HomeMy WebLinkAbout08. Receive FY 2020-21 Pre-Audit Capital Improvement Budget Year-End Status Page 1 of 7
Item 8.
CENTRALSAN
jdf A- hom
CENTRAL CONTRA COSTA SANITARY DISTRICT
November 4, 2021
TO: HONORABLE BOARD OF DIRECTORS
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE FISCAL YEAR 2020-21 PRE-AUDIT CAPITAL IMPROVEMENT
BUDGET YEAR-END STATUS REPORT
The Board of Directors (Board) approves the Capital Improvement Budget (CIB) and Ten-Year Plan on a
yearly basis. At fiscal year (FY) end, staff reviews and compares the final revenues and expenditures,
based on the pre-audit financial reports, to update the Board on the progress of the Capital Improvement
Program.
A public hearing was held on June 4, 2020, after which the Board adopted the FY 2020-21 C I B. The
proposed revenue and estimated expenditures for FY 2020-21 Cl B were approximately$97,952,902 and
$88,024,000, respectively. Based on the pre-audit June 2021 financial statements, the actual revenues
and expenditures including carry-forward and budget transfers are $63,957,924 and $69,610,843, as
detailed in Attachment 1 - Pre-Audit FY 2020-21 Cl B Year-End Status Report. Attached is the
presentation that staff will review with the Board.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations, Strategy 2—Anticipate and prepare for potential regulatory
changes
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability, Strategy 2—Ensure integrity and transparency in financial
management
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
November 4, 2021 Regular Board Meeting Agenda Packet- Page 54 of 324
Page 2 of 7
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 2—Execute long-term capital renewal and
replacement program, Strategy 3—Protect personnel and assets from threats and emergencies
GOAL SEVEN:Agility and Adaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
ATTACHMENTS:
1. Pre-Audit FY 2020-21 CI B Year-End Status Report
2. Presentation
November 4, 2021 Regular Board Meeting Agenda Packet- Page 55 of 324
Page 3 of 7
Attachment 1
Pre-Audit Fiscal Year (FY) 2020-21 Capital Improvement Budget (CIB)
Year-End Status Report
Sewer Construction Fund:
Revenue
Sewer Service Charge $56,673,402 $30,156,394 -46.8%
Ad Valorem Taxes $15,940,000 $17,697,471 11.0%
Capacity Fees $6,000,000 $5,223,516 -12.9%
Pumped Zone Fees $262,000 $219,733 -24.7%
Developer Fees $484,000 $350,915 -27.5%
Interest Income $293,500 $245,740 -16.3%
City of Concord $15,300,000 $10,064,155 -34.2%
State Revolving Fund
L $3,000,000 $0
Loan Proceeds -
Total Revenue $97,952,902 $63,957,924 -34.7%
FY i
. . Budget-FY 2020-21 Y 2020.2 IL. to-Actual
Budget Budget2 Actual 11 to-Actual Forward-
Expenditures
Collection System $40,165,000 $48,807,558 $37,195,846 -7.4% -23.8%
Treatment Plant $32,334,000 $40,761,343 $18,809,902 -41.8% -53.9%
General Gene
G neral nts $3,925,000 $6,409,992 $5,305,341 35.2% -17.2%
Recycled Water $9,500,000 $11,573,639 $8,299,754 -12.6% -28.3%
Contingency' $2,100,000 $1,043,234 - - -
Total Expenditures $88,024,000 $108,595,766 $69,610,843 -20.9% -35.9%
Contingency budget is used for any CIB program, at year end the remaining balance will be a positive
variance to the sewer construction fund
2 Includes carry-forward and FY transfers
November 4, 2021 Regular Board Meeting Agenda Packet- Page 56 of 324
Page 4 of 7
ATTACHMENT 2
PRE-AUDIT FISCAL YEAR (FY) 2020-21
CAPITAL IMPROVEMENT BUDGET
YEAR-END STATUS REPORT
Board Meeting
November 4, 2021
7
Edgar J. Lopez, P.E.
Capital Projects Division Manager
AM
PRE-AUDIT FY 2020-21
REVENUE
Sewer COnstruc[ivn Fund:
I FY 2020-21 FY 2020-21
Budget Actual ='-t.)-]
NEEPWO Actual
Revenue
Sewer Service Charge $56,673,402 $30,158,394 -46.8%
Ad Valorem Taxes $15,940.000 $17,697,471 11.0%
Capacity Fees $5,000.000 $5,223,516 -12.9%
Pumped Zone Fees $262,000 $219,733 -24.7%
Developer Fees $484,000 $350,915 -27.5%
Interest Income $293,500 $245,740 -16.3%
City of Concord $15,300,000 $10,064,155 -34.2%
State Revolving Fund $
Loan Proceeds 3,000,000 $0
Total Revenue 597,952,9132 $63,957,924 -34.7%
AO Iz
1
November 4, 2021 Regular Board Meeting Agenda Packet- Page 57 of 324
Page 5 of 7
PRE-AUDIT FY 2020-21
EXPENDITURES
FY 2020-21 FY 2020-21 (Variance)
FY 20201-21 (Variance) Carry
Program Adjusted Budget-
Budget Actual Forward-
Budget to-Actual to-Actual
Expenditures
Collection System $40,165,000 $48,807,558 $37,195,846 -7.A% -23.8%
Treatment Plant $32,334,000 $40,761,343 $18,809,902 418% -53.9%
General $3,925,000 $6,409,992 $5,305,341 35.2% -17.2%
Improvements
Recycled Water $9,500,000 $11,573,639 $8,299,754 -12.6° -28.3%
Contingency' $2,100,000 $1,043,234 - - -
Total Expenditures $88,024,000 $108,595,766 $69,610,843 -20.9% -35.9%
Contingency budget transferred to Capital Improvement Budget(CIB)programs
2Includes carry-forward and FY transfers
13
MAJOR PROJECT VARIANCES (>$1 MILLION
BY PROGRAM
Collection System Program
FY
-21 FY 2020-21
Adjusted Actuals
Budget
Pump
Pump Station Upgrades- Construction ongoing and
Phase 1,District Project $16,555,800 $14,150,504 scheduled to be complete in
(DP)8436 FY 2021-22.
Funds are available in FY
Large Diameter Pipeline $1,208,700 $81,927 2021-22.Contractor hired,
Inspection,DP 8443 issues starting work.
Large Diameter Awaiting inspection results
Renovation Program, $1,500,000 $0 from DP 8443.Funding shall
DP 100007 be revised in the next CIB.
I"
Z
November 4, 2021 Regular Board Meeting Agenda Packet- Page 58 of 324
Page 6 of 7
MAJOR PROJECT VARIANCES ($1 MILLION
BY PROGRAM
Treatment Plant Program
IF Y
21 FY 2020 21
.�-Adjusted Actuals
Bid timeline extended.Project
Solids Handling Facility $4,151,000 $2,712,111 being repackaged,reduced
Improvements,DP 7348 scope,and digesters being
evaluated.
Steam and Aeration Condition assessments
Blower Systems $2,860,000 $1,488,506 complete,funds available in FY
Renovations,DP 7349 2021-22.
Treatment Plant Piping Project bid with Electric Blower
Renovations,Phase 10, $3,202,400 $619,835 Improvements,construction
DP 7369 contract awarded,and funds
are available in FY 2021-22.
Is
MAJOR PROJECT VARIANCES ($1 MILLION
BY PROGRAM
Treatment Plant Program
BudgetIFY
21 FY 2020-21
0Adjuste,
Actuals
Replacement equipment
Annual Infrastructure delayed,Uniform Public
Replacement,DP 7370 $1,765,000 $599,930 Construction Cost Accounting
Act projects pending and funds
available in FY 2021-22.
Contractor Staging Contract awarded and
Improvements,DP 7375* $3,484,000 $607,321 construction started in
FY 2021-22.
Funds for security
TP Security $1,063,000 $0 improvements.Construction
Improvements,DP 7354* contract awarded and funds are
available in FY 2021-22.
*Improvements bid together,and work started in FY 2021-22 I
6
3
November 4, 2021 Regular Board Meeting Agenda Packet- Page 59 of 324
Page 7 of 7
MAJOR PROJECT VARIANCES ($1 MILLION
BY PROGRAM
Recycled Water Program
FY
21 FY 2020-21
.�-Adjusted Actuals
Filer Plant and Clearwell Construction ongoing and funds
Improvements-Phase $10,234,000 $8,068,424 will roll over and be available in
1A,DP 7361 FY 2021-22.
I'