HomeMy WebLinkAbout04.a. Review draft Position Paper to award a construction contract in the amount of $3,117,488 to Basset Engineering, the lowest responsive and responsible bidder for the Walnut Creek Sewer Renovations, Phase 15, District Project 8465; find that the proj Page 1 of 6
Item 4.a.
Algi CENTRAL SAN BOARD OF DIRECTORS
POSITION PAPER
DRAFT
MEETING DATE: JUNE 1, 2021
SUBJECT: REVIEW DRAFT POSITION PAPER TO AWARD A CONSTRUCTION
CONTRACT IN THE AMOUNT OF $3,117,488 TO BASSET ENGINEERING,
THE LOWEST RESPONSIVE AND RESPONSIBLE BIDDER FOR THE
WALNUT CREEK SEWER RENOVATIONS, PHASE 15, DISTRICT
PROJECT 8465; FIND THAT THE PROJECT IS EXEMPT FROM THE
CALIFORNIA ENVIRONMENTAL QUALITYACT (CEQA); AND AUTHORIZE
UP TOA 15-PERCENT CONTINGENCY
SUBMITTED BY: INITIATING DEPARTMENT:
DAMASIO ZEPEDAARAGON, ASSOCIATE ENGINEERING AND TECHNICAL SERVICES-
ENGINEER CAPITAL PROJECTS
REVIEWED BY: SASHA MESTETSKY, SENIOR ENGINEER
EDGAR J. LOPEZ, CAPITAL PROJECTS DIVISION MANAGER
JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
ISSUE
The Board of Directors (Board) must award the contract or reject bids within 50 days of the bid opening.
The General Manager also needs authorization to execute the Contract Documents subject to submittal
requirements including up to a 15-percent contingency.
BACKGROUND
The Walnut Creek Sewer Renovations, Phase 15, District Project 8465 (Project) is part of the Collection
System Program of the Capital Improvement Budget (Cl B). Its aim is to replace or rehabilitate
deteriorated sewer infrastructure at the end of its useful life and in poor condition. The construction work is
coordinated with local jurisdictions, cities, utilities, private property owners, and tenants.
I n the midst of the novel coronavirus (COVI D-19), Central San continues construction activities as an
essential service and infrastructure provider under guidelines provided by Contra Costa Health Services,
Occupational Safety and Health Administration, state and federal agencies. Several sites in this Project
include work on private properties and public rights-of-way. The construction contract includes strict
provisions to mitigate the spread of COVID-19, such as personal protective equipment, handwashing
June 1, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 3 of 10
Page 2 of 6
stations, and other safety items, practices, and procedures as guidelines stricken or lessen.
The Project will replace or rehabilitate approximately 9,300 feet of small 6-to 8-inch diameter sewer
mains, utility access holes, and other work within public rights-of-way and private easements. Central San
staff prepared the plans and specifications for the Project. Construction methods primarily include open
trench, pipe bursting, and cured-in-place pipe. Attachment 1 provides an overview map of all the site
locations.
The Engineer's estimate for construction was $4,000,000. Central San advertised this Project on May 4
and 11, 2021. Central San received seven bids ranging from $3,117,488 to $4,698,191 and publicly
opened them on May 25, 2021. The Capital Projects Division conducted a technical and commercial
review of the bids and determined that Basset Engineering (Basset) is the lowest responsive and
responsible bidder with a total bid amount of$3,117,488. Basset is a new general contractor to Central
San, and references were provided and verified by staff. Basset has completed similar work in the San
Francisco BayArea and is listed as a pre-qualified sewer contractor for the San Francisco Public Utility
District. Attachment 2 supplies a summary of the bids received.
Central San will administer the construction contract and provide construction management, resident
engineering, survey, administration, and submittal review. Central San has engaged a consultant under an
existing agreement to provide inspection services.
CEQA
Staff has concluded that this Project is exempt from CEQA under Central San CEQA Guidelines Section
15302. It involves the replacement of existing facilities at the same locations and with the same purpose
and level of activity as the facilities being replaced.Any capacity increases are for non-growth inducing,
wet weather purposes. The Project also is exempt under Central San CEQA Guidelines Section
15061(b)(3), since there is no possibility that the Project may have a significant effect on the environment.
This certainty is based on Central San's experience with numerous sewer construction projects of this
nature, the relatively short distances involved, and Central San's mitigating construction specifications.
These specifications are standardized general and special conditions in the Project bid documents to
address environmental considerations, such as protecting trees and riparian areas. They comply with
applicable federal, state, county, district, municipal and local laws, ordinances, orders, and regulations.
Approval of this Project will establish the Board's independent finding that this Project is exempt from
CEQA.
ALT ERNAT IVES/CONSIDERAT IONS
1. Delay or postpone the work. Staff has coordinated the Project with private property owners, the
public, utilities and cities, and does not recommend this option.
2. Reject all bids. Staff does not recommend this either.
FINANCIAL IMPACTS
The total estimated Project cost is $4.68 million. The cost includes planning, design, bid price,
contingency, construction management, and consultant costs as detailed in Attachment 3. The Project
budget is also shown on page 219 of Central San's Fiscal Year 2021-22 Budget at$5.4 million.
Staff recommends a 15-percent contract contingency on this Project. The contingency would cover
additional urgently needed repairs or replacement of nearby sewers and the risks associated with
renovation work.
Presently, staff does not foresee any added budgetary impact on this Project due to COVI D-19.
June 1, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 4 of 10
Page 3 of 6
COMMUNITY OUTREACH
Central San staff did extensive homeowner outreach to prepare residents for the upcoming construction
work. I nitial Project letters were sent in the summer of 2020 informing residents of the design work.
Throughout the course of design, staff addressed email and phone inquiries about the Project and
conducted face-to-face outreach with several easement homeowners. Due to COVI D-19, staff was
creative in preparing residents for construction. In place of a public meeting, staff supplied a video
presentation on the Central San website.Additionally, the public was encouraged to reach out with any
other questions or concerns. To date, all questions and concerns received have been answered and
addressed.
COMMITTEE RECOMMENDATION
The Engineering and Operations Committee reviewed this matter at its meeting on June 1, 2021, and
recommended
RECOMMENDED BOARD ACTION
Staff recommends the following:
1. Find that the Project is exempt from CEQA;
2. Award a construction contract in the amount of$3,117,488 to Basset Engineering, the lowest
responsive and responsible bidder for the Walnut Creek Sewer Renovations, Phase 15, District
Project 8465; and
3. Authorize the General Manager to execute the Contract Documents subject to submittal
requirements and include up to a 15-percent contingency.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service, Strategy 2—Maintain a positive reputation
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100%compliance in all regulations
GOAL FIVE:Infrastructure Reliability
Strategy 2—Execute long-term capital renewal and replacement program, Strategy 3—Protect personnel and assets
from threats and emergencies
GOAL SEVEN:Agility and Adaptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
ATTACHMENTS:
1. Project Location Map
2. Summary of Bids
3. Post-Bid/P reconstruction Estimate
June 1, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 5 of 10
CENTRAL SAN
• I
yette
Moraga
680 � �. � , :. �•,� o •• i
24 L .
ct Location and Number
Note: Map Displayed in North American Datum of 1983 Attachment
Central San data as of May 2021. California State Plane,Zone III FIPS 0403,US Feet 1 1
Page 5 of 6
ATTACHMENT 2
WALNUT CREEK SEWER RENOVATIONS, PHASE 15
DISTRICT PROJECT 8465
SUMMARY OF BIDS
PROJECT NO.: 8465 NO. OF ADDENDA: 1 DATE/TIME: MAY 25, 2021/12:00 PM
PROJECT NAME: WALNUT CREEK SEWER RENOVATIONS, PHASE 15
PROJECT MANAGER: DAMASIO ZEPEDA ARAGON
PROJECT LOCATION: CENTRAL SAN SERVICE AREA
ENGINEER'S ESTIMATE: $4,000,000
NO. BIDDER BID PRICE
Basset Engineering $3,117,488
San Francisco, California
2 California Trenchless, Inc. $3,219,355*
Hayward, California
3 K.J. Woods Construction, Inc. $3,238,000
San Francisco, California
4 Cratus, Inc. $3,312,088
San Francisco, California
5 Precision Engineering, Inc. $3,612,450
San Francisco, California
6 Andes Construction, Inc. $4,375,015
Oakland, California
7 Ranger Pipelines, Inc. $4,698,191
San Francisco, California
*Upon bid evaluation, staff corrected the bid provided by California Trenchless, Inc.
from $3,181,855 to $3,219,355 based on arithmetic discrepancies. Per the project bid
specifications, Central San can recalculate the total bid based on the resolution of any
arithmetic discrepancy. The lowest bid is determined after any required recalculations.
BIDS OPENED BY /s/ Katie Young
DATE: May 25, 2021 at 1:00 p.m. via livestream due to COVID-19
June 1, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 7 of 10
Page 6 of 6
ATTACHMENT 3
WALNUT CREEK SEWER RENOVATIONS, PHASE 15
DISTRICT PROJECT 8465
POST-BID/PRECONSTRUCTION ESTIMATE
% Of
Item Description Amounts Construction
No. Cost
1. CONSTRUCTION
a. Construction Contract $3,117,488
b. 15% Contingency $467,512
c. Permits $55,000
SUBTOTAL- CONSTRUCTION COST $3,640,000 100%
2. CONSTRUCTION MANAGEMENT
a. District Forces
- Construction Management (Engineering, Survey) $190,000
- Public Relations/Right-of-Way $20,000
- Operations (Collection System Operations) $30,000
b. Consultants
- Inspection $180,000
- Material Testing/Arborist/Others $40,000
SUBTOTAL - CONSTRUCTION MANAGEMENT $460,000 13%
3. PREBID EXPENDITURES
a. Engineering (Design, Survey, Right-of-Way, Drafting) $580,000
SUBTOTAL - PREBID EXPENDITURES $580,000 16%
4. TOTAL ESTIMATED PROJECT COST $4,680,000
June 1, 2021 EOPS Regular Committee Meeting Agenda Packet- Page 8 of 10