HomeMy WebLinkAbout16. Continuation of immediate sewer replacement at El Toyonal in Orinda Page 1 of 2
Item 16.
Algi
CENTRAL SAN BOARD OF DIRECTORS
WE VS.101 M POSITION PAPER
MEETING DATE: MARCH 18, 2021
SUBJECT: CONTINUATION OF IMMEDIATE SEWER REPLACEMENTAT EL TOYONAL
IN ORINDA
SUBMITTED BY: INITIATING DEPARTMENT:
EDGAR J. LOPEZ, CAPITAL PROJECTS ENGINEERING AND TECHNICAL SERVICES-
DIVISION MANAGER CAPITAL PROJECTS
REVIEWED BY: JEAN-MARC PETIT, DIRECTOR OF ENGINEERING AND TECHNICAL
SERVICES
Roger S. Bailey
General Manager
ISSUE
On February 18, 2021, the Board adopted Resolution No. 2021-014 proclaiming it was in the best public
interest for Central San to immediately replace the subject sewer prior to final paving of the public roadway
in Orinda. It is a statutory requirement that in such a case that the declaration shall confirm every 30 days
until the work is deemed complete.
BACKGROUND
The existing sewer located within the public right-of-way along EI Toyonal Road in the City of Orinda (City)
requires immediate replacement. This sewer is a 6-inch diameter clay pipe, is approximately 1,400 lineal
feet, and was originally installed in 1950.
It has come to the attention of the Collection System Operations Department (CSOD) and Capital
Projects that the East Bay Municipal Utility District (EBMUD) hired a contractor, Teichert Construction
(Teichert), to install two water mains on EI Toyonal. EBMUD's project plans to re-pave EI Toyonal in April
of this year. During the work performed by Teichert, several sections of Central San's sewer were
exposed and inspected by CSOD. The condition of the sewer is deficient and replacement before
EBMUD's paving was recommended by staff and authorized by the Board on February 18, 2021.
March 18, 2021 Regular Board Meeting Agenda Packet- Page 339 of 340
Page 2 of 2
Competitive pricing was received, and the Collection System Program has the adequate funding for the
subject work. Since Board approval, staff has entered into contract with the general contractor, Pacific
Trenchless, Inc., and has ordered and received the majority of materials, piping, and manhole structures
needed. Construction has commenced with completion estimated in April of this year, prior to re-paving of
the road.
ALTERNATIVES/CONSIDERATIONS
No feasible alternatives.
FINANCIAL IMPACTS
The total estimated cost for this contingency project is $450,000, which includes design, contractor
construction costs, permits, construction management, and contingency.
COMMITTEE RECOMMENDATION
This matter was not reviewed by a Board Committee.
RECOMMENDED BOARD ACTION
Confirm by motion that the action proclaimed on February 18, 2021 continues to exist, and that
expenditures to address the sewer replacement are continuing.
Strategic Plan Tie-In
GOAL ONE: Customer and Community
Strategy 1—Deliver high-quality customer service, Strategy 2—Maintain a positive reputation
GOAL TWO: Environmental Stewardship
Strategy 1—Achieve 100% compliance in all regulations
GOAL FOUR: Workforce Development
Strategy 4—Meet or exceed industry safety standards
GOAL FIVE:Infrastructure Reliability
Strategy 2—Execute long-term capital renewal and replacement program, Strategy 3—Protect personnel and assets
from threats and emergencies
GOAL SEVEN:Agility and A daptability
Strategy 1—Maintain a safe working environment for employees and the public during the COVID-19 pandemic
March 18, 2021 Regular Board Meeting Agenda Packet- Page 340 of 340
Item 16.
(Handout)
�1
EL TOYONAL SEWER REPLACEMENT
I CONTINGENCY PROJECT
ONGOING
4_ Board Meeting
March 18, 2021
Edgar J. Lopez, P.E.
Capital Projects Division Manager
.d
LOCATION MAP
EI Toyonal Sewer Replacement
�o
A-
'> .
CENTRALSAN
1
NARROW ROADWAYS
AM Ill 3
CENTRALSAN
WORK COMPLETED TO DATE
• Contracted with Pacific Trenchless, Inc.
• Ordered and received materials, piping, etc.
• Coordinated with East Bay Municipal Utility District's
contractor and the City of Orinda.
• Notified the public and nearby residents.
• Completed USA, Call 811 Before You Dig.
• Began construction activities.
• New sewer to be installed prior to EI Toyonal paving,
anticipated in late April.
CENTRALSAN
I4
2
RECOMMENDED BOARD ACTION
Staff recommends the following:
• Confirm by motion that the action proclaimed on
February 18, 2021 continues to exist, and that
expenditures to address the sewer replacement are
continuing.
_ 5