HomeMy WebLinkAbout15. Award a construction contract and consultant agreements for Solids Handling Facility Improvements, DP 7348 Page 1 of 26
Item 15.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: SEPTEMBER 2, 2021
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $179,841,000
TO KIEWIT INFRASTRUCTURE WEST CO., THE LOWEST RESPONSIVE
AND RESPONSIBLE BIDDER FOR THE SOLIDS HANDLING FACILITY
IMPROVEMENTS, DISTRICT PROJECT 7348; AND
• AUTHORIZE STAFF TO ENTER INTO CONTRACTUAL AGREEMENTS
WITH THIRD-PARTY CONSULTANTS TO CONDUCT INDEPENDENT
ASSESSMENTS OF SOLIDS HANDLING ALTERNATIVES;
• AUTHORIZE THE GENERAL MANAGER TO:
• EXECUTE FIVE PROFESSIONAL SERVICES AGREEMENTS
WITH NOT TO EXCEED AMOUNTS AS NOTED FOR
CONSTRUCTION MANAGEMENTAND ENGINEERING SUPPORT
DURING CONSTRUCTION WITH: 1) MWH CONSTRUCTORS,
INC. FOR $12 MILLION; 2) BLACK & VEATCH CORPORATION
FOR $4 MILLION; 3)ARCSINE ENGINEERING FOR $1.5
MILLION; 4) HDR, INC. FOR $1 MILLION; AND 5) DEGENKOLB
ENGINEERS FOR $650,000; AND
• EXECUTE CONTRACT DOCUMENTS SUBJECT TO SRF
FUNDING, SUBMITTAL REQUIREMENTS, VALUE
ENGINEERING, AND INCLUDE UP TO A 15-PERCENT PROJECT
CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
NATHAN HODGES, SENIOR ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
September 2, 2021 Regular Board Meeting Agenda Packet- Page 128 of 199
Page 2 of 26
ISSUE
On June 16, 2021, three sealed bids were received and opened for the construction of the Solids
Handling Facility Improvements, District Project(DP) 7348 (Solids Project). The Board of Directors
(Board) must award the contract or reject all bids within 120 calendar days or by October 14, 2021.
Authorization is also required to execute agreements or amendments greater than $200,000.
BACKGROUND
The Comprehensive Wastewater Master Plan (CWMP)finalized in 2017 identified many improvements to
the solids and energy unit processes associated with the treatment plant(plant). The following approach
for short-term and long-term improvements were outlined in the CWMP:
The Fiscal Year(FY)2021-22 Ten-Year Capital Improvement Plan (CI P) includes:
• Solids Handling Facility Improvements, DP 7348 (Solids Project): $183.9 M.
• Steam Aeration & Blower Systems Renovations, DP 7349: $35.4 M.
• Multiple Hearth Furnaces (MHFs) Replacement, DP 100009: $1 M.
• Cogeneration (Co-Gen) Replacement (starting FY 2023-24): $25.1 M.
• Other Solids Facility Improvements— Dissolved Air Flotation Thickener(DAFT) Tanks (starting FY
2028-29): $2.4 M
The Long-term Planning Improvements (20-year), in present dollars, include:
• Solids Handling, Phase 2:Add two anaerobic digesters and convert to biogas Co-Gen and consider
adding high strength waste to increase "green" gas production at$126.8 M.
• Solids Handling, Phase 3:Add two additional anaerobic digesters and replace the MHFs with
fluidized bed incinerator at$175.4 M.
The Solids Project was introduced to the CI P in FY 2017-18 to consolidate several projects already
identified in the Treatment Plant Program since 2010. The project elements are all related to solids
processing and handling within or around the Solids Conditioning Building (SCB). When the Solids Project
was initiated, a detailed condition assessment was conducted, and new air pollution control equipment(wet
scrubber)was pilot tested to confirm the design parameters. Critical equipment such as the centrifuges,
cake pumps, and wet scrubbers were pre-selected and designed. Staff also coordinated with regulatory
agencies, developed construction constraints, applied for a State Revolving Fund (SRF) loan, prequalified
contractors, bid the project, and received bids on June 16, 2021.
The following major elements are included in the Solids Project:
• Replacement of the two wet scrubber systems with new air pollution control equipment to meet air
regulations, including a new Venturi scrubber capable of handling waste heat bypass events.
• Replacement and upgrades to sludge blending, storage, and mixing systems.
• Replacement of the centrifuges and cake pumps.
• Incinerator burner upgrades and new after-burners including modern controls.
• Addition of a new Ash Handling Facility to modernize the conveyance and improve loading to reduce
fugitive ash emissions and increase reliability.
• Construction of major seismic modifications to the SCB and to the two existing incinerators to meet
the current seismic standards.
• Addition of a new electrical room and replacement of major electrical, instrumentation, and controls
(E I&C)to accommodate the new systems and integrate with the remaining systems not in the Solids
Project.
• Requirement of significant constraints, including restrictions to shut down the incinerators, install
temporary electrical facilities, and the off-haul and disposal of sludge.
September 2, 2021 Regular Board Meeting Agenda Packet- Page 129 of 199
Page 3 of 26
• Demolition of the abandoned digester tank near the SCB. (Completed)
• Construction of the SCB emergency stairway for the third-floor control room for safety egress.
(Completed)
• Construction modifications to the Emergency Sludge Loadout Facility(ESLF)to reliably operate and
load sludge for extended durations. (Completed)
A site location map is provided as Attachment 1.
The Solids Project is the largest single renovation project that Central San has undertaken since the plant
was expanded in the 1970's. As with all large or critical projects, staff has been updating the Board through
Committee and Board meetings throughout the process. Since 2017, staff has discussed and received
authorization from the Board on several occasions as outlined in Attachment 2.
Bid Schedule: The Solids Project was advertised on February 22 and March 1, 2021. The original bid
opening date,April 28, 2021, was extended on multiple occasions and was changed to June 16, 2021 due
to requests from bidders and scope clarifications by addenda. Nine addenda were issued during the bid
period. Staff facilitated over 20 bidder site visits and answered over 300 bid questions. The project
documents, bid forms, and security included a 120-calendar day period in which bids cannot be withdrawn
to accommodate for the SRF review, which is common practice for large SRF-financed projects.
Bid Opening and Evaluation: On June 16, 2021, three bids were received and publicly opened, that
ranged from $179,841,000 to $216,293,989.A summary of bids is shown in Attachment 3.
The Engineer's estimate for construction was originally listed at$110 M when first advertised, and later
amended up to $140 M to reflect changes in the evolving bid market and elements included in addenda.
Capital Projects staff conducted a technical and commercial review of the bids and determined that Kiewit
Infrastructure West Co. (Kiewit) is the lowest responsible and responsive bidder with a bid amount of
$179,841,000. During the bid evaluation, staff found one minor discrepancy, which was clarified by Kiewit.
The discrepancy was that Kiewit did not correctly list the name of the packaged electrical systems (motor
control centers and variable frequency drives) as required by the specifications. This discrepancy is
considered non-material by staff since it was clarified and met the specifications.
The lowest bid is approximately$40 M above Central San's construction estimate. Staff's bid review
included meetings with the three bidding general contractors, MW H Constructors, I nc. (MW H), and
several other consultants.After discussions with the three bidders, it became clear that the cost of
materials, vendors, and subcontractors were significantly higher than the estimate, which is the main factor
for receiving higher pricing. The increases were due to uncertainty in local, U.S., and global market
conditions engendered by the COVI D-19 pandemic. This was further compounded by several risk
elements associated with the project, including vendor ability to receive materials or equipment on time to
meet the milestones and timelines identified in the contract documents or the inability to receive
guaranteed pricing for items that were already in high demand or becoming unavailable. These
uncertainties and risks increased costs as suppliers or subcontractors attempted to predict the future
pricing for commodities required for the contract.
During the bid period, the Solids Project team evaluated the COVI D-19 impact and supply chain issues or
delayed deliveries might have on the final bid price, including the rapidly escalating commodity pricing. For
these reasons, staff raised the construction estimate from $110 M to a maximum of$140 M to
accommodate material prices and reflect the changes in the electrical scope made via addenda. More
recent, staff in the Treatment Plant Program are starting to report delays in major equipment, such as
electrical, and significant cost escalation requests for steel or copper.
It should be noted that staff had not seen or experienced significant cost escalation in past construction
September 2, 2021 Regular Board Meeting Agenda Packet- Page 130 of 199
Page 4 of 26
projects during COVI D-19. The Board has awarded thirteen construction contracts since the pandemic
first started in March 2020, in which only one project came over the Engineer's estimate. The Solids
Project involves major upgrades and renovations to a one-of-a-kind industrial four-story facility, the center
for Central San's solids handling, disposal, and energy production. There is no other similar facility in the
western U.S., the closest being in the Midwest or found on the East Coast.
Furthermore, even though the team spent considerable time during the design evaluating shutting down the
SCB to facilitate and shorten construction, it became apparent that it would have been logistically and
economically impractical. One outcome was to consider shutting down the MHFs for 12 months and up to
18 months. Another significant challenge is associated with the El&C systems for the existing systems to
remain in the project. The El&C challenges have been throughout the design and continue even after the
bid to be a major effort as Central San does not have complete or accurate wiring records for all systems.
Although not yet defined in terms of costs, this has contributed to higher electrical pricing and fewer
interested electrical subcontractors.
I n October 2020, staff pre-qualified seven general contractors (GCs) and eight electrical subcontractors
(ECs). During the bidding period, staff was informed that four GCs and six ECs would not be participating
in the bid. Feedback for not bidding was based on the cost or the duration of the project, or due to pursuit
of easier and smaller projects. The project duration is 1,460 days. Many bidders and potential bidders
considered this duration as added risk. Staff's assessment is that the complexity of the Solids Project
made it especially challenging for bidding since the project is not a typical public works, low bid job.
Therefore, the limited competition contributed to the higher costs received at bid time.
Only three GCs and two ECs provided bid prices. Mass Electric Construction Co., a Kiewit Corporation
subsidiary, provided a labor quote only to Kiewit. The other EC, Blocka Construction, I nc., provided pricing
of over$58 M to the other two GCs. Kiewit did have better pricing from their electrical subcontractor and
plans to purchase all electrical materials and equipment, which was a significant reason for the difference
between Kiewit's bid and the two other bidders.
Central San is the only public agency in California still operating sewage incinerators. The incinerator work
is specialized and there was only a single subcontractor that provided pricing. The Solids Project scope
included 12 months of temporary sludge operations, including pumping, dewatering, odor control,
conveyance, hauling, and disposal.Additional unit pricing was included for up to six months of temporary
operations. Pricing received for the entire 18-month scope ranged between $15.1 M and $34.53 M, which
is significant. This price range indicates the wide variability in the bid item and the cost impact and the
difference between the bids.
Finally, the overall operations and construction risks influenced pricing. Many risks have been identified,
including the milestones and constraints, project duration, combined with challenging elements such as
deferred design, electrical being a critical path, and timely receipt of materials and equipment resulted in
contractors adding more value than taking on more risk than the Engineer anticipated.
Construction Support: Staff will administer and have overall control of the construction and interaction
with plant staff, engineering consultants, and safety for Central San employees. MW H will be the
construction manager(CM) providing frontline or day-to-day management with the contractor, including
general inspection, special inspections, coordination of construction activities, startup and commissioning
services, recommending payments, schedule and cost review, file management, and various other support
duties required to effectively manage the complexities of the Solids Project. MW H had been previously
selected through a formal public solicitation and has been assisting staff with review of the bid documents,
schedule analysis, and cost estimating. Staff negotiated the CM scope with MWH with a cost ceiling of
$12.0 M. New agreements are proposed for all the Solids Project supporting consultants due to Central
San's updated terms, insurance changes, and for the new enterprise resource planning (ERP)
system. MW H's current agreement is valued at$1.1 M. If the CM services are fully utilized, the total fee
September 2, 2021 Regular Board Meeting Agenda Packet- Page 131 of 199
Page 5 of 26
anticipated for MWH is $13.1 M.
Black& Veatch Corporation (B&V), and sub-consultants HDR, Inc. (HDR) and Degenkolb Engineers
(Degenkolb) are the Solids Project designers. These firms were selected and hired under two solicitations
that consisted of planning and detailed design.All three firms will provide engineering support during
construction (ESDC) services. Staff is recommending a pay for performance fee structure with B&V
based on previous experiences. The ESDC services will be on an as-needed basis with a not to exceed
cost ceiling of$4.0 M. The current agreement amount is approximately$9.6 M and will be closed. The
total fees expected for B&V including the design agreement and for ESDC is expected to reach $13.6 M.
HDR will provide structural and architectural ESDC services at a cost up to $1.0 M, while Degenkolb will
provide seismic ESDC services for an amount not to exceed $650,000. Staff has elected to enter into
agreements directly with each sub-consultant to better support the construction effort directly with Central
San and MWH.
During the bid phase, staff utilized Aresine Engineering (Aresine)to prepare additional drawings and
specifications for the installation of temporary electrical and control systems related to existing systems
that were not addressed by B&V's design. Staff intends to continue using Aresine due to their expertise
and understanding of Central San's standards and existing electrical systems. The anticipated budget for
the electrical services is estimated at$1.5 M and will be performed on an as-needed basis. Electrical is
one of the most critical and complex elements to the success of the Solids Project and has been the most
difficult trade to find experienced and qualified, local personnel to help staff or to hire.Additional electrical
and field support to supplement or assist staff will be presented for approval at a future time.
Hazardous materials testing and related services are essential for a safe worksite and project. Existing
building materials have lead paint or primers, asbestos, and a significant amount of concrete demolition will
take place inside the SCB.Additionally, excavation for exterior shear walls and installation of drilled piles
are expected to encounter contaminated soil. Staff is in the process of selecting a consultant to provide
hazardous material support for the project. The costs for these services is expected to reach $1.0 M;
Board approval will be requested at a future time.
Staff has also identified the need to include additional professional engineering services for third-party
review, quality assurance and quality control (QA/QC), cost reduction alternatives, and recommendations
that can assist in a cost-effective project and avoid schedule impacts. The scope of services will focus on
industrial mechanical and electrical, incinerator retrofits, installation of new air pollution control equipment,
ash handling, and other elements or consulting work. A Request for Qualifications (RFQ) has been publicly
advertised and staff anticipates a budget of$2.5 M for the additional services. The RFQ includes the
ability to hire multiple firms, if needed; therefore, staff will return to the Board once the RFQ process is
finalized and fees have been negotiated.
California Environmental Quality Act(CEQA)
At its December 6, 2018 meeting, the Board independently found that the Solids Project is exempt from
CEQA under Central San's CEQA Guidelines Section 15301, since it involves minor alterations to
existing public facilities involving no expansion of use, and CEQA Guidelines Section 15302, since it
involves replacement of existing public facilities at the same location and with the same purpose.
ALTERNATIVES/CONSIDERATIONS
CONSIDERATIONS: The following factors were considered by staff as several of the project alternatives
are evaluated. As stated above, three sealed bids were received and opened for the construction of the
Solids Project.At the next Board meeting on September 2, 2021, the Board will need to either award the
contract or reject all bids within 120 calendar days or by October 14, 2021.Authorization will also be
September 2, 2021 Regular Board Meeting Agenda Packet- Page 132 of 199
Page 6 of 26
requested from the Board to execute both new agreements and amendment for the several construction
management and consulting engineering firms that will be required for this four-year construction project.
Time - Rejecting all bids, proceeding with a project redesign, and rebidding the project is anticipated to
result in as much as a 12-month delay to the start of construction. I n addition, delaying the project will also
impact Operations and delay the installation of new equipment and facilities, such as the new scrubbers
and centrifuges. Most of the equipment being replaced under this project is beyond its useful life and in
need of replacement. Kiewit is a very qualified and experienced general contractor. They are planning to
self-perform a lot of the project scope.
Costs - Repackaging and rebidding the project (or project phases) may not reduce total project costs or
could possibly result in increased costs.An important consideration is that repackaging the project is
primarily intended to reduce the exposure to risks such as delay claims during construction.Any cost
savings that might be developed as part of a redesign may likely be offset by other factors like inflation or
continued supply issues.
Air Permit Compliance - The existing MHFs air pollution controls are having difficulty achieving air permit
compliance.A priority will be to address these regulatory issues in an efficient manner. Since Clean AirAct
Section 129 regulations (129 rule)went into effect in March 2016, the Bay Area Air Quality Management
District(BAAQMD) has issued to Central San several notices of violations (NOVs) related to the
emergency bypass damper openings. Staff has been able to reduce the frequency of bypass events, but
because of inherent limitations of the existing equipment, the bypass damper continues to periodically
open, in violation of the 129 rule. The MHFs also cannot consistently meet the hydrochloric acid (HCI)
emission limit in the 129 rule. Staff has been working closely with the United States Environmental
Protection Agency(USEPA)to address these compliance challenges. Local regulation will also impact
compliance. Data from an on-site pilot study conducted in 2018 indicated the new MHF air pollution control
devices will significantly reduce the frequency of emergency bypass damper openings and reduce HCI
and particulate matter(PM) emissions below their respective limits. BAAQMD Rule 6-1, which goes into
effect in 2025, lowers the PM concentration limit on the MHFs, and the existing air pollution control devices
are not sufficient to ensure compliance. Staff with a specialty consultant, GHD, is currently doing pre-
design for future devices to reduce PM and carbon oxide (CO)to the new standards. This would require
the addition of the wet electrostatic precipitators (W ESP)to meet PM 2.5 and adding a "zero" hearth on
top of the MHFs to meet the lower CO limits.
SCB Shutdowns - Shutting down most SCB processes, including temporary dewatering and hauling of
sludge, will likely remain part of the scope of work; however, it may be significantly reduced if the project is
repackaged or phased, as this turn out to be an expensive proposition.
ALTERNATIVES: Staff evaluated several alternatives and options for solids handling and energy starting
with the CW MP, during the predesign, design, bidding, and most recently following the bid opening prior to
award. Three alternative paths are being considered and are described below and were further discussed
during the August 26, 2021 Board workshop.
Alternative 1: Award the Contract
Staff recommends awarding the Solids Project to Kiewit, since Central San has a final design for the
project, a qualified, experienced contractor ready and able to start construction of this complex project, and
is expecting to receive the final draft agreement from the State of California Clean Water SRF Funding for
a $173.1 M low interest loan. However, a multistep Notice to Proceed (NTP) path is being recommended
since the construction contract is significantly over budget. Once awarded, staff and Kiewit will conduct a
detailed analysis of the project sequencing, milestones, and evaluate other ways to reduce risks and
potential costs for the project. This will include cost reduction value engineering (VE)with design
assistance from Kiewit. The VE is expected to take four months to complete and is recommended since
Central San has not executed the final SRF Agreement and needs up to $77.5 M to fund the total
September 2, 2021 Regular Board Meeting Agenda Packet- Page 133 of 199
Page 7 of 26
estimated project cost. Staff has met with Kiewit and discussed the timing of funding, using provisions
within the contract documents to initiate the contract, and possibly use the termination clause if there is not
adequate funding or issues are discovered during the findings of the VE. An initial NTP would be issued to
conduct a review as stated above and of such items as deferred design components (temporary seismic
shoring and electrical), sludge hauling, and the detailed schedule of values for the contract. Kiewit has
several in-house resources and experienced leadership in building industrial and complicated construction
like the Solids Project within their local Fairfield office.
A second NTP for construction will not be issued until Central San and Kiewit are comfortable and staff will
update the Board and request authorization prior to moving forward. In the event a NTP is not issued, the
contract will be terminated by Central San. Accordingly, Central San would be required to pay the cost
incurred by Kiewit for the agreed amounts and rates for the VE process only.
Staff explored the option of extending the time for award beyond the bonded 120 calendar days. This
option was not pursued since Kiewit would be beyond the guaranteed pricing with all their vendors,
suppliers, and subcontractors and likely result in additional costs.
Alternative 2: Reject Bids
The Board may elect to reject bids, which would result in staff having to regroup to determine the best
solution moving forward. Several options exist; however, staff would have to continue evaluating and report
back to the Board if one of the following options were selected.
Alternative 2(a) Rebid the Solids Project: Staff would conform all the addenda with the contract
documents, evaluate and incorporate more ways to reduce risks, and rebid within six to nine months. This
option may mitigate some effects of the current market; however, other costs may increase which cannot
be foreseen. Without significant changes to the scope of work, staff expects that the bidders may not
participate in a re-bid. If this option is pursued, staff would remove the pre-qualification for contractors to
get more interest. This is not recommended.
Alternative 2(b) Rebid Solids Project within Approved Budget: Staff could repackage the project and
rebid some of the project elements to stay within the current authorized budget of $183.9 M. This would
require removing and delaying some of the scope to fit the budget and add future project(s)to complete
the remainder of the scope. This is not recommended.
Alternative 2(c) Consider Design-Build Project Delivery: Staff could evaluate a design-build delivery
method. Under this approach, staff would be using the existing Solids Project's bid package as a basis.
This would allow a contractor with a designer to work together to optimize the Solids Project while starting
construction on critical path elements. Additional time would be required to prepare the front ends and
specifications for alternate construction delivery and put the responsibility of the changes of the design and
sequence onto the contractor to resolve. A design-build approach would likely attract more bidders than
rebidding the Solids Project under option 2(a) as several design-build contractors were interested and did
not participate during the pre-qualification process. However, staff expects that the bid price would
increase compared to the Kiewit bid. The only advantage for this option would be that the design-build cost
would be considered a maximum price while the contractor works to stay within the bid. This is not
recommended.
Alternative 2(d) Perform the Solids Project in Multiple Phases: Staff could separate and implement
the Solids Project scope into multiple phases. This would include repackaging the work in various smaller
projects which could be implemented in either two or up to six phases. The first phase(s) could prioritize
the new wet scrubbers, followed by the new electrical room, seismic utility relocations, centrifuges and
cake pumps, and low impact seismic renovations within the building. The subsequent phase(s)would
continue seismic work, followed by sludge blending tanks, and a new ash facility. Final phase(s) may
complete seismic work, complete electrical demolition, and finish some remaining project elements. One
September 2, 2021 Regular Board Meeting Agenda Packet- Page 134 of 199
Page 8 of 26
advantage with multiple project phases is that by reducing the scope of work and duration on each phase,
Central San likely has less exposure to cumulative delay change order claims and risks during
construction. Central San would also incorporate the lessons learned and construction challenges into the
future phases. Disadvantages with this option is increasing the overall Solids Project duration and
extending the timeline before new equipment is placed into service.As for costs, staff believes that
multiple phases or smaller projects will increase the bidder competition thus likely will lower the
construction costs. However, the engineering costs and staff time to support a longer duration and multiple
contracts, and inflation may offset some of the potential savings. While this Alternative 2(d) is technically
feasible, there is no guarantee that the overall costs will be lower since staff estimates that an additional
three to four years would be needed to complete all the scope identified in the Solids Project. This
alternative could be further considered if other alternatives are not pursued.
Alternative 3: Evaluate an Alternative Long-term Solids Handling Approach including Anaerobic
Digestions
Alternative 3(a) Evaluate an Alternative Long-term Solids Handling Approach including
Anaerobic Digestions with all new Solids Facilities: Before issuing a final NTP for the Solids Project
construction, staff will reconsider and evaluate the long-term solids handling based on furnaces, ash
disposal and steam recovery to include or change to anaerobic digestions. This alternative could change
the design and construction of the solids and energy facilities such as anaerobic digestions including new
biogas cogeneration. This would include new facilities located north of the emergency sludge loading
facility. The current SCB and MHFs could continue to operate as the sludge disposal method in the
interim. Followed by ultimately, the abandonment of the SCB, MHF, steam, auxiliary boilers, and existing
Co-Gen. This alternative could be delivered as atypical design-bid-build or design-build project. Biosolids
disposal would be addressed either by continuing to use the existing MHFs for ten years or so, or using
the newly renovated sludge loading building, or adding sludge dryers and pyrolizer. The project could also
be phased, with phase one focusing on adding two new anaerobic digesters, followed by a phase for new
biogas Co-Gen, and another phase adding two additional digesters and biosolids handling. Time would be
required to select a new consultant team, prepare designs and specifications. This alternative, if fully
implemented, would greatly simplify and modernize Central San's solids handling and energy facilities.
This approach would likely attract more bidders than rebidding the Solids Project. The project could be
constructed and not require the complex sequencing and temporary work required for the Solids Project.
This would reduce risks and would be designed and constructed within the same time frame, four to five
years. However, this would be a radical shift in Central San's process and would need to be carefully
vetted and evaluated. Overall cost of this alternative may not be significantly less than the current approach
but should be evaluated based on the bids received for the Solids Project. It would, however, reduce many
risks associated with the current path. The main risk associated with this alternative is the biosolids
disposal and the potential future per- and polyfluoroalkyl substances (PFAS) regulations associated with
biosolids disposal. While staff does not recommend rejecting all bids, staff recommends pursuing a three
to four-month evaluation of this Alternative 3(a) in more detail and compare the results with Alternative 1.
This effort is planned to have the same timeline as Alternative 1 (90-120 days) so the two alternatives can
be compared before making a long-term decision. This effort will be conducted by third-party engineering
consultant firms.
Alternative 3(b) Evaluate an Alternative Long-term Solids Handling Approach including
Anaerobic Digestions with using a Private-Public-Partnership (P3) delivery for all new Solids
Facilities: Currently,Anaergia has a lease option on about nine acres located on the Kiewit property to
evaluate the feasibility of design-build-construct a private solid handling and biogas production facility
consisting of anaerobic digesters, high strength waste receiving station, and pyrolysis. This evaluation
could also include an option to build these same facilities north of the emergency loading facility under a
P3.As with the other alternatives listed above, before issuing a final NTP for construction of the Solids
Project, staff suggest reconsidering and evaluating the long-term solids handling operations. The current
SCB and MHFs would be decommissioned under this Alternative 3(b). Staff could operate some or all
September 2, 2021 Regular Board Meeting Agenda Packet- Page 135 of 199
Page 9 of 26
these facilities. The sludge disposal method would be pyrolysis producing a chart (like ash). Biosolids
disposal initially based on tipping fees with the ability for Central San to buy out these facilities either in 20-
years or sooner. This would require time to select a P3 concessionaire and to select a consultant team for
technical, finance, and legal support. Also, continuing to purse on parallel schedule to other alternatives
over the next three to four-month evaluation of this Alternative 3(b) in more detail and compare to
Alternative 1.
FINANCIAL IMPACTS
The total estimated project cost is $261,373,000 which includes all prebid expenditures, design, bidding,
bid price, CM, consultant costs, staff time, and contingency as detailed in Attachment 4. A detailed
financial analysis with alternatives was presented at the August 26, 2021 Board workshop. The current
budget for the Solids Project is shown on page 236 in the FY 2021-22 District Budget at$183,894,000.
The total estimated project cost includes up to 15-percent Contingency or$27 M. At this time, staff is
holding a high contingency until the project can be evaluated under the VE.
The 15% Contingency, or$27 M, includes the following:
• 5% or$9 M for standard allowance for change orders (COs).
• 5% or$9 M due to major renovations and project complexity.
• 5% or$9 M for regulatory changes based on: Maximum Achievable Control Technology (MACT)
50% rule ($5 M)to add WESP and zero hearth for carbon oxide. Additional staffing costs due to
COs and MACT 50% rule or engineering costs to support the project ($4 M).
Staff will re-evaluate the Contingency required prior to issuing the second NTP to Kiewit and request
authorization if the project proceeds into construction.
State of California Clean Water Revolving Fund (SRF)
Central San has applied and requested a total of $173.1 M in funding from SRF and received approval. In
December 2020, prior to advertising the Solids Project, staff submitted updated Solids Project
documents in support of receiving the initial agreement. The Water Board informed staff in March 2021
that the initial agreement would be routed for Division of Financial Assistance (DFA) approvals, after which
it would be sent to Central San for execution within the next several months. This initial agreement is
currently being routed for Water Board officials' signatures and is expected to be issued to Central San
within several weeks. Staff has recently spoken with the Water Board concerning the higher bids that was
received and the need for additional funding. After the initial agreement is executed, the final project
amount and supporting documents need to be submitted and will provide an opportunity for the Water
Board to request additional funding for the budget gap that is necessary.
Also, the Water Board indicated that if the Solids Project is rejected and split into more than two project
phases, then it would be challenging to win approval for additional funding. Staff will consider SRF and
other funding options as alternatives are evaluated. These were presented at the August 26, 2021 Board
workshop for the Solids Project.
Project Financing Approach
As stated above, the total budget cost for the project listed for FY 2021-22 Budget is $183.9 M for the
project. Staff has applied and is expected to receive the agreement from SRF for a loan of$173.1 M. The
latest total estimated Project Cost is $261,373,000. The variance between the FY 2021-22 Budget of
$183.9 M and the latest estimated project cost of $261,373,000 is a gap of approximately$77.5 M.
Proposed Financing of Project Gap
Staff brought the Solids Project contract approval to the August 17, 2021 Engineering & Operations
(E&O) Committee for discussion at the August 26, 2021 Board workshop, and then for potential approval
by the Board in September 2021. The need, merits, and technical approach of the project were subject to
September 2, 2021 Regular Board Meeting Agenda Packet- Page 136 of 199
Page 10 of 26
discussion at the August 17, 2021 E&O Committee. The matter of the funding approach for the Solids
Project, considering higher than anticipated costs, was discussed at the August 26, 2021 Board workshop.
With the receipt of bids for the Solids Project, the overall cost of the project has been increased by$77.5
M. Recognizing that there are multiple approaches to addressing this funding gap, staff has explored and
is recommending a multi-faceted approach, including $25 M ($5 M per year for 5 consecutive years) in
reductions from other planned projects in the Ten-Year Cl P, approximately$2.5 M in savings based on
updated financials and the balance coming from increased use of debt financing. While the funding
shortfall would affect the latter years of the project (3-4 years from now), it would be possible to proceed
with the Solids Project without immediately addressing this funding need, but staff recognizes that it is
preferable to have a planning funding approach before proceeding with contract award. It should also be
noted that the contract award to the recommended contractor has notable "off ramps" language in the
specifications, including a VE phase after which Central San can elect not to proceed for convenience,
after reimbursing the contractor for their time to conduct the VE phase only.
Staff has identified several of possible financing options approaches to eliminate the $77.5 M funding gap.
The updated financial assumptions provide approximately$2.5 M in cash funding. To reduce the funding
gap, a $25 M cut to the Capital Program for all scenarios, is proposed consisting of five years of$5 M per
year. The proposed reductions are as follows: $3 M from Collection System Sewer Renovation; $0.5 M
from Vehicle Replacement Program; and $1.5 M from Contingency. The funding approaches for the
remaining $50 M necessary for funding are summarized below.
Financial Plan Scenarios
The preferred approaches presented and discussed at the August 26, 2021 Board Workshop are listed
below:
Funding Option 1 -SRF Funding: Request additional SRF funds. Based on an update of the financial
plan, a total of$50 M of additional SRF borrowing would be required. This could be accommodated
without an increase in the scheduled rate increases foreseen prior to the SRF project cost increase.
Funding Option 2 - Issue Bonds: (certificates of participation)within 12 months. Bonds could be issued
to fund FY 2022-23 Capital Expenditures, freeing up cash that could be set aside for the Solids Project
funding gap 3-4 years from now(in FY 2024-25 and FY 2025-26). Based on an update of the financial
plan, a total of$53 M of additional bond borrowing would be required.
Funding Option 3 - Future Issuance of Bonds: Under this option, a bond issuance for Solids Project
funding would be needed in 3-4 years from now. This would require issuance of about$62 M of bonds
when funding was needed for FY 2024-25 through project completion in FY 2025-26 due. Under this
option, we are assuming higher interest rates.
The following funding options were not recommended.
Funding Option 4 - Explore Other Funding Sources: Staff has been monitoring the availability of
funding from federal sources, including potentially in the pending $1 trillion infrastructure bill, or through the
pre-existing Water I nfrastructure Finance and I nnovation Act (W I F IA). As to the latter, an assessment of
the W I FIA program in 2018 led staff to conclude that the program did not hold value to Central San. Staff
has inquired with our financial consultant PFM to determine whether the program has changed since then
to make it more attractive.
Funding Option 5 - Cash Funding: If no additional borrowing was available or viewed as acceptable, an
increase in rates above those previously projected would be necessary to fund the increased costs.
Funding Option 6: Defer an additional $50 M in the CI P over the next ten years.
September 2, 2021 Regular Board Meeting Agenda Packet- Page 137 of 199
Page 11 of 26
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its August 17, 2021 meeting. Staff did
not anticipate a recommendation as further discussion was held with the Board of Directors on August 26,
2021 at a special workshop.
RECOMMENDED BOARD ACTION
Staff recommends the following Board actions:
(A) Award a construction contract in the amount of$179,841,000 to Kiewit Infrastructure West Co., the
lowest responsive and responsible bidder for the Solids Handling Facility Improvements, District Project
7348;
(B) Authorize staff to enter into contractual agreements with third-party consultants to conduct independent
assessments of Solids Handling Alternatives;
(C) Authorize the General Manager to execute the following five new professional services agreements
with:
1. MW H Constructors, I nc. in an amount not to exceed $12.0 million for construction management
services.
2. Black& Veatch Corporation in an amount not to exceed $4.0 million for engineering support
during construction.
3. Aresine Engineering in an amount not to exceed $1.5 million for electrical engineering support.
4. HDR, I nc. in an amount not to exceed $1 million for architectural and structural engineering
support; and
5. Degenkolb Engineers in an amount not to exceed $650,000 for seismic engineering support.
(D) Authorize the General Manager to execute Contract Documents subject to SRF funding, submittal
requirements, value engineering, and include up to a 15-percent project contingency.
Strategic Plan re-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations, Strategy 4- Reduce reliance on non-renewable energy
GOAL THREE: Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
GOAL FIVE: Infrastructure Reliability
Strategy 1—Manage assets optimally to prolong their useful life, Strategy 2—Execute long-term capital renewal and
replacement program
September 2, 2021 Regular Board Meeting Agenda Packet- Page 138 of 199
Page 12 of 26
ATTACHMENTS:
1. Project Location Map
2. Prior Board Actions Summary
3. Summary of Bids
4. Post Bid / Preconstruction Estimate
5. Presentation
September 2, 2021 Regular Board Meeting Agenda Packet- Page 139 of 199
Page 13 of 26
o �
CD
O
r-p. CLEARWELL
BASIN
a CP pQ
0 NORTH
10 BASIN
3 C31.t E�3 o °
3:3w �V1�0�'
• ,I FILTER p DRAIN BACK
PLANT CHANNEL
N
Q
0
0 400 800
FEET
a PROJECT AREA
CONSTRUCTION
SOUTH
ACCESS ROUTING NORTH BASIN O �O=�
O
CLARIFIERS� C?�V4U
0
AERATION SOLIDS CONTRACTOR
TANKS �J STAGING AREA
SOUTH
o CLARIFIERS
o �J SOLIDS
BUILDING
Q � O
1-5
ro O
o v
c
0
o PRIMARY
TANKS
a�
I
Attachment
Y CENTRAL SAN SOLIDS HANDLING FACILITY IMPROVEMENTS
N
' DISTRICT PROJECT 7348 1
Q
Page 14 of 26
ATTACHMENT 2
HISTORICAL BOARD ACTION SUMMARY
SOLIDS PROJECT, DISTRICT PROJECT 7348
Historical Board Action Summary:
As with all large projects, staff has been continually updated during the
development of the Solids Project. A list of prior Board actions are outlined below:
• December 1, 2016 - Board approved combining projects, predesign funding,
and a $2 million (M) Professional Engineering Services (PES) agreement
with Black & Veatch (B&V) for the pre-design efforts;
• December 15, 2016 - Board approved wet scrubber piloting work and
contracts;
• April 6, 2017 - Board approved air emissions testing consulting agreement to
support wet scrubber piloting;
• April 26, 2018 - Board approved amending the B&V agreement to include
final design services for an amount not to exceed $5.9 M;
• December 6, 2018 - Board approved resolution regarding funding eligibility
for State Revolving Fund (SRF) funding;
• December 20, 2018 - Board authorized the pre-selection and contracting for
the centrifuge equipment, cake pump equipment, and new wet scrubber
equipment;
• June 20, 2019 - Board authorized a construction contract for the Emergency
Sludge Loadout Facility Upgrades and amending the PES with B&V by
$220,000;
• December 19, 2019 - Board authorized a PES agreement with MWH
Constructors, Inc. (MWH) for an amount not to exceed $400,000 for
constructability review and pre-bid services;
• August 6, 2020 - Board authorized the General Manager to submit an
updated SRF loan application for additional funding and Board resolutions;
• August 20, 2020 - Board authorized increasing the B&V agreement to
$9,654,636 and the MWH agreement to $950,000; and
• February 18, 2021 - Staff presented a project update and announced
advertisement of project bidding. Additionally, the Board authorized the
General Manager to amend the MWH PES to a ceiling of $1.1 M and amend
the blanket agreement with Aresine Engineering to a ceiling of $975,000.
September 2, 2021 Regular Board Meeting Agenda Packet- Page 141 of 199
Page 15 of 26
ATTACHMENT 3
SOLIDS HANDLING FACILITY IMPROVEMENTS
DISTRICT PROJECT 7348
SUMMARY OF BIDS
PROJECT NO.: 7348 NO. OF ADDENDA: 9 DATE/TIME: JUNE 16, 2021/12:00 PM
PROJECT NAME: SOLIDS HANDLING FACILITY IMPROVEMENTS
PROJECT MANAGER: NATHAN HODGES
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $130,000,000 - $140,000,000
NO. BIDDER BID PRICE
Kiewit Infrastructure West Co. $179,841,000
Fairfield, California
2 W.M. Lyles Co. $206,856,000
Fresno, California
3 Flatiron West Inc. $216,293,989
Benicia, California
BIDS OPENED BY /s/ Katie Young
DATE: June 16, 2021 at 12:30 p.m. via livestream due to COVID-19
September 2, 2021 Regular Board Meeting Agenda Packet- Page 142 of 199
Page 16 of 26
ATTACHMENT 4
SOLIDS HANDLING FACILITY IMPROVEMENTS
DISTRICT PROJECT 7348
POST-BID/PRECONSTRUCTION ESTIMATE
No. Item Description Amounts %Construction
Cost
1. CONSTRUCTION
a. Construction Contract $179,841,000
b. Project Contingency at 15% (CM included) $27,000,000
c. Permits(Air Testing included) $1,000,000
d. Hazardous Compliance(Testing included) $700,000
e. ESLF Construction Completed(Not SRF Eligible) $2,866,000
SUBTOTAL-CONSTRUCTION $211,407,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
-Engineering staff(PM, RE, Safety,etc.) $6,000,000
-Operations Support, including Maintenance $5,000,000
b. Consultants
-MWH: Construction Management Services $12,000,000
-Hazardous Material Consulting $300,000
-Existing Electrical Support(Aresine&Carollo) $2,000,000
-B&V(ESDC) $4,000,000
-HDR(ESDC) $1,000,000
-Degenkolb(ESDC) $650,000
-Furnace Support(TBD) $650,000
-As-needed Services, Third-Party Review, QA/QC,VE $2,500,000
SUBTOTAL-CONSTRUCTION MANAGEMENT $34,100,000 16.1%
3. PREBID EXPENDITURES
a. Engineering
-District Staff Time(Engr.And Operations) $3,900,000
-B&V $9,600,000
-MWH $1,100,000
-Other Consultants $720,000
-Equipment Selection Procurement $496,000
-Regulatory Permits $50,000
SUBTOTAL-PREBID EXPENDITURES $15,866,000 7.5%
4. TOTAL ESTIMATED PROJECT COST 1 $261,373,000
September 2, 2021 Regular Board Meeting Agenda Packet- Page 143 of 199
Page 17 of 26
Attachment 5
SOLIDS HANDLING FACILITY IMPROVEMENTS
11
DISTRICT PROJECT 7348
PROJECT AWARD
Board Meeting
September 2, 2021
Jean-Marc Petit, P.E.
Director of Engineering and Technical Services
s,
Edgar J. Lopez, P.E.
Capital Projects Division Manager `
1
SOLIDS HANDLING FACILITY IMPROVEMENTS
(SOLIDS PROJECT, PHASE 1
1 2 2 3 4 5 6 7 8 Completed related
O •r eects
Emergency Sludge
Loadout
• Emergency exterior
stairways
Digester demolition
EXISTING SLUDGE MULTIPLE AIR POLLUTION ASH HANDLING ELECTRICAL CENTRIFUGE
SOLIDS
DIGESTER BLENDING/ HEARTH
CONTROL AND LOADOUT SYSTEMS DEWATERING CONDITIONING
DEMOLITION STORAGE FURNACES SYSTEM BUILDING
(MHFs)
SEISMIC Z
RETROFIT
2
1
September 2, 2021 Regular Board Meeting Agenda Packet- Page 144 of 199
Page 18 of 26
SOLIDS PROJECT IS VERY COMPLEX AND
RENOVATES AN OPERATING FACILITY WITH ALL
THE SOLIDS AND POWER ELEMENTS OF THE
TREATMENT PLANT
■
■
i
Ok
3
PRE-QUALIFIED GENERAL CONTRACTORS AND
ELECTRICAL SUBCONTRACTORS
General Contractors: Electrical Subcontractors:
• Balfour Beatty Infrastructure, Inc. • Blocka Construction, Inc.
• Flatiron West, Inc. • Con J. Franke Electric, Inc.
• Kiewit Infrastructure West Co. • Contra Costa Electric, Inc.
(Kiewit) • Helix Electric, Inc.
• C. Overaa&Co. Mass Electric Construction Company
• Shimmick Construction Company, . San Joaquin Electric, Inc.
Inc.
• Walsh Construction • Shimmick Construction Company,
Inc.
• W. M. Lyles Co. • Sprig Electric Co.
Bidders
4
2
September 2, 2021 Regular Board Meeting Agenda Packet- Page 145 of 199
Page 19 of 26
BID SUMMARY
Bid opening: June 16,2021,2:30 PM
Engineer's Estimate: $130,000,000-$'140,000,000
No. Bidder Total Bid
1 Kiewit Infrastructure West Co. $779,841,000
2 W.M.Lyles Co. $206,856,000
3 Flatiron West Inc. $216,293,989
` 5
CENTRAL SAN
5
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
Fiscal Year(FY) CIB Budget Comments Construction Progression of
Estimate Scope Elements
Baseline—Scrubbers,
$51.4 Million dewatering,seismic,ash,
FY 17-18 $66,439,000 Master Plan M blending,etc.
Scrubber pilot testing:
more electrical,instrumentation
FY 18-19 $82,100,000 30%Design $63.0 M and controls EI8 C identified.
New ash building,smart motor
control center(MCC)equipment,
upgrades to Emergency Sludge
Loadout Facility(ESLF)and other
FY 19-20 $93,376,000 50%Design 1 $85.9 M side prolects.
Pv zi-zz Long time to complete this
Capital Design.Quality assurance and
Improvement quality control(QA/QC)concerns
Budget(CIB) on EI&C.Added constraints and
Project FY 20-21 $128,234,000 90%Design $97.3 M sequencing.
Approved Added more constraints,longer
Budget project duration,and partial
building shutdown for MHFs
FY 21-22 $183,894,000 100%Estimate $110.0 M temporary ower.
Sludge hauling 8,disposal,
electrical work for existing
Revised in bid systems,9 Addenda clarifications,
eriod $183 894 000 Per Addenda $140Malation increases.
til
6
6
3
September 2, 2021 Regular Board Meeting Agenda Packet- Page 146 of 199
Page 20 of 26
PRICE INCREASES AND DIFFERENCES
• Reasons for increased costs since FY 21-22 Budget:
• 1,460 Days or over 4 years of construction
• Impact of construction sequencing from seismic improvements
• Very detailed project construction constraints and milestones
• MHFs shut down for 12 months and additional 6 months requires
temporary sludge hauling-$19 M
• Deferred design:
• Pipe and electrical conduits supports and routing
• Temporary shoring design for seismic walls
• Ash system and metal building
• Existing electrical systems issues
• Electrical on critical path is very complex and increased the project risk
• Limited number of bidders-Only three general contractors and two
electrical subcontractors
• Included major temporary electrical system as part of sequencing
• Bid market impacts
• Global supply disruption during COVID-19
One of a kind in difficult times and market
CENTRALSAN
7
POST BID/PRE-CONSTRUCTION ESTIMATE
No. Item Description Amounts %ConAmolon
Cost
1 CON$TRUr7lON
a.ConsVrcllan Cnr&W 5179,841,000
b.Project Canlingency at 15%(CM Included) 527,000,600
c.Permks(Air Tesling nowed) 51,000,000
d.HaE rdou9 Compliance[resting included] S700,000
e.ESLF Coriatruation Completed(Not SRF Eligible) 52.886.000
SUBTOTAL-CONSTRUCTION 5211 9117 000 100%
2. CONSTRUCTION MANAGEMENT
a.Dorm Farces
-Engineering staff(PM,RE,Safety,etc.) 58,000,000
-Operations Support Wl ud ing MaYdenance 55,000,000
6.Consultants
MWH:Construction Ma nagem em Services $12,000,000
-Ha[ardom Material Consulting 4300,00D
-Existing Electrical Sopyort(Aresine&Carollo) 52,000,000
-S&V(ESD(-,) $4.000,000
H DR(ESOC) S1,000,000
-Degenkale(ESDC) 4850,000
-Furnace Seppart(TED) SB5g600
-As-neewd Servtcas,Tired-Party Rew .Olk=.VE 52 300.000
SUBTOTAL-CONSTRUCTION MANAGEM ENT $34.100.000 16 1'%.
3. PREBID EXPENDITURES
P.Engineering
-Dlstrkt Stitt Tlme(Ergr.And Operatroris) 53,900,000
-$&V S9 6N 000
-MWH $1,100,000
-aner ConsullaNa 4720,000
-Erauigme nt Selection Procure mem $
996,000
-Regulatory PaimitG S50,OW
SUBTOTAL-PREBID EXPENDITURES 515.866.000 7541.
d. TOTAL ESTIMATED PROJECT COST $281,979,000
CEN TRAL SAN
8
4
September 2, 2021 Regular Board Meeting Agenda Packet- Page 147 of 199
Page 21 of 26
PROJECT CONTINGENCY DETAILS
• Staff is requesting to budget 15% Contingency
• Breakdown for needing 15% or $27 M:
• 5% or$9 M is Standard Allowance for change orders;
• 5% or$9 M due to major renovation and project complexity;
• 5% or$9 M for the following:
• Regulatory changes based on Maximum Achievable Control
Technology (MACT)50% rule ($5 M)
• Additional staffing costs due to change orders and MACT
50% rule or engineering costs to support project($4 M)
• Staff will re-evaluate the Contingency required prior to
issuing Notice to Proceed (NTP) for Construction.
9
CENTRALSAN
PROJECT FINANCING
• FY 2021-22 Budget:............ $ 183.9 M
• Total Estimated Project Cost: $ 261.4 M
• Overall Variance: ($ 77.5 M)
OrCENTRAL SAN
r to
10
5
September 2, 2021 Regular Board Meeting Agenda Packet- Page 148 of 199
Page 22 of 26
FINANCIAL PLANNING ASSUMPTIONS
Our long-term financial plan has updated to evaluate several scenarios related to
funding options for the Solids Project.
Some of the general assumption updates include:
• Unfunded Actuarial Accrued Liability(UAAL)eliminated and debt service on
2021 Certificates of Participation (COPs).
• Anticipated Cost-Of-Living Adjustments(COLAs)per anticipated Memoranda of
Understanding(MOUs).
• Other inflation assumptions updated.
• $15.9 M of previously funded costs(pre-bid expenditures for planning and
design)of the Solids Project will be reimbursed from the existing$173.1 M SRF
loan.
$25 M cut to the Ten-Year Capital Improvement Program (CIP)or five years of
$5 M per year.
o$3 M from Collection System Sewer Renovation;
o$0.5 M from Vehicle Replacement Program; and
o$1.5 M from Contingency.
WE HAVE OPTIONS TO FUND
SOLIDS PROJECT FUNDING GAP
(Each option includes a proposed reduction of$25 M CIP)
PREFERRED APPROACHES
1. Request an additional $50 M from SRF loan. No sewer
service rate impacts above what is currently planned.
2. Issue $53 M in revenue bonds or COPs to fund FY 2022-23
Capital Expenditures, freeing up cash that could be set aside
for the Solids Project funding gap. No sewer service rate
impacts above what is currently planned.
Not Recommended
3. Cash finance the funding gap through increased sewer service
rates with additional 1.75% for each of four years for a total
increase of 7%.
4. Defer another$50 M in projects in the Ten-Year CIP.
CENTRALSAN
12
6
September 2, 2021 Regular Board Meeting Agenda Packet- Page 149 of 199
Page 23 of 26
ALTERNATIVES
• Alternative 1:Award the Contract Award the project to Kiewit but _—
proceed with a multi-step NTP. Evaluate and review project —_
sequencing,milestones,costs,and more ways to reduce risks for
the contractor and Central San.Staff will report back prior to issuing _—
a NTP for construction.
Incorporate VE&
NTP-1 NTP-2 Field Verifications NTP-3
Award Project Conductper Contract;Order Begin
Value Long Lead Construction
Engineering Equipment/Shop
(VE) Off Ramp Drawings
Terminate for
Convenience `13
CENTRALSAN
13
ALTERNATIVES (CONTINUED)
• Alternative 2:Reject Bids
• A)Rebid the Project:Staff would conform all the addenda with
the contract documents,evaluate and incorporate more ways to
reduce risks to the contractor and rebid within 6-9 months.
• B)Rebid within Approved Budgef:Staff could repackage and
rebid the project to proceed within the$183.9 M budget and add
a future project(s)to complete the remainder of the scope.
• C)Consider Design-Build Proiect Delivery:Staff could
evaluate alternative delivery to complete the project using Not Recommended
design-build and use the existing Solids Project's bid documents
as the basis.
• D)Repackage Proiect in Multiple Phases:Staff could split
and implement the Solids Project scope into multiple phases.
This would include rebidding in various smaller projects which
could be implemented in either two or up to six phases and take
more years to complete. (Could be evaluated further if all other
alternatives are not pursued.)
14
14
7
September 2, 2021 Regular Board Meeting Agenda Packet- Page 150 of 199
Page 24 of 26
ALTERNATIVES (CONTINUED)
• Alternative 3(A):Evaluate an Alternative Long-term Solids
Handling Approach including Anaerobic Digestions with all new
Solids Facilities:Staff recommends re-evaluating the long-term
solids handling from current operations based on furnaces,ash
disposal and steam recovery to including or changing to anaerobic
digestions based on the higher costs of the Solids Project.
• Alternative 3(B):Evaluate an Alternative Long-term Solids
Handling Approach including Anaerobic Digestions using a
Private-Public-Partnership(P3)Approach:Like Alternative 3(A),
staff recommends re-evaluating the long-term solids handling from
current operations based on furnaces,ash disposal and steam
recovery to anaerobic digestions using a P3 approach and use green
energy.
CENTRALSAN
`ss
15
RE-EVALUATE LONG-TERM PATH FOR
SOLIDS HANDLING AT CENTRAL SAN
Alternative 3 A or B: Re-
Alternative 1:Award based Evaluate Long-Term Solids
on Contractor Design Assist Handling
and reduce risk after VE
All New Project:
Refurbish -Anaerobic
MHFs, Digestion and
continue with
-� Biogas Co-Gen.
Steam and Abandon Steam.
Co-Gen with Convert to all
Natural Gas Electric Blowers
Evaluate both
- paths before
NTP for - --
construction - ==
h'16
CENTRALSAN
�.
16
8
September 2, 2021 Regular Board Meeting Agenda Packet- Page 151 of 199
Page 25 of 26
CONSTRUCTION SCHEDULE
FY 2021-22 FY 2022-23 FY 2023-24
Bid and Award
NTP-1:Solids Handling,Phase
1 Optimization VE with Kiewit
Alternative Long-Term Solids
Handling Alternatives
Evaluation
Board decision on Alternative
Path for Long-Term Solids
Handling
NTP-2:for Construction
Construction
July 2021 July 2022 July 2023 July 2024 July 2025 July 2026
❑ Bid and Award:February 22,2021—September 2,2021
NTP-1:Solids Handling Contract review with Kiewit and Engineering:October 2021—Feb.2022
Q Alternative Long-Term Solids Handling Alternatives Evaluation:September 2021—Feb.2022
Update Board in February 2022 and request approval for construction
Q NTP-2:Proceed with Kiewit for Solids Handling,Phase 1 Construction:March 2022
Construction Phase:March 1,2022—February 28,2026(1,460 Days)
� v
CENTRALSAN
17
PROJECT SUPPORT NEEDED
• Construction Management: MWH Constructors, Inc.
• Engineering Services During Construction:
• Black & Veatch Corporation: Civil, Mechanical, HVAC,
and EI&C
• HDR, Inc.: Architectural, Structural, and As-Needed
• Degenkolb Engineers: Seismic Design
• Aresine Engineering: Assist Capital Projects with Review
of Electrical and Controls Items and Questions
• (TBD): Furnace and Air Pollution Control
• Others: As-Needed Engineering to conduct third party
independent assessments of Solids Handling Alternatives
r 18
CENTRAL SAN
1s
9
September 2, 2021 Regular Board Meeting Agenda Packet- Page 152 of 199
Page 26 of 26
BOARD RECOMMENDATIONS FOR ACTION
1. Award of a construction contract in the amount of$179,841,000 to Kiewit
Infrastructure West Co., the lowest responsive and responsible bidder,for
the construction of the Solids Handling Facility Improvements, District
Project 7348.
2. Authorize staff to enter contractual agreements with third-party consultants
to conduct independent assessments of Solids Handling Alternatives
3. Authorize the General Manager to execute five new agreements:
a) MWH Constructors, Inc. at a cost not to exceed $12.0 million for
construction management services.
b) Black&Veatch Corporation at a cost not to exceed $4.0 million for
engineering support during construction.
c) Aresine Engineering at a cost not to exceed $1.5 million for electrical
engineering support.
d) HDR, Inc. at a cost not to exceed $1.0 million.
e) Degenkolb Engineers at a cost not to exceed $650,000.
4. Authorize the General Manager to execute Contract Documents subject to
SRF funding, submittal requirements, value engineering, and include up to
a 15-percent project contingency.
` 19
CENTRALSAN
19
QUESTIONS?
51
r 20
20
10
September 2, 2021 Regular Board Meeting Agenda Packet- Page 153 of 199