HomeMy WebLinkAbout08. Award a construction contract for North Orinda Sewer Renovations-Phase 8, DP 8463 Page 1 of 7
Item 8.
CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
MEETING DATE: AUGUST 19, 2021
SUBJECT: AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $2,838,000
TO K.J. WOODS CONSTRUCTION, INC., THE LOWEST RESPONSIVE AND
RESPONSIBLE BIDDER FOR THE NORTH ORINDA SEWER
RENOVATIONS, PHASE 8, DISTRICT PROJECT 8463; FIND THAT THE
PROJECT IS EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL
QUALITYACT; AND AUTHORIZE UP TO A 15-PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
JASON FITCH, ASSOCIATE ENGINEER ENGINEERING AND TECHNICAL SERVICES-
CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
The General Manager also needs authorization to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency for the project.
BACKGROUND
Novel Coronavirus (COVID-19) Impact: In the midst of COVI D-19, Central San continues construction
activities as an essential service and infrastructure provider under guidelines provided by Contra Costa
Health Services, Occupational Safety and Health Administration, state, and federal agencies. Several sites
in this project include work on private properties and public rights-of-way. The construction contract
August 19, 2021 Special Board Meeting Agenda Packet- Page 40 of 77
Page 2 of 7
includes strict provisions to mitigate the spread of COVI D-19, such as personal protective equipment,
handwashing stations, and other safety items, practices, and procedures as guidelines become more
restrictive or lessen.
The North Orinda Sewer Renovations, Phase 8, District Project 8463 (Project) is part of the Collection
System Program of the Capital Improvement Budget (CI B). Its aim is to replace or rehabilitate
deteriorated sewer infrastructure at the end of its useful life and in poor condition. The construction work is
coordinated with local jurisdictions, cities, utilities, private property owners, and tenants.
This Project will replace or rehabilitate approximately 9,900 feet of small 6-to 8-inch diameter sewer
mains, utility access holes, and other work within public rights-of-way and private easements. Staff
prepared the plans and specifications for the Project. Construction methods primarily include open trench
and pipe bursting. Attachment 1 provides an overview map of all the site locations.
The Engineer's estimate for construction was $3,800,000. The Project was advertised on July 19 and 26,
2021. Seven bids ranging from $2,838,000 to $4,185,210 were received and publicly opened on August
5, 2021. The Capital Projects Division conducted a technical and commercial review of the bids and
determined that K.J. Woods Construction, Inc. (K.J. Woods) is the lowest responsive and responsible
bidder with a total bid amount of $2,838,000. The bid submitted by K.J. Woods did contain a discrepancy
in providing all wet signatures; however, staff considers this discrepancy as immaterial as K.J. Woods
clarified that this was a clerical error. Attachment 2 provides a summary of the bids received.
Central San will administer the construction contract and provide construction management, resident
engineering, survey, administration, and submittal review. Central San has engaged a consultant under an
existing agreement to provide inspection services.
California Environmental Quality Act (CEQA)
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15302. It involves the replacement of existing facilities at the same locations and with the same purpose
and level of activity as the facilities being replaced. Any capacity increases are for non-growth inducing, wet
weather purposes. The Project also is exempt under Central San CEQA Guidelines Section 15061(b)(3),
since there is no possibility that the Project may have a significant effect on the environment. This certainty
is based on Central San's experience with numerous sewer construction projects of this nature, the
relatively short distances involved, and Central San's mitigating construction specifications. These
specifications are standardized general and special conditions in the Project bid documents to address
environmental considerations, such as protecting trees and riparian areas. They comply with applicable
federal, state, county, district, municipal and local laws, ordinances, orders, and regulations. Approval of
this Project will establish the Board's independent finding that this Project is exempt from CEQA.
ALTERNATIVES/CONSIDERATIONS
Central San staff spent a significant amount of time coordinating the Project work with the private property
owners, public, City of Orinda, California Department of Fish and Wildlife, and California Water Boards.
Delaying or postponing the sewer work is not recommended.
An alternative would be to reject all bids, which is also not recommended.
FINANCIAL IMPACTS
The total estimated Project cost is $4,304,000. The cost includes planning, design, bid price, contingency,
construction management, staff, and consultant costs as detailed in Attachment 3. The Project budget of
$5.3 million is shown on page 217 of Central San's Fiscal Year 2021-22 Budget. Staff will transfer the
approximate $1 million savings for the Project to the Cl B Contingency account.
August 19, 2021 Special Board Meeting Agenda Packet- Page 41 of 77
Page 3 of 7
Staff recommends a 15-percent contract contingency on this Project. The contingency would cover
additional urgently needed repairs or replacement of nearby sewers and for any unforeseen conditions that
may be encountered during the renovation work.
COMMUNITY OUTREACH
Central San staff did extensive homeowner outreach to prepare residents for the upcoming construction
work. Initial Project letters were sent in the summer of 2021 informing residents of the design work.
Throughout the course of design, staff addressed email and phone inquiries about the Project and
conducted face-to-face outreach with several easement homeowners. Due to COVI D-19, staff was
creative in preparing residents for construction. I n place of a public meeting, staff supplied a video
presentation on the Central San website. Additionally, the public was encouraged to reach out with any
other questions or concerns. To date, all questions and concerns received have been answered and
addressed.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on August 10, 2021 and
recommended approval.
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of $2,838,000 to K.J. Woods Construction, Inc., the
lowest responsive and responsible bidder for the North Sewer Renovations, Phase 8, District
Project 8463; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency.
Strategic Plan re-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL FIVE: Infrastructure Reliability
Strategy 2—Execute long-term capital renewal and replacement program, Strategy 3—Protect personnel and assets
from threats and emergencies
GOAL SEVEN:Agility andAdaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
August 19, 2021 Special Board Meeting Agenda Packet- Page 42 of 77
Page 4 of 7
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post Bid/P reconstruction Estimate
August 19, 2021 Special Board Meeting Agenda Packet- Page 43 of 77
Page 5 of 7
North Orinda Sewer Renovations Phase 8
District Project 8463
Map Date:7/22/2021
t Br/o'�eS Rosen oir Martinez
.� Illllllllll� I
5°
c
�i�° • Pleasant Hill
Detail
Area qu
Walnut
�aCreek
Orinda
Lafayette
8463 Lombardy,
Miner-Rd
m`
U
� �Espiral
o�
do m
� 8463
8463CD
N
8463 C
8463 Canon
c:U
�T �a
8463 0� 8463 �aties 6�
ay
�c
d
Project Location and Number
Note: 0 1,000 2,000 Map Displayed in North American Datum of 1983 Attachment
Central San data as of July 2021. Feet California State Plane,Zone III FIPS 0403,US Feet 1
August 19, 2021 Special Board Meeting Agenda Packet- Page 44 of 77
Page 6 of 7
ATTACHMENT 2
NORTH ORINDA SEWER RENOVATIONS, PHASE 8
DISTRICT PROJECT 8463
SUMMARY OF BIDS
PROJECT NO.: 8463 NO. OF ADDENDA: 1 DATE/TIME: AUGUST 5, 2021/12:00 PM
PROJECT NAME: NORTH ORINDA SEWER RENOVATIONS, PHASE 8
PROJECT MANAGER: JASON FITCH
PROJECT LOCATION: CENTRAL SAN SERVICE AREA
ENGINEER'S ESTIMATE: $3,800,000
NO. BIDDER BID PRICE
K.J. Woods Construction, Inc. $2,838,000
San Francisco, California '
Cratus, Inc.
2 San Francisco, California $3,182,625
3 D'Arcy and Harty Construction, Inc. $3,257 426
San Francisco, California '
4 California Trenchless, Inc. $3,637,730
Hayward, California
5 Bay Pacific Pipelines, Inc. $3,959,576
Novato, California
Ranger Pipelines, Inc.
6 San Francisco, California $4,093,101
Precision Engineering, Inc.
7 San Francisco, California $4,185,210
BIDS OPENED BY: /s/Katie Young
DATE: August 5, 2021
August 19, 2021 Special Board Meeting Agenda Packet- Page 45 of 77
Page 7 of 7
ATTACHMENT 3
NORTH ORINDA SEWER RENOVATIONS, PHASE 8
DISTRICT PROJECT 8463
POST-BID/PRECONSTRUCTION ESTIMATE
% Of
Item Description Amounts Construction
No. Cost
1. CONSTRUCTION
a. Construction Contract $2,838,000
b. 15% Contingency $426,000
c. Permits $50,000
SUBTOTAL - CONSTRUCTION COST $3,314,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management $190,000
- Public Relations/Right-of-Way $30,000
- Operations (Collection System Operations) $30,000
b. Consultants
- Inspection (including geotechnical and structural) $190,000
- Material Testing/Arborist/Others $40,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $480,000 14%
3. PREBID EXPENDITURES
a. Engineering (Design, Survey, Right-of-Way, Drafting) $510,000
SUBTOTAL - PREBID EXPENDITURES $510,000 15%
4. TOTAL ESTIMATED PROJECT COST $4,304,000
August 19, 2021 Special Board Meeting Agenda Packet- Page 46 of 77