HomeMy WebLinkAbout02. Conduct a workshop on the Solids Handling Facility Improvements, District Project 7348 Page 1 of 28
Item 2.
CENTRALSAN
Jdf A- hom
CENTRAL CONTRA COSTA SANITARY DISTRICT
August 26, 2021
TO: HONORABLE BOARD OF DIRECTORS
FROM: NATHAN HODGES, SENIOR ENGINEER
REVIEWED BY: EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
SUBJECT: HOLD AN INFORMATIONAL WORKSHOP REGARDING THE SOLIDS
HANDLING FACILITY IMPROVEMENTS, DISTRICT PROJECT 7348. THE
FOLLOWING WILL BE PRESENTED FOR DISCUSSION:
• RECEIVE A STATUS UPDATE OF THE PROJECTAND RECENT BID
PERIOD ACTIVITIES;
• CONSIDER A STAFF PROPOSED RECOMMENDATION TO AWARD A
CONSTRUCTION CONTRACT, ATA FUTURE MEETING, TO KIEWIT
INFRASTRUCTURE WEST CO., THE LOWEST RESPONSIVE AND
RESPONSIBLE BIDDER, IN THE AMOUNT OF $179,841,000;
• CONSI DER ALTERNATIVES;
• CONSIDER STAFF PROPOSED NEED FOR ADDITIONAL
ENGINEERING SUPPORT SERVICES DURING CONSTRUCTION,
INCLUDING AMENDMENTS TO EXISTING AGREEMENTS AND
EXECUTION OF TWO NEW AGREEMENTS; AND
• HOLD A QUESTIONS AND ANSWERS SESSION
The Comprehensive Wastewater Master Plan (CWMP)finalized in 2017 identified many
improvements to the solids and energy unit processes associated with the treatment plant (plant). The
following approach for short-term and long-term improvements were outlined in the CWMP:
The Fiscal Year (FY) 2021-22 Ten-Year Capital Improvement Plan (CI P) includes:
• Solids Handling Facility Improvements, District Project (DP) 7348 (Solids Project): $183.9 million
(M) •
• Steam Aeration & Blower Systems Renovations, DP 7349: $35.4 M.-
Multiple Hearth Furnaces (MHFs) Replacement, DP 100009: $1 M.•
August 26, 2021 Special Board Meeting Agenda Packet- Page 3 of 30
Page 2 of 28
• Cogeneration (Co-Gen) Replacement (starting FY 2023-24): $25.1 M.
• Other Solids Facility Improvements— Dissolved Air Flotation Thickener(DAFT) Tanks (starting FY
2028-29): $2.4 M
The Long-term Planning Improvements (20-year+ IN 2021$) include:-
• Solids Handling, Phase 2:Add two anaerobic digesters and convert to biogas Co-Gen and consider
adding high strength waste to increase "green" gas production at$126.8 M.•
• Solids Handling, Phase 3:Add two additional anaerobic digesters and replace the MHFs with
fluidized bed incinerator at$175.4 M.
The Solids Project was introduced to the CI P in FY 2017-18 to consolidate several projects already
identified in the Treatment Plant Program since 2010. The project elements are all related to solids
processing and handling within or around the Solids Conditioning Building (SCB). When the Solids Project
was initiated, a detailed condition assessment was conducted and new air pollution control equipment (wet
scrubber)was pilot tested to confirm the design parameters. Critical equipment such as the centrifuges,
cake pumps, and wet scrubbers were pre-selected and designed. Staff also coordinated with regulatory
agencies, developed construction constraints, applied for a State Revolving Fund (SRF) loan, pre-
qualified contractors, bid the project, and received bids on June 16, 2021.
The following major elements are included in the Solids Project:
• Replacement of the two wet scrubber systems with new air pollution control equipment to meet air
regulations, including a new Venturi scrubber capable of handling waste heat bypass events.
• Replacement and upgrades to sludge blending, storage, and mixing systems.
• Replacement of the centrifuges and cake pumps.
• Incinerator burner upgrades and new after-burners including modern controls.
• Addition of a new Ash Handling Facility to modernize the conveyance and improve loading to reduce
fugitive ash emissions, and increase reliability.
• Construction of major seismic modifications to the SCB and to the two existing incinerators to meet
the current seismic standards.
• Addition of a new electrical room and replacement of major electrical, instrumentation, and controls
(E I&C)to accommodate the new systems and integrate with the remaining systems not in the Solids
Project.
• Requirement of significant constraints, including restrictions to shut down the incinerators, install
temporary electrical facilities, and the off-haul and disposal of sludge.
• Demolition of the abandoned digester tank near the SCB. (Completed)
• Construction of the SCB emergency stairway for the third-floor control room for safety egress.
(Completed)
• Construction modifications to the Emergency Sludge Loadout Facility to reliably operate and load
sludge for extended durations. (Completed)
A site location map is provided as Attachment 1.
The Solids Project is the largest single renovation project that Central San has undertaken since the
treatment plant was expanded in the 1970's.As with all large or critical projects, staff has been updating
the Board of Directors (Board)through Committee and Board meetings throughout the process. Since
2017, staff has discussed and received authorization from the Board on several occasions as outlined in
Attachment 2.
Bid Schedule: The Solids Project was advertised on February 22 and March 1, 2021. The original bid
opening date,April 28, 2021, was extended on multiple occasions and was changed to June 16, 2021 due
to requests from bidders and scope clarifications by addenda. Nine addenda were issued during the bid
August 26, 2021 Special Board Meeting Agenda Packet- Page 4 of 30
Page 3 of 28
period. Staff facilitated over 20 bidder site visits and answered over 300 bid questions. The project
documents, bid forms, and security included a 120-calendar day period in which bids cannot be withdrawn
to accommodate for the SRF review, which is common practice for large SRF-financed projects.
Bid Opening and Evaluation: On June 16, 2021, three bids were received and publicly opened, that
ranged from $179,841,000 to $216,293,989.A summary of bids is shown in Attachment 3.
The Engineer's estimate for construction was originally listed at$110 M when first advertised, and later
amended up to $140 M to reflect changes in the evolving bid market and elements included in addenda.
Capital Projects staff conducted a technical and commercial review of the bids and determined that Kiewit
Infrastructure West Co. (Kiewit) is the lowest responsible and responsive bidder with a bid amount of
$179,841,000. During the bid evaluation, staff found one minor discrepancy, which was clarified by Kiewit.
The discrepancy was that Kiewit did not correctly list the name of the packaged electrical systems (motor
control centers and variable frequency drives) as required by the specifications. This discrepancy is
considered non-material by staff since it was clarified and met the specifications.
The lowest bid is approximately$40 M above Central San's construction estimate. Staff's bid review
included meetings with the three bidding general contractors, MW H Constructors, I nc. (MW H), and
several other consultants. After discussions with the three bidders, it became clear that the cost of
materials, vendors, and subcontractors were significantly higher than the estimate, which is the main factor
for receiving higher pricing. The increases were due to uncertainty in local, U.S., and global market
conditions engendered by the COVI D-19 pandemic. This was further compounded by several risk
elements associated with the project, including vendor ability to receive materials or equipment on time to
meet the milestones and timelines identified in the contract documents or the inability to receive
guaranteed pricing for items that were already in high demand or becoming unavailable. These
uncertainties and risks increased costs as suppliers or subcontractors attempted to predict the future
pricing for commodities required for the contract.
During the bid period, the Solids Project team evaluated the COVI D-19 impact and supply chain issues or
delayed deliveries might have on the final bid price, including the rapidly escalating commodity pricing. For
these reasons, staff raised the construction estimate from $110 M to a maximum of$140 M to
accommodate material prices and reflect the changes in the electrical scope made via addenda. More
recent, staff in the treatment plant program are starting to report delays in major equipment, such as
electrical, and significant cost escalation requests for steel or copper.
It should be noted that staff had not seen or experienced significant cost escalation in past construction
projects during COVI D-19. The Board has awarded thirteen construction contracts since the pandemic
first started in March 2020, and all but one project came over the Engineer's estimate. However, the Solids
Project involves major upgrades and renovations to a one-of-a-kind industrial four-story facility, the center
for Central San's solids handling, disposal, and energy production. There is no other similar facility in the
western U.S., the closest being located in the Midwest and most of which are located on the East Coast.
Furthermore, even though the team spent considerable time during the design evaluating shutting down the
SCB to facilitate and shorten construction, it became apparent that it would have been logistically and
economically impractical. One outcome was to consider shutting down the MHFs for 12 months and up to
18 months. Another significant challenge is associated with the El&C systems for the existing systems to
remain in the project. The El&C challenges have been throughout the design and continue even after the
bid to be a major effort as Central San does not have complete or accurate wiring records for all systems.
Although not yet defined in terms of costs, this has contributed to higher electrical pricing and fewer
interested electrical subcontractors.
I n October 2020, staff pre-qualified seven general contractors (GCs) and eight electrical subcontractors
(ECs). During the bidding period, staff was informed that four GCs and six ECs would not be participating
August 26, 2021 Special Board Meeting Agenda Packet- Page 5 of 30
Page 4 of 28
in the bid. Feedback for not bidding was based on the cost or the duration of the project, or due to pursuit
of easier and smaller projects. The project duration is 1,460 days. Many bidders and potential bidders
considered this duration as added risk. Staff's assessment is that the complexity of the Solids Project
made it especially challenging for bidding since the project is not a typical public works, low bid job.
Therefore, the limited competition contributed to the higher costs received at bid time.
Only three GCs and two ECs provided bid prices. Mass Electric Construction Co., a Kiewit Corporation
subsidiary, provided a labor quote only to Kiewit. The other EC, Blocka Construction, I nc., provided pricing
of over$58 M to the other two GCs. Kiewit did have better pricing from their electrical subcontractor and
plans to purchase all electrical materials and equipment, which was a significant reason for the difference
between Kiewit's bid and the two other bidders.
Central San is the only public agency in California still operating sewage incinerators. The incinerator work
is specialized and there was only a single subcontractor that provided pricing. The Solids Project scope
included 12 months of temporary sludge operations, including pumping, dewatering, odor control,
conveyance, hauling, and disposal.Additional unit pricing was included for up to six months of temporary
operations. Pricing received for the entire 18-month scope ranged between $15.1 M and $34.53 M, which
is significant. This price range indicates the wide variability in the bid item and the cost impact and the
difference between the bids.
Finally, the overall operations and construction risks influenced pricing. Many risks have been identified,
including the milestones and constraints, project duration, combined with challenging elements such as
deferred design, electrical being a critical path, and timely receipt of materials and equipment resulted in
contractors adding more value than taking on more risk than the Engineer anticipated.
Construction Support: Staff will administer and have overall control of the construction and interaction
with plant staff, engineering consultants, and safety for Central San employees. MWH will be the
construction manager(CM) providing frontline or day-to-day management with the contractor, including
general inspection, special inspections, coordination of construction activities, startup and commissioning
services, recommending payments, schedule and cost review, file management, and various other support
duties required to effectively manage the complexities of the Solids Project. MWH had been previously
selected through a formal public solicitation and has been assisting staff with review of the bid documents,
schedule analysis, and cost estimating. Staff negotiated the CM scope with MWH with a cost ceiling of
$12.0 M. MWH's current agreement is valued at$1.1 M and including the CM services will result in a new
cost ceiling of$13.1 M.
Black& Veatch Corporation (B&V) and sub-consultants HDR, Inc. (HDR) and Degenkolb Engineers
(Degenkolb) are the Solids Project designers. These firms were selected and hired under two solicitations
that consisted of planning and detailed design.All three firms will provide engineering support during
construction (ESDC) services. Staff is recommending a pay for performance fee structure with B&V
based on prior experiences. The services with B&V will be on an as-needed basis with a not to exceed
cost ceiling of$4.0 M. The current agreement amount is approximately$9.6 M and including the ESDC
services will result in a new agreement valued at$13.6 M.
HDR will provide structural and architectural ESDC services at a cost up to $1.0 M, while Degenkolb will
provide seismic ESDC services for an amount not to exceed $650,000. Staff has elected to enter into
agreement directly with each sub-consultant to better support the construction effort directly with Central
San and MWH. During the bid phase, staff utilized Aresine Engineering (Aresine)to prepare additional
drawings and specifications for the installation of temporary electrical and control systems related to
existing systems that were not addressed by B&V's design. Staff intends to continue using Aresine due to
their expertise and understanding of Central San's standards and existing electrical systems. In addition,
staff is also recommending electrical support by Carollo Engineers, Inc. (Carollo) since their field services
can be provided locally to quickly respond to any issues that may arise during construction. Carollo was
August 26, 2021 Special Board Meeting Agenda Packet- Page 6 of 30
Page 5 of 28
recently selected under a competitive solicitation to perform electrical inspection and CM services on an
as-needed basis. These electrical services are focused on assisting and supplementing the specialized
work that would be normally performed by staff. The anticipated budget for the electrical services is
estimated at$2.0 M and will be performed on an as-needed basis and split between the two engineering
firms. Electrical is one of the most critical and complex elements to the success of the Solids Project and
has been the most difficult trade to find experienced and qualified, local personnel to help staff or to hire.
Hazardous materials testing and related services are essential for a safe worksite and project. Existing
building materials have lead paint or primers, asbestos, and a significant amount of concrete demolition will
take place inside the SCB.Additionally, excavation for exterior shear walls and installation of drilled piles
are expected to encounter contaminated soil. Staff is in the process of selecting a consultant to provide
hazardous material support for the project. The costs for these services are expected to reach $1.0 M;
Board approval will be requested at a future time.
Staff has also identified the need to include additional professional engineering services for third-party
review, quality assurance and quality control (QA/QC), cost reduction alternatives, and recommendations
that can assist in a cost-effective project and avoid schedule impacts. The scope of services will focus on
industrial mechanical and electrical, incinerator retrofits, installation of new air pollution control equipment,
ash handling, and other elements or consulting work.A Request for Qualifications (RFQ) has been publicly
advertised and staff anticipates a budget of$2.5 M for the additional services. The RFQ includes the
ability to hire multiple firms, if needed; therefore, staff will return to the Board once the RFQ process is
finalized and fees have been negotiated.
California Environmental Quality Act(CEQA)
At its December 6, 2018 meeting, the Board independently found that the Solids Project is exempt from
CEQA under Central San's CEQA Guidelines Section 15301, since it involves minor alterations to
existing public facilities involving no expansion of use, and CEQA Guidelines Section 15302, since it
involves replacement of existing public facilities at the same location and with the same purpose.
CONSIDERATIONS AND ALTERNATIVES
CONSIDERATIONS: The following factors were considered by staff as several of the project alternatives
are evaluated. As stated above, three sealed bids were received and opened for the construction of the
Solids Project.At the next Board meeting on September 2, 2021, the Board will need to either award the
contract or reject all bids within 120 calendar days or by October 14, 2021.Authorization will also be
requested from the Board to execute both new agreements and amendment for the several construction
management and consulting engineering firms that will be required for this four-year construction project.
Time - Rejecting all bids, proceeding with a project redesign, and rebidding the project is anticipated to
result in as much as a 12-month delay to the start of construction. I n addition, delaying the project will also
impact Operations and delay the installation of new equipment and facilities, such as the new scrubbers
and centrifuges. Most of the equipment being replaced under this project is beyond its useful life and in
need of replacement. Kiewit is a very qualified and experienced general contractor. They are planning to
self-perform a lot of the project scope.
Costs - Repackaging and rebidding the project (or project phases) may not reduce total project costs or
could possibly result in increased costs.An important consideration is that repackaging the project is
primarily intended to reduce the exposure to risks such as delay claims during construction.Any cost
savings that might be developed as part of a redesign may likely be offset by other factors like inflation or
continued supply issues.
Air Permit Compliance - The existing MHFs air pollution controls are having difficulty achieving air permit
compliance. A priority will be to address these regulatory issues in an efficient manner. Since Clean AirAct
August 26, 2021 Special Board Meeting Agenda Packet- Page 7 of 30
Page 6 of 28
Section 129 regulations (129 rule)went into effect in March 2016, the Bay Area Air Quality Management
District(BAAQMD) has issued to Central San several notices of violations (NOVs) related to the
emergency bypass damper openings. Staff has been able to reduce the frequency of bypass events, but
because of inherent limitations of the existing equipment, the bypass damper continues to periodically
open, in violation of the 129 rule. The MHFs also cannot consistently meet the hydrochloric acid (HCI)
emission limit in the 129 rule. Staff has been working closely with United States Environmental Protection
Agency(USEPA)to address these compliance challenges. Local regulation will also impact compliance.
Data from an on-site pilot study conducted in 2018 indicate the new MHF air pollution control devices will
significantly reduce the frequency of emergency bypass damper openings and reduce HCI and particulate
matter(PM) emissions below their respective limits. BAAQMD Rule 6-1, which goes into effect in 2025,
lowers the PM concentration limit on the MHFs and the existing air pollution control devices are not
sufficient to ensure compliance. Staff with a specialty consultant, GHD, is currently doing pre-design for
future devices to reduce PM and carbon oxide (CO)to the new standards. This would require the addition
of the wet electrostatic precipitators (WESP)to meet PM 2.5 and adding a "zero" hearth on top of the
MHFs to meet the lower CO limits.
SCB Shutdowns - Shutting down most SCB processes, including temporary dewatering and hauling of
sludge, will likely remain part of the scope of work; however, it may be significantly reduced if the project is
repackaged or phased, as this turn out to be an expensive proposition.
ALTERNATIVES: Staff evaluated several alternatives and options for solids handling and energy starting
with the CW MP, during the predesign, design, bidding, and most recently following the bid opening prior to
award. Three alternative paths are being considered and are described below and will be further discussed
during the workshop.
Alternative 1:Award the Contract
Staff recommends awarding the Solids Project to Kiewit, since Central San has a final design for the
project, a qualified, experienced contractor ready and able to start construction of this complex project, and
are expecting to receive the final draft agreement from the State of California Clean Water SRF Funding
for a $173.1 M low interest loan. However, a two-step Notice to Proceed (NTP) path is being considered
since the project is over budget. This stepped approach following award but before starting construction is
recommended because the project total cost estimate has significantly increased since its inception, and
particularly now that we have a bid from a contractor. Once awarded, staff and Kiewit will conduct a detailed
analysis of the project sequencing, milestones, and evaluate other ways to reduce risks and potential costs
to the contractor and Central San. This will include value engineering and design assist from Kiewit, staff,
the design team, the CM, and specialty consultants. This effort is planned to last 90-120 days.
This approach is recommended since Central San has not executed the final SRF Agreement and needs
an additional $77.5 M to fund the total estimated project cost. Staff met with Kiewit and discussed the
timing of funding, using provisions within the contract documents to initiate the contract, and use of the
termination clause if there is not adequate funding or issues are discovered during the findings of the
schedule and costs analysis.An initial NTP would be issued to conduct a review as stated above and of
such items as deferred design components (temporary seismic shoring and electrical), sludge hauling, and
the detailed schedule of values for the contract. Kiewit has several in-house resources and experienced
leadership in building industrial and complicated construction like the Solids Project within their local
Fairfield office.A second NTP for construction will not be issued until Central San and Kiewit are
comfortable in moving forward with costs and schedule. I n the event a NTP is not issued, the contract will
be terminated by Central San.Accordingly, Central San would be required to pay the cost incurred by
Kiewit and time needed to reestablish their contract terms.
Staff explored the option of extending the time for award beyond the bonded 120 calendar days. This
option was not pursued since Kiewit would be beyond the guaranteed pricing with all their vendors,
suppliers, and subcontractors and likely result in additional costs.
August 26, 2021 Special Board Meeting Agenda Packet- Page 8 of 30
Page 7 of 28
Alternative 2: Reject Bids
The Board may elect to reject bids, which would result in staff having to regroup to determine the best
solution moving forward. Several options exist; however, staff would have to continue evaluating and report
back to the Board if one of the following options were selected.
Alternative 2(a) Rebid the Solids Project: Staff would conform all the addenda with the contract
documents, evaluate and incorporate more ways to reduce risks, and rebid within six to nine months. This
option may mitigate some effects of the current market; however, other costs may increase which cannot
be foreseen. Without significant changes to the scope of work, staff expects that the bidders may not
participate in a re-bid. If this option is pursued, staff would remove the pre-qualification for contractors to
get more interest. This is not recommended.
Alternative 2(b) Rebid Solids Project within Approved Budget: Staff could repackage the project and
rebid some of the project elements to stay within the current authorized budget of$183.9 M. This would
require removing and delaying some of the scope to fit the budget and add future project(s)to complete
the remainder of the scope. This is not recommended.
Alternative 2(c) Consider Design-Build Project Delivery: Staff could evaluate a design-build delivery
method. Under this approach, staff would be using the existing Solids Project's bid package as a basis.
This would allow a contractor with a designer to work together to optimize the Solids Project while starting
construction on critical path elements.Additional time would be required to prepare the front ends and
specifications for alternate construction delivery and put the responsibility of the changes of the design and
sequence onto the contractor to resolve.A design-build approach would likely attract more bidders than
rebidding the Solids Project under option (a) as several design-build contractors were interested and did
not participate during the pre-qualification process. However, staff expects that the bid price would
increase compared to the Kiewit bid. The only advantage for this option would be that the design-build cost
would be considered a maximum price while the contractor works to stay within the bid. This is not
recommended.
Alternative 2(d) Perform the Solids Project in Multiple Phases: Staff could separate and implement
the Solids Project scope into multiple phases. This would include repackaging the work in various smaller
projects which could be implemented in either two or up to six phases. The first phase(s) could prioritize
the new wet scrubbers, followed by the new electrical room, seismic utility relocations, centrifuges and
cake pumps, and low impact seismic renovations within the building. The subsequent phase(s)would
continue seismic work, followed by sludge blending tanks, and new ash facility. Final phase(s) may
complete seismic work, complete electrical demolition, and finish some remaining project elements.
One advantage with multiple project phases is that by reducing the scope of work and duration on each
phase, Central San likely has less exposure to cumulative delay change order claims and risks during
construction. Central San would also incorporate the lessons learned and construction challenges into the
future phases. Disadvantages with this option is increasing the overall Solids Project duration and
extending the timeline before new equipment is placed into service.As for costs, staff believes that
multiple phases or smaller projects will increase the bidder competition thus likely to lower the construction
costs. However, the engineering costs and staff time to support a longer duration and multiple contracts,
and inflation may offset some of the potential savings. While this alternative 2(d) is technically feasible,
there are no guarantee that the overall costs will lower since staff estimates that an additional three to four
years would be needed to complete all the scope identified in the Solids Project. This alternative could be
further considered if other alternatives do not end up being further pursued.
Alternative 3(a) Evaluate an Alternative Long-term Solids Handling Approach including
Anaerobic Digestions with all new Solids Facilities: Before issuing a final NTP for the Solids Project
construction, staff will reconsider and evaluate the long-term solids handling based on furnaces, ash
August 26, 2021 Special Board Meeting Agenda Packet- Page 9 of 30
Page 8 of 28
disposal and steam recovery to include or change to anaerobic digestions. This alternative could change
the design and construction of the solids and energy facilities such as anaerobic digestions including new
biogas cogeneration. This would include new facilities located north of the emergency sludge loading
facility. The current SCB and MHFs could continue to operate as the sludge disposal method in the
interim. Followed by ultimately, the abandonment of the SCB, MHF, steam, auxiliary boilers, and existing
Co-Gen. This alternative could be delivered as a typical design-bid-build, or design-build project. Biosolids
disposal would be addressed either by continuing to use the existing MHFs for ten years or so, or using
the newly renovated sludge loading building, or adding sludge dryers and pyrolizer. The project could also
be phased, with phase one focusing on adding two new anaerobic digesters, followed by a phase for new
biogas Co-Gen, and another phase adding two additional digesters and biosolids handling. Time would be
required to select a new consultant team, prepare designs and specifications. This alternative, if fully
implemented, would greatly simplify, and modernize Central San's solids handling and energy facilities.
This approach would likely attract more bidders than rebidding the Solids Project. The project could be
constructed and not require the complex sequencing and temporary work required for the Solids Project.
This would reduce risks and would be designed and constructed within the same time frame, four to five
years. However, this would be a radical shift in Central San's process and would need to be carefully
vetted and evaluated. Overall cost of this alternative may not be significantly less than the current approach
but should be evaluated based on the bids received for the Solids Project. It would, however, reduce many
risks associated with the current path. The main risk associated with this alternative is the biosolids
disposal and the potential future per- and polyfluoroalkyl substances (PFAS) regulations associated with
biosolids disposal. While staff does not recommend rejecting all bids, staff recommends pursuing a three-
to-four-month evaluation of this alternative 3a in more detail and compare the results with Alternative 1. This
effort is planned to have the same timeline as Alternative 1 (90-120 days) so the two alternatives can be
compared before making a long-term decision. This effort will be conducted by third party engineering
consultant firms.
Alternative 3(b): Evaluate an Alternative Long-term Solids Handling Approach including
Anaerobic Digestions with using a Private-Public-Partnership (P3) delivery for all new Solids
Facilities: Currently,Anaergia has a lease option on about nine acres located on the Kiewit property to
evaluate the feasibility of design-build-construct a private solid handling and biogas production facility
consisting of anaerobic digesters, high strength waste receiving station, and pyrolysis. This evaluation
could also include an option to build these same facilities north of the emergency loading facility under a
Public-Private-Partnership (P3).As with the other alternatives listed above, before issuing a final NTP for
construction of the Solids Project, staff suggest to reconsider and evaluate the long-term solids handling
operations. The current SCB and MHFs would be decommissioned under this alternative 3B. Staff could
operate some or all these facilities. The sludge disposal method would be pyrolysis producing a chart (like
ash). Biosolids disposal initially based on tipping fees with the ability for Central San to buy out these
facilities either in 20-years or sooner. This would require time to select a P3 concessionaire and to select a
consultant team for technical, finance, and legal support. also continuing to purse on parallel schedule to
other alternatives over the next 3-to 4-month evaluation of this alternative 3(b) in more detail and compare
to Alternative 1.
FINANCIAL IMPACT
The total estimated project cost is $261,373,000 which includes all prebid expenditures, design, bidding,
bid price, CM, consultant costs, staff time, and contingency as detailed in Attachment 4.A detailed
financial analysis with alternatives will be presented to the August 26, 2021 Board workshop. The current
budget for the Solids Project is shown on page 236 in the FY 2021-22 District Budget at$183,894,000.
The total estimated project cost includes a recommended 15% project budget Contingency or$27 M.
This is a high percentage and a higher cost than typically anticipated and included on such a large project.
August 26, 2021 Special Board Meeting Agenda Packet- Page 10 of 30
Page 9 of 28
A breakdown for requesting 15% or$27 M is shown below:
• 5% or$9 M for standard allowance for change orders (COs).•
• 5% or$9 M due to major renovations and project complexity.•
• 5% or$9 for regulatory changes based on:
• Maximum Achievable Control Technology (MACT) 50% rule ($5 M)to add WESP and zero
hearth for carbon oxide
• Additional staffing costs due to COs and MACT 50% rule or engineering costs to support the
project ($4 M).
Staff will re-evaluate the Contingency required prior to issuing the NTP for construction.
State of California Clean Water SRF Funding
Central San has applied and requested a total of $173.1 M in funding from SRF and received approval. In
December 2020, prior to advertising the Solids Project, staff submitted updated Solids Project
documents in support of receiving the initial agreement. The Water Board informed staff in March 2021
that the initial agreement would be routed for Division of Financial Assistance (DFA) approvals, after which
it would be sent to Central San for execution within the next several months. This initial agreement is
currently being routed for Water Board officials' signatures and is expected to be issued to Central San
within several weeks. Staff has recently spoken with the Water Board concerning the higher bids that was
received and the need for additional funding. After the initial agreement is executed, the final project
amount and supporting documents need to be submitted and will provide an opportunity for the Water
Board to request additional funding for the budget gap that is necessary.
Also, the Water Board indicated that if the Solids Project is rejected and split into more than two project
phases, then it would be challenging to win approval for additional funding. Staff will consider SRF and
other funding options as alternatives are evaluated. These will be presented at the August 26, 2021 Board
workshop for the Solids Project.
Project Financing Approach
As stated above, the total budget cost for the project listed for FY 2021-22 Budget is $183.9 M for the
project. Staff has applied and is expected to receive the agreement from SRF for a loan of$173.1 M. The
latest total estimated Project Cost is$261,373,000. The variance between the FY 2021-22 Budget of
$183.9 M and the latest estimated project cost of $261,373,000 is a gap of approximately$77.5 M.
Proposed Financing of Project Gap
Staff brought the Solids Handling Project contract approval to the August 17 Engineering & Operations
(E&O) Committee for discussion at the August 26 Board workshop on, and then for potential approval by
the Board in September. The need, merits, and technical approach of the project were subject to
discussion at the E&O Committee. The matter of the funding approach for the Solids Project, considering
higher than anticipated costs, will be discussed at the August 26, 2021 Board workshop.
With the receipt of the bids for the Solids Handling project, the overall cost of the project has been
increased by$77.5 M. Recognizing that there are multiple approaches to addressing this funding gap,
staff have explored and are recommending a multi-faceted approach, including $25 M ($5 M per year for 5
consecutive years) in reductions from other planned projects in the 10-year CI P, approximately$2.5 M in
savings based on updated financials and the balance coming from increased use of debt financing. While
the funding shortfall would affect the latter years of the project (3-4 years from now), it would be possible to
proceed with the Solids Project without immediately addressing this funding need, but staff recognizes that
it is preferrable to have a planning funding approach before proceeding with contract award. It should also
August 26, 2021 Special Board Meeting Agenda Packet- Page 11 of 30
Page 10 of 28
be noted that the contract award to the recommended contractor has notable "off ramps" language in the
specifications, including a value-engineering phase after which Central San can elect not to proceed for
convenience, after reimbursing the contractor for their time to conduct the value engineering phase only.
Staff has identified several of possible financing options approaches to eliminate the $77.5 M funding gap.
The updated financial assumptions provide approximately$2.5 M in cash funding. To reduce the funding
gap, a $25 M cut to the capital program for all scenarios, is proposed consisting of five years of$5 M per
year. The proposed reductions are as follows: $3 M from Collection System Sewer Renovation; $0.5 M
from Vehicle Replacement Program; and $1.5 M from Contingency. The funding approaches for the
remaining $50 M necessary for funding are summarized below.
Financial Plan Scenarios
Funding Option 1 - SRF Funding: Request additional SRF funds. Based on an update of the financial
plan, a total of$50 M of additional SRF borrowing would be required. This could be accommodated
without an increase in the scheduled rate increases foreseen prior to the SRF project cost increase.
Funding Option 2 - Issue Bonds: (certificates of participation)within 12 months. Bonds could be issued
to fund FY 2022-23 Capital Expenditures, freeing up cash that could be set aside for the Solids Project
funding gap 3-4 years from now(in FY 2024-25 and FY 2025-26). Based on an update of the financial
plan, a total of$53 M of additional bond borrowing would be required.
Funding Option 3 - Future Issuance of Bonds: Under this option, a bond issuance for Solids Project
funding would be needed in 3-4 years from now. This would require issuance of about$62 M of bonds
when funding was needed for FY 2024-25 through project completion in FY 2025-26 due. Under this
option, we are assuming higher interest rates.
Funding Option 4 - Explore Other Funding Sources: Staff have been monitoring the availability of
funding from federal sources, including potentially in the pending $1 trillion infrastructure bill, or through the
pre-existing Water I nfrastructure Finance and I nnovation Act (WI F IA). As to the latter, an assessment of
the W1 FIA program in 2018 led staff to conclude that the program did not hold value to Central San. Staff
have inquired with our financial consultant PFM to determine whether the program has changed since then
to make it more attractive.
Funding Option 5 - Cash Funding: If no additional borrowing was available or viewed as acceptable, an
increase in rates above those previously projected would be necessary to fund the increased costs.
RECOMMENDATIONS
E&O Committee Recommendations:
The status of the Solids Project and early discussions on some of the alternatives as presented by staff to
the E&O Committee at its August 17, 2021 meeting. No recommendations were made as staff is
presenting further discussion on the subject at the August 26, 2021 Board workshop.
Future Board Meeting Recommendations:
Staff will be presenting recommendations following the August 26, 2021 Board workshop at the
September 2, 2021 Board meeting. These recommendations may include the following Board actions:
A. Consider a staff proposed recommendation to award a construction contract, at a future meeting, to
Kiewit Infrastructure West co., the lowest responsive and responsible bidder in the amount of
$179,841,000;
August 26, 2021 Special Board Meeting Agenda Packet- Page 12 of 30
Page 11 of 28
B. Consider alternatives;
C. Consider staff proposed need for additional engineering support services during construction, including
existing agreement amendments and execution of two new agreements;
D.Authorizing the General Manager to execute Contract Documents subject to SRF funding, submittal
requirements; and
E. Include up to a 15-percent project contingency.
Strategic Plan Tie-In
GOAL TWO:Environmental Stewardship
Strategy 1—Achieve 100%compliance in all regulations, Strategy 2—Anticipate and prepare for potential regulatory
changes
GOAL THREE:Fiscal Responsibility
Strategy 1—Maintain financial stability and sustainability
GOAL FOUR: Workforce Development
Strategy 2—Foster relationships across all levels of Central San, Strategy 4—Meet or exceed industry safety
standards
GOAL FIVE:Infrastructure Reliability
Strategy 2—Execute long-term capital renewal and replacement program, Strategy 3—Protect personnel and assets
from threats and emergencies
GOAL SIX.Innovation and Optimization
Strategy 2—Improve and modernize operations through technology and efficiency measures
GOAL SEVEN:Agility and Adaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
ATTACHMENTS:
1. Project Location Map
2. Prior Board Actions Summary
3. Summary of Bids
4. Post Bid / Preconstruction Estimate
5. Presentation
August 26, 2021 Special Board Meeting Agenda Packet- Page 13 of 30
Page 12 of 28
o �
CD
O C
r-p. CLEARWELL
BASIN
a CP pQ
0 NORTH
10 BASIN
3 C31.t E�3 o °
3:3w �V1�0�'
• ,I FILTER p DRAIN BACK
PLANT CHANNEL
N
Q
0
0 400 800
FEET
a PROJECT AREA
CONSTRUCTION
SOUTH
ACCESS ROUTING NORTH BASIN O �O=�
O
CLARIFIERS� C?�V4U
0
AERATION SOLIDS CONTRACTOR
TANKS �J STAGING AREA
SOUTH
o CLARIFIERS
o �J SOLIDS
BUILDING
Q � O
1-5
ro O
o v
c
0
o PRIMARY
TANKS
a�
I
Attachment
Y CENTRAL SAN SOLIDS HANDLING FACILITY IMPROVEMENTS
N
' DISTRICT PROJECT 7348 1
Q
Page 13 of 28
ATTACHMENT 2
HISTORICAL BOARD ACTION SUMMARY
SOLIDS PROJECT, DISTRICT PROJECT 7348
Historical Board Action Summary:
As with all large projects, staff has been continually updated during the
development of the Solids Project. A list of prior Board actions are outlined below:
• December 1, 2016 - Board approved combining projects, predesign funding,
and a $2 million (M) Professional Engineering Services (PES) agreement
with Black & Veatch (B&V) for the pre-design efforts;
• December 15, 2016 - Board approved wet scrubber piloting work and
contracts;
• April 6, 2017 - Board approved air emissions testing consulting agreement to
support wet scrubber piloting;
• April 26, 2018 - Board approved amending the B&V agreement to include
final design services for an amount not to exceed $5.9 M;
• December 6, 2018 - Board approved resolution regarding funding eligibility
for State Revolving Fund (SRF) funding;
• December 20, 2018 - Board authorized the pre-selection and contracting for
the centrifuge equipment, cake pump equipment, and new wet scrubber
equipment;
• June 20, 2019 - Board authorized a construction contract for the Emergency
Sludge Loadout Facility Upgrades and amending the PES with B&V by
$220,000;
• December 19, 2019 - Board authorized a PES agreement with MWH
Constructors, Inc. (MWH) for an amount not to exceed $400,000 for
constructability review and pre-bid services;
• August 6, 2020 - Board authorized the General Manager to submit an
updated SRF loan application for additional funding and Board resolutions;
• August 20, 2020 - Board authorized increasing the B&V agreement to
$9,654,636 and the MWH agreement to $950,000; and
• February 18, 2021 - Staff presented a project update and announced
advertisement of project bidding. Additionally, the Board authorized the
General Manager to amend the MWH PES to a ceiling of $1.1 M and amend
the blanket agreement with Aresine Engineering to a ceiling of $975,000.
August 26, 2021 Special Board Meeting Agenda Packet- Page 15 of 30
Page 14 of 28
ATTACHMENT 3
SOLIDS HANDLING FACILITY IMPROVEMENTS
DISTRICT PROJECT 7348
SUMMARY OF BIDS
PROJECT NO.: 7348 NO. OF ADDENDA: 9 DATE/TIME: JUNE 16, 2021/12:00 PM
PROJECT NAME: SOLIDS HANDLING FACILITY IMPROVEMENTS
PROJECT MANAGER: NATHAN HODGES
PROJECT LOCATION: 5019 IMHOFF PLACE, MARTINEZ, CALIFORNIA
ENGINEER'S ESTIMATE: $130,000,000 - $140,000,000
NO. BIDDER BID PRICE
Kiewit Infrastructure West Co. $179,841,000
Fairfield, California
2 W.M. Lyles Co. $206,856,000
Fresno, California
3 Flatiron West Inc. $216,293,989
Benicia, California
BIDS OPENED BY /s/ Katie Young
DATE: June 16, 2021 at 12:30 p.m. via livestream due to COVID-19
August 26, 2021 Special Board Meeting Agenda Packet- Page 16 of 30
Page 15 of 28
ATTACHMENT 4
SOLIDS HANDLING FACILITY IMPROVEMENTS
DISTRICT PROJECT 7348
POST-BID/PRECONSTRUCTION ESTIMATE
No. Item Description Amounts %Construction
Cost
1. CONSTRUCTION
a. Construction Contract $179,841,000
b. Project Contingency at 15% (CM included) $27,000,000
c. Permits(Air Testing included) $1,000,000
d. Hazardous Compliance(Testing included) $700,000
e. ESLF Construction Completed(Not SRF Eligible) $2,866,000
SUBTOTAL-CONSTRUCTION $211,407,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
-Engineering staff(PM, RE, Safety,etc.) $6,000,000
-Operations Support, including Maintenance $5,000,000
b. Consultants
-MWH: Construction Management Services $12,000,000
-Hazardous Material Consulting $300,000
-Existing Electrical Support(Aresine&Carollo) $2,000,000
-B&V(ESDC) $4,000,000
-HDR(ESDC) $1,000,000
-Degenkolb(ESDC) $650,000
-Furnace Support(TBD) $650,000
-As-needed Services, Third-Party Review, QA/QC,VE $2,500,000
SUBTOTAL-CONSTRUCTION MANAGEMENT $34,100,000 16.1%
3. PREBID EXPENDITURES
a. Engineering
-District Staff Time(Engr.And Operations) $3,900,000
-B&V $9,600,000
-MWH $1,100,000
-Other Consultants $720,000
-Equipment Selection Procurement $496,000
-Regulatory Permits $50,000
SUBTOTAL-PREBID EXPENDITURES $15,866,000 7.5%
4. TOTAL ESTIMATED PROJECT COST 1 $261,373,000
August 26, 2021 Special Board Meeting Agenda Packet- Page 17 of 30
(Handout)
Updated as
presented
SOLIDS HANDLING FACILITY IMPROVEMENTS
11
DISTRICT PROJECT 7348
PROJECT STATUS
Special Board Workshop
August 26, 2021
Jean-Marc Petit, P.E.
Director of Engineering and Technical Services
s,
Edgar J. Lopez, P.E.
Capital Projects Division Manager
1
WORKSHOP AGENDA
• Why are we doing this project?
• Project Background and Description
• Big Issues to discuss are:
• 1 ) Higher cost for the proposed project
• 2) What are the Alternatives?
• 3) What is(are) best path(s) forward?
Future Board Actions
CENTRALSAN
z
1
WHY ARE WE DOING THIS PROJECT?
• Treatment plant has several key process areas:
1. Liquid Treatment
2. Recycled Water Treatment and Distribution
!Solids Handling and Dispos
4. Energy Production
-
•�.
-ms's.
lRems
3
SOLIDS HANDLING FACILITY IMPROVEMENTS
(SOLIDS PROJECT PHASE 1 ) DESCRIPTION
1 2 2 3 4 5 6 7 8 Completed related
r
O • eects
Emergency Sludge
Loadout
• Emergency exterior
stairways
Digester demolition
EXISTING SLUDGE MULTIPLE AIR POLLUTION ASH HANDLING ELECTRICAL CENTRIFUGE
SOLIDS
DIGESTER BLENDING/ HEARTH
CONTROL AND LOADOUT SYSTEMS DEWATERING CONDITIONING
DEMOLITION STORAGE FURNACES SYSTEM BUILDING
SEISMIC
RETROFIT
4
4
2
PROJECT BACKGROUND
• Elements of the project in CIBs prior to 2017
•Comprehensive Wastewater Master Plan (2017)
•Current FY 21-22 CIB and 10-Yr CIP:
• Solids Phase 1: Improvements to the Solids Handling Facilities
DP-7348: $183.9 M (+ $77M = $261.4M)
• Steam System Improvements DP 7349: $35AM
• MHF Hearth Replacement DP 100009: $1 M
• Replace Co-Gen System: $25.4 M
• Other Solids facilities Improvement Projects: e.g.; DAFT: $2.41VI
• Future Solids Related Projects beyond 10-Yr :
• Solids Phase 2:Add two Anaerobic Digesters with Digester Gas
CO-Gen: $126.8M
• Solids Phase 3:Add two additional Anaerobic Digesters and a
Fluidized bed incinerator(And abandon existing MHFs): $175.4M
� 5
5
CWMP LONG-TERM PATH FOR SOLIDS
HANDLING AT CENTRAL SAN IN 2017
efurbish
Multiple Add Anaerobic
Hearth Digestion and
Furnaces, $66.4 M $112 M Biogas Co-Gen.
continue with
Steam and
Co-Gen with
Natural Gas
6
3
RE-EVALUATE LONG-TERM PATH FOR
SOLIDS HANDLING AT CENTRAL SAN
Alternative 1:Award based Alternative 3 A or B: Re-
on Contractor Design Assist Evaluate Long-Term Solids
and reduce risk after VE Handling
Refurbish All New Project:
Multiple $261,4 M --Anaerobic
Hearth Digestion and
Furnaces, —7 Biogas Co-Gen.
continue with Abandon Steam.
Steam and Convert to all
Co-Gen with Electric Blowers
Natural Gas
ww
Evaluate both = _
paths before
NTP for
constructionCENTRALSAN
I
7
SOLIDS PROJECT IS VERY COMPLEX AND
RENOVATES AN OPERATING FACILITY WITH ALL
THE SOLIDS AND POWER ELEMENTS OF THE
TREATMENT PLANT
i
II
m,
8
4
PRE-QUALIFIED GENERAL CONTRACTORS AND
ELECTRICAL SUBCONTRACTORS
General Contractors: Electrical Subcontractors:
• Balfour Beatty Infrastructure, Inc. • Blocka Construction, Inc.
• Flatiron West, Inc. • Con J. Franke Electric, Inc.
• Kiewit Infrastructure West Co. • Contra Costa Electric, Inc.
(Kiewit) • Helix Electric, Inc.
• C. Overaa&Co. • Mass Electric Construction Co. (A
• Shimmick Construction Company, Kiewit Company)
Inc. • San Joaquin Electric, Inc.
• Walsh Construction • Shimmick Construction Company, Inc.
• W. M. Lyles Co. • Sprig Electric Co.
3 Bidders
CENTRAL SAW
9
BID SUMMARY
Bid Opening: June 16,2021,2:30 PM
Engineer's Estimate: $130,000,000-$14D,000,000
No. Bidder Co- Total Bid
1 Kiewit Infrastructure West Co. $179,841,D00
2 W.M.Lyles Co. $206,856,D40
3 Flatiron West Inc. $216,293,989
r 10
CENTRAL SAN
10
5
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
CIB Budget Comments Construction Progression of
Esti mate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 7$ 66,439 000 Master Plan $51.4 M Blendin ,etc.
AwlCENTRALSAN
11
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
�Wet Comments ttr.uctioVP�Progression of
JL Ls
a ate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 $ 66,439,000 Master Plan $51.4 M Blending,etc.
Scrubber pilot testing;
More Electrical,Instrumentation
FY 18-19 $ 82100 000 30%Design $63.0 M and Controls EI&C Identified
iL
12
6
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
CIB Budget Comments Construction Progression of
Estimate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 $ 66,439 000 Master Plan $51.4 M Blending,etc.
Scrubber pilot testing;
More Electrical,Instrumentation
FY 18-19 $ 82100 000 30%Design $63.0 M and Controls EI&C Identified
New Ash building,Smart MCC
equipment,upgrades to ESLF
FY 19-20 $ 93,376,000 50%Design $85.9 M and other side projects
13
CENTRALSAIN
13
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
t Comments MnstructioW�Progression of
jilligstimate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 $ 66,439,000 Master Plan $51.4 M Blending,etc.
Scrubber pilot testing;
More Electrical,Instrumentation
FY 18-19 $ 82100 000 30%Design $63.0 M and Controls EI&C Identified
New Ash building,Smart MCC
equipment,upgrades to ESLF
FY 19-20 $ 93,376,000 50%Design $85.9 M and other side projects
Long time to complete this
Design.QA/QC concerns on
EI&C.Added constraints and
FY 20-21 $ 128,234,000 90%Design $97.3 M Sequencing
*Confirmed notification of a SRF Loan for$89.6M for construction
14
7
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
CIB Budget Comments Construction Progression of
Estimate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 $ 66,439 000 Master Plan $51.4 M Blending,etc.
Scrubber pilot testing;
More Electrical,Instrumentation
FY 18-19 $ 82100 000 30%Design $63.0 M and Controls EI&C Identified
New Ash building,Smart MCC
equipment,upgrades to ESLF
FY 19-20 $ 93,376,000 50%Design $85.9 M and other side projects
Long time to complete this
Design.QA/QC concerns on
EI&C.Added constraints and
FY 20-21 $ 128,234,000 90%Design $97.3 M Sequencing
FY 21-22 CIB Added more constraints,longer
i
tApprov d
t project duration,and partial
Building Shutdown for MHFs
L
,984,000 1100%estimate $110.0M Temporary Power
d increase in funding for SRF Loan:$173.1 M
1s
15
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
t Comments Construct!oW�Progression of
Estimate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 $ 66,439,000 Master Plan $51.4 M Blending,etc.
Scrubber pilot testing;
More Electrical,Instrumentation
FY 18-19 $ 82100 000 30%Design $63.0 M and Controls EI&C Identified
New Ash building,Smart MCC
equipment,upgrades to ESLF
FY 19-20 $ 93,376,000 50%Design $85.9 M and other side projects
Long time to complete this
Design.QA/QC concerns on
EI&C.Added constraints and
FY 20-21 $ 128,234,000 90%Design $97.3 M Sequencing
Added more constraints,longer
project duration,and partial
Building Shutdown for MHFs
FY 21-22 $ 183,984,000 100%estimate $110.0 M Temporary Power
Sludge Hauling&Disposal,
Electrical work for Existing
systems,9Addenda
Revised in bid clarifications,significant
period $ 183,984,000 Per Addenda $140.0 M escalation increases.
CENTRALSAN
16
8
REVIEW OF PROJECT COST ESTIMATE
PROGRESSION AND INCREASES
Cl Budget/Total Comments Construction Progression of
Pirloject Budget Estimate Scope Elements
Baseline—Scrubbers,
Dewatering,Seismic,Ash,
FY 17-18 $ 66,439,000 Master Plan $51.4 M Blending,etc.
Scrubber pilot testing;
More Electrical,Instrumentation
FY 18-19 $ 82,100,000 30%Design $63.0 M and Controls EI&C Identified
New Ash building,Smart MCC
equipment,upgrades to ESLF
FY 19-20 $ 93,376,000 50%Design $85.9 M and other side projects
Long time to complete this
Design.QA/QC concerns on
EI&C.Added constraints and
FY 20-21 $ 128,234,000 90%Design $97.3 M Sequencing
Added more constraints,longer
project duration,and partial
Building Shutdown for MHFs
FY 21-22 $ 183,984,000 1009/6estimate $110.0 M Temporary Power
Sludge Hauling&Disposal,
Electrical work for Existing
systems,9 Addenda
Revised in bid clarifications,significant
�rI Deriod I$ 213,984,000 1 Per Addenda 1 $140.0 M I escalation increases.
,7 iii Current Estimate $179.8 M None
17
i=
PRICE INCREASES AND DIFFERENCES
• Reasons for increased costs since FY 21-22 Budget:
• 1,460 Days or over 4 years of Construction
• Impact of Construction Sequencing from Seismic Improvements
• Very Detailed Project Construction Constraints and Milestones
• MHFs Shut Down for 12 months and additional 6 months requires
temporary sludge hauling-$19 M
• Deferred Design:
• Pipe and Electrical Conduits Supports and routing
• Temporary Shoring Design for Seismic Walls
• Ash system and metal building
• Existing Electrical Systems issues
• Electrical on critical path is very complex and increased the project risk
• Limited number of bidders—Only three GCs and two electrical
subcontractors
• Included major temporary electrical system as part of sequencing
• Bid Market Impacts
• Global Supply Disruption during COVID-19
One of a Kind Project Bid in Difficult Times and Volatile Market l
r 1s
CENTRAL SAN
18
9
POST BID/PRE-CONSTRUCTION ESTIMATE
No. Itsln De"llptlon Allloilnts Y.Conarructlon
cost
1 CONSTRUCTION
a.Conatrriclion Coftwt 5179,841,000
11.PWja"Coriingancy at 15%(CM included) $27.000.000
C.permits(Air Testing lnclmw) $1,000,000
d.H—rdoua Complia nca(T—tirg intruded) $700,000
e.ESLF Coriatruction Completed(Nor SRF Eligible) 52.866.000
SUBTOTAL-CONSTRUCTION 5211-007900 100%
2. CONSTRUCTIONMANAGEMENT
P.Dk9Wt Farces
-Engineering staff(PM,RE,Safety,e1c.) 58,000,000
-Operon—Support,includ ing Maimanarica 55,000,000
6.Con. nte
-M1NH:Canatruction Ma nagem em Se ima $12,00,000
-Hazardous Material Consulting S300,0o0
-Existing Electrical Support(Aresine&Carollo) $2,000,000
-88V(ESDC) 54,000,000
-H DR[E SDC] 51,000,000
-Degii.mlt(ESRC) .650,000
-Fumace Support(TBID) $850,000
-Rs-needed Services,Tnap•Parry Renevr,n4IG1C,VE 52.500.000
SUBTOTAL-CONSTRUCTION MANAGEM ENT $34.100.000 16.14:
3. PREBID EXPENDITURES
P Engineering
-DlstrlG crUtf Tlme[Ergr.And Operawnsi 53,900,000
-B&V $9,60,000
-MLYH 51,100,000
-00wr Coneullants 5720,000
-
Equi pme nt SelecW Procure mem S N.000
-Regulatory Permit& s59.009
SUBTOTAL-PREBID EXPENDITURES 515.866.000 75'n.
1, TOTAL ESTIMATED PROJECT COST $2&1,973,000
` 19
CENTRAL SAN
19
PROJECT CONTINGENCY DETAILS
• Staff is requesting to budget 15% Contingency
• Breakdown for needing 15% or $27 Million (M):
• 5% or$9 M is Standard Allowance for change orders;
• 5% or$9 M due to major renovation and project complexity
• 5% or$9 for the following:
• Regulatory changes based on MACT 50% rule ($5 M)
• Additional staffing costs due to CO's and MACT 50 or
engineering costs to support project($4 M)
• Staff will re-evaluate the Contingency required prior to
issuing Notice to Proceed for Construction.
USEPA Rule 129 MACT: Maximum Achievable Control Technology `
09`zo
IM CENTRAL SAN
20
10
129 RULE 50% COST TRIGGERS
Zero Hearth for CO limits CD
�WESP fo
2.5�o
iFsr
° a ° -`�'r
c] r,•
n e n
• Q i 0
W
n s °
u 9 c b gran ..................
WNY ........................
i to ry p
21
'odglnallV classified as likely exempt,reclassifietl as exempt
included in Solids Handling Protea
originally clazsifiM asnon-exempt,reclassifetl as exempt,reclassrfietl again as nan-exempt
originally classified as exempt,reclassified asnon-exempt
ZL
FISCAL YEAR (FY) 2021 -22
CAPITAL IMPROVEMENT BUDGET
Solids Handling Facility Improvements Budget
® Budget-to- FY 2021-22 FY 2022-23 Future FYs Total
Date
® $1,000,000 $- $- $- $1,000,000
® 12,090,000 - - - 12,090,000
® 6,894,000 21,000,000 45,000,000 98,000,000 170,894,000
® $19,984,000 $21,000,000 $45,000,000 $98,000,000 $183,894,000
Central San has applied for a SRF Loan for up to$173.1 M
22
11
PROJECT FINANCING
• FY 2021-22 Budget:............ $ 183.9 M
Total Estimated Project Cost: $ 261.4 M
Overall Variance: ($ 77.5 M)
v, P"//
5JA
23
FINANCIAL PLANNING ASSUMPTIONS
In preparation for the workshop,staff updated the long-term financial plan
to evaluate several scenarios related to funding options for the Solids
project.
Some of the general assumption updates include:
• UAAL eliminated, and debt service on 2021 COPs
• Anticipated COLAs per anticipated MOUS
• Other inflation assumptions updated
• $15.9 million of previously funded costs(pre-bid expenditures for
planning and design)of the Solids Handling Project will be reimbursed
from the existing$173.1 million SRF loan.
• $25 million cut to the 10-year CIP or five years of$5 million per year.
o$3 million from Collection System Sewer Renovation;
o$0.5 million from Vehicle Replacement Program;and
1.5 million from CIB Contingency.
24
12
WE HAVE OPTIONS TO FUND
SOLIDS PROJECT FUNDING GAP
(Each option includes a proposed reduction of$25 million CIP)
PREFERRED APPROACHES
1. Request an additional$50M from SRF loan. No sewer service rate
impacts above what is currently planned.
2. Issue$53M in revenue bonds or certificates of participation to fund
FY 2022-23 Capital Expenditures,freeing up cash that could be set
aside for the Solids project funding gap . No sewer service rate
impacts above what is currently planned.
Not Recommended
3. Cash finance the funding gap through increased sewer service rates
with additional 1.75%for each of four years for a total increase of
7%
4. Defer another$50M in projects in the ten-year Cl P.
25
ALTERNATIVES
• Alternative 2:Reiect Bids
• A)Rebid the Proiect:Staff would conform all the addenda with
the contract documents,evaluate and incorporate more ways to
reduce risks to the contractor and rebid within 6-9 months.
• B)Rebid within Approved Budget:Staff could repackage and
rebid the project to proceed within the$183.9 M budget and add
a future project(s)to complete the remainder of the scope.
• C)Consider Design-Build Project Delivery:Staff could
evaluate alternative delivery to complete the project using Not Recommended
design-build and use the existing Solids Project's bid documents
as the basis.
• D.)Repackage Proiect in Multiple Phases:Staff could split
and implement the Solids Project scope into multiple phases.
This would include rebidding in various smaller projects which
could be implemented in either two or up to six phases and take
more years to complete. (Could be evaluated further if all other
alternatives are not pursued.
r 2C
CENTRAL SAN
26
13
ALTERNATIVES
• Alternative 1:Award the Contract Award the project to Kiewit but —
proceed with a multi-step NTP. Evaluate and review project value -
engineering(VE),including sequencing,milestones,costs,and
more ways to reduce risks for the contractor and Central San.Staff
will report back prior to issuing a NTP for construction.
Board I
workshop
Board Incorporate VE&
NTP-1 workshopBegin
Field Verifications NTP-2 Construction
Award Project Conduct a VE per Contract;Order
long lead Equip.
Shop Drawings
Off Ramp
Terminate for Off Ramp
Convenience `27
CENTRALSAN
27
ALTERNATIVES (CONTINUED)
• Alternative 3:Alternative Lona-Term Approach
• Alternative 3(A):Evaluate an Alternative Long-term Solids
Handling Approach including Anaerobic Digestions with all new
Solids Facilities:Staff recommends re-evaluating the long-term
solids handling from current operations based on furnaces,ash
disposal and steam recovery to including or changing to anaerobic
digestions based on the higher costs of the Solids Project.
• Alternative 3(B):Evaluate an Alternative Long-term Solids
Handling Approach including Anaerobic Digestions using a P3
Approach:Like Alternative 3(A),staff recommends re-evaluating the
long-term solids handling from current operations based on furnaces,
ash disposal and steam recovery to anaerobic digestions using a P3
approach and use green energy.Anaergia currently evaluating land
lease.
CIENTRALSAN
28
14
RE-EVALUATE LONG-TERM PATH FOR SOLIDS HANDLING AT CENTRAL SAN
Alternative 1:Award based Alternative 3 A or B: Re-
on Contractor Design Assist Evaluate Long-Term Solids
and reduce risk after VE Handling
Refurbis All New Project:
Multiple --Anaerobic
Hearth Digestion and
Furnaces, - Biogas Co-Gen.
continue with `�� Abandon Steam.
Steam and Convert to all
Co-Gen with Electric Blowers
Natural Gas
Evaluate both = __
paths before
NTP for
construction
29
FY2024.25 FY2025.26
Bid and Award
NTP-1:Solids Handling Phase
1 Optimization VE with Kiewit
Alternative Long-Term Solids
Handling Alternatives l�
Evaluation
Board decision on Alternative
Path for Long-Term Solids IF
Handling
NTP-2:for Construction M
Construction
July 2021 July 2022 July 2023 July 2024 July 2025 July 2026
Q Bid and Award:February 22,2021—September 2,2021
NTP-1:Solids Handling Contract review with Kiewit and Engineering:October 2021—Feb.2022
Alternative Long-Term Solids Handling Alternatives Evaluation:September 2021—Feb.
2022
- Update Board in Feb.2022 and request approval for construction or Off Ramp
NTP-2:Proceed with Kiewit for Solids Handling Phase 1 Construction:March 2022
Construction Phase:March 1,2022—February 28,2026(1,460 Days) `
CENTRAL SAN
30
15
PROJECT SUPPORT NEEDED
• Construction Management: MWH Constructors, Inc.
• Engineering Services During Construction:
• Black & Veatch: Civil, Mechanical, HVAC, Electrical
Instrumentation and Control Engineering (EAC)
• HDR, Inc.: Architectural, Structural, and As-Needed
• Degenkolb: Seismic Design
• Aresine Engineering: Assist Capital Projects with Review
of Electrical and Controls Items and Questions
• (TBD): Furnace and Air Pollution Control
• Others: Central San will be using As-Needed Engineering
31
MUT-72TV"M
31
FUTURE RECOMMENDATIONS FOR BOARD ACTION
1. Award of a construction contract in the amount of$179,841,000 to
Kiewit Infrastructure West Co., the lowest responsive and
responsible bidder, for the construction of the Solids Handling
Facility Improvements, District Project 7348.
2. Authorize the General Manager to execute five new agreements:
a) MWH Constructors, Inc. at a cost not to exceed $12.0 million for
construction management services.
b) Black&Veatch Corporation at a cost not to exceed $4.0 million
for engineering support during construction.
c) Aresine Engineering at a cost not to exceed $1.5 million for
electrical engineering support.
d) HDR, Inc. at a cost not to exceed $1.0 million.
e) Degenkolb Engineers at a cost not to exceed $650,000.
3. Authorize the General Manager to execute Contract
Documents subject to SRF funding, submittal
requirements, and include up to a 15-percent project
contingency. l
l 32
- CENTRAL SAN
32
16
QUESTIONS?
�J
33
CENTRALSAN
17