Item 5.b.
CENTRAL SAN
October 12, 2021
TO: ENGINEERING AND OPERATIONS COMMITTEE
FROM: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ROGER S. BAILEY, GENERAL MANAGER
SUBJECT: RECEIVE UPDATE ON MAJOR CONSTRUCTION PROJECTS WITHIN THE
FISCAL YEAR 2021-22 CAPITAL IMPROVEMENT BUDGET
Attached is a presentation on Fiscal Year 2021-22 Capital Improvement Budget projects update.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE:Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life
GOAL SIX: Innovation and Optimization
Strategy 2—Improve and modernize operations through technology and efficiency measures
GOAL SEVEN:Agility andAdaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
ATTACHMENTS:
1. Presentation
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 7 of 27
Page 2 of 10
Major Construction
Project Updates
NOS
Engineering & Operations Committee Meeting
October 12, 2021
Edgar J. Lopez, P.E.
Capital Projects Division Manager
� y
FILTER PLANT AND CLEARWELL
IMPROVEMENTS — PHASE 1A
iio ' .
• Replace Backwash Motors -,�✓,,,, ,. ����• •�_
(480V) �
• Recvc led Water Storage:
L Replace East Clearwell_
(CW)with two new
above-ground storage7!
1;.
tanks(steel or pre-
stressed concrete) h� Wcst
9�' CW
• Clearwell Overflow a }
Structure Modifications / Y _
_ 1r
• Rehabilitate one Filter 't>� c �L ••! LJL;
(#3)and Mechanical/ x
Instrumentations on others
6.tation
pgrade Chemical Feed ' " '✓ Upgrade/Replace Electrical Gear
New Recycled Pump Station
plied Water PumpElectrical Facility
(AWPS) Substation 40-2400V
• Variable Frequency Drives
(VFDs)for AWPS
I!2
CENTRALSAN
1
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 8 of 27
Page 3 of 10
FILTER PLANT AND CLEARWELL
IMPROVEMENTS — PHASE 1A
Contractor: C. Overaa & Company
Contract Price: $26,584,000
Paid to Date: $8,145,839 (August 2021)
Duration: October 13, 2020 - October 14, 2022
Work Completed: Work In Progress:
• Basin C levee raise • Substation 40
• East Clearwell demo construction
• Grading and • Steel recycled water
underground piping tanks
• Electrical and shutdown
coordination
E 3
Nib— CENTRAL SAN
FILTER PLANT AND CLEARWELL
IMPROVEMENTS — PHASE 1A
k'=
Recycled Water Tank Progress Basin C Levee
_ I'a
CIENTRALSAN
2
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 9 of 27
Page 4 of 10
PUMP STATION UPGRADES —
PHASE 1 , DISTRICT PROJECT 8436
Contractor: Mountain Cascade, Inc.
Contract Price: $25,634,551
Paid to Date: $16,940,432 (September 2021)
Duration: May 6, 2019 - December 31, 2021
Project Purpose: Address infrastructure needs,
mechanical and electrical systems, and improve
reliability for PG&E outages and resiliency at the
Moraga, Orinda Crossroads, and Flush Kleen Pumping
Stations (PS)
CENTRALSAN
� 5
MAJOR ITEMS COMPLETED AND PROGRESS AT
ORINDA CROSSROADS AND MORAGA PS
1
i
� II
Installed New Dry Weather Removed Wet Weather Installed Rebuilt Wet Weather
Pumps and Piping Pump Diesel Engines Pumps and New Piping
` 6
CENTRALSAN
3
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 10 of 27
Page 5 of 10
MAJOR ITEMS COMPLETED AND PROGRESS AT
ORINDA CROSSROADS AND MORAGA PS
I
ti
Installed New Surge Tank Installed New Grinder Installed New Surge Tank
Structure and Structure
7
CENTRALSAN
MAJOR ITEMS COMPLETED AND PROGRESS AT
ORINDA CROSSROADS AND MORAGA PS
Ij......:.; _.....
U
Installing New Main Generators Delivered New VFDs and Motor
Control Panel Control Centers(MCCs)
CENTRALSAN
' s
4
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 11 of 27
Page 6 of 10
COLLECTION SYSTEM -
SEWER RENOVATION PROJECTS
Sewer Renovation Projects:
• Walnut Creek, Phase 14— 9,840 feet of sewers (100%
complete)
• Martinez, Phase 6— 10,685 feet of sewers (100% complete)
• Lafayette, Phase 14 — 12,745 feet of sewers (100% complete)
• South Orinda, Phase 8 — 5,100 feet of sewers (95% complete)
• Walnut Creek, Phase 15— 9,500 feet of sewers (20% complete)
• North Orinda, Phase 8 —9,900 feet of sewers (Notice to
Proceed October 4, 2021)
9
CENTRALSAN
SOUTH ORINDA, PHASE 8
CENTRALSAN
s
T -
5
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 12 of 27
Page 7 of 10
PACHECO BOULEVARD SEWER REPLACEMENT
x
CENTRAL SAN
INFLUENT PUMP ELECTRICAL IMPROVEMENTS
Contractor:Auburn Constructors, LLC
Contract Price: $6,497,300
Paid to Date: $2,876,472 (August 2021)
Duration: October 5, 2020 - October 28, 2022
Project Purpose: Address end of life electrical components
and improve reliability at Headworks
Work Completed:
• Replaced three MCCs
• Replaced three programmable logic controller drop
panels
• Replaced VFDs No. 1 and No. 2
• Refurbished Influent Pump Motors No. 1 and No. 2
• Installed new walkways, gates, and ventilation/odor
control for Wet Well No. 1
I112
CIENTRALSAN
6
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 13 of 27
Page 8 of 10
INFLUENT PUMP ELECTRICAL IMPROVEMENTS
MAJOR ITEMS COMPLETED OR IN PROGRESS
h -
■
New VFD No.1 Installed
Inside New VFD No.1 during Installation
13
CENTRAILSAN
INFLUENT PUMP ELECTRICAL IMPROVEMENTS
MAJOR ITEMS COMPLETED OR IN PROGRESS
Installation of Refurbished Influent Pump Motor No.2 Mounting Motor Term Box on Pump No.2
' 1a
CENTRALSAN
7
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 14 of 27
Page 9 of 10
INFLUENT PUMP ELECTRICAL IMPROVEMENTS
MAJOR ITEMS COMPLETED OR IN PROGRESS
Aim
vx �
Wet Well No.1:Scaffolding Work Platform,Walkway Beams,Ventilation X-Rays for Rebar to Install Anchors and Conduits
' 15
CENTRALSAN
INFLUENT PUMP ELECTRICAL IMPROVEMENTS
MAJOR ITEMS COMPLETED OR IN PROGRESS
Wet Well No.1 Filled For Testing
i
Wet Well No. 1:New Walkways and Gates
CENTRALSAN
8
October 12, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 15 of 27
Page 10 of 10
ELECTRIC BLOWER IMPROVEMENTS AND
TREATMENT PLANT PIPING RENOVATIONS,
PHASE 10
Contractor: Auburn Constructors, LLC
Contract Price: $9,594,300
Duration: September 13, 2021 - November 1, 2022
Project Purpose: Provide full capacity and improved
reliability to the aeration air system at the treatment
plant; to address other piping and electrical needs
Work Completed:
• Executed Contract
• Submittal Review .,
• Mobilizing Soon
1
�7
CENTRAL SAN
9