel located in the Plant Operations Building.
This project will be advertised on November 29 and December 3, 2021. Bids are
scheduled to be opened on December 21, 2021. The Engineer's estimate is $450,000.
More information will be presented when the Board is asked to award the construction
contract on January 27, 2022, tentatively.
HUMAN RESOURCES
2) Central San Welcomes New Household Hazardous Waste Technician II
Latoya Williams
On October 25, the Household Hazardous Waste (HHW) Program welcomed
Latoya Williams as its new HHW Technician II. Latoya has worked with the HHW team for
the last six months as an HHW Technician. Prior to joining Central San, she was an
Environmental Risk and Compliance Supervisor with Nortech Waste, LLC in Roseville.
Latoya lives in the Sacramento area, loves the outdoors, traveling, and is an avid reader.
November 18, 2021 Regular Board Meeting Agenda Packet- Page 66 of 112